7 floors · 60 apartments · 40,789 sq ft · built 2024 · class D7 · owner of record: 114 Atlantic Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 9 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 70 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 70 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 70 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 86 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 40,789 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 191 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 191 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | No current registration found |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. Agency page | Feb 21, 2028 in 487 days | No Cycle 10 report on record yet |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Aug 29, 2026 | Construction CLASS - 1 OBSERVED: ACTIVE SITE UPON INSPECTION REQUESTED A FTER HOUR VARIANCE PERMIT TO CP ALEX GONZALEZ AFTER HE MAKE A CALL I WAS NOTIFYED NO SUCH PERMIT WAS GET IN ADVANCE . #39558530N | Nov 10, 2026 PENDING | $2,500 |
| Jul 13, 2026 | Construction CLASS - 2 OBSERVED: FENCE ERECTED ON EXP 1,4 UPON INSPECTION NOTED IT NOT STRAIGHT LENNING INWARD AT EXPOSURE4, NOT UNIFORM PAINTED AND SOME FRAFITI AT EXPOSURE 4, CONTRARY TO BUILING CODE MAINTAING FENCE #39556498N | Sep 22, 2026 IN VIOLATION | $1,000 |
| Mar 16, 2026 | Construction CLASS - 2 AT THE TIME OF MY INSPECTION I OBSERVED THAT THE JOB SITE CONSTRUCTIONFENCE PERMIT HAD EXPIRED. #39551834K | May 27, 2027 DEFAULT | $6,250 |
| Dec 21, 2025 | Construction CLASS - 2 AT THE TIME OF MY INSPECTION OF A 7-STORY NEW BUILDING, CONSTRUCTION FENCING WAS OBSERVED AT EXPOSURES 1 AND 2. REVIEW OF RECORDS CONFIRMED THE FENCE PERMIT EXPIRED ON 12/20/2025. THIS CONDITION CREATES A HAZAR #39548430R | Mar 3, 2026 DEFAULT | $3,125 |
| Dec 21, 2025 | Unknown CLASS - 2 7 STORIES NB INACTIVE JOBSITE, WITH A BUILDING FOOTPRINT (SQ. FT.)8000,45 WALK JOBSITE PERIMETERS, KNOCK & CALLED OUT, I OBSERVED NO COMPETENT WATCH . AS PER BC 3303.7.7.6 A WATCHPERSON REQUIREMENTS OF SECTION #39548431Z | Mar 3, 2026 DEFAULT | $10,000 |
| Dec 21, 2025 | Unknown CLASS - 1 BC 3301.2: AT THE TIME OF MY INSPECTION OF A 7-STORY NEW BUILDING, THE PEDESTRIAN WALKWAY WAS OBSTRUCTED AND NOT MAINTAINED AT THE REQUIRED MINIMUM WIDTH OF FIVE FEET, CREATING A HAZARDOUS CONDITION FOR PEDESTR #39548432K | Mar 3, 2026 DEFAULT | $10,000 |
| Dec 19, 2025 | Construction CLASS - 2 OBSERVED CLOSED SITE WITH AN INSTALLED CONSTRUCTION FENCE AROUND THE PROPERTY FOR NEW 7-STORY BUILDING. UPON INSPECTION FROM WEATHER ADVISORY SWEEP, CONSTRUCTION FENCE GATE WAS NOT SECURED AS HIGH WIND SPEEDS S #39548101X | Feb 24, 2026 DEFAULT | $2,500 |
| Mar 27, 2025 | Unknown CLASS - 2 AT TIME OF INSPECTION, I OBSERVED ONE TREE AT EXPOSURE #4 WAS NOT PROTECTED AS PER CODE SECTION BC 3309.11. #39538442P | Oct 13, 2026 IN VIOLATION | $2,500 |
| Jan 29, 2025 | Construction CLASS - 2 AT THE TIME OF MY INSPECTION I OBSERVED THAT THE SIDEWALK SHED INSTALLED DID NOT HAVE ANY INFORMATION PANEL INSTALLED AND THERE WERE UNCAPPED BOLTS IN THE WALK WAY UNDER THE SIDE WALK SHED. #39536400H | Oct 5, 2026 IN VIOLATION | $2,400 |
| Jul 29, 2024 | Construction CLASS - 1 AT TIME OF MY INSPECTION I OBSERVED 1 STORY BUILDING BEEN DEMOLISHED; SEARCH OF DOB RECORDS SHOW NO NOTIFICATION AS REQUIRED.APPLICANT FAILS TO GIVE NOTICE 24-48 HOURS BEFORE COMMENCEMENT OF DEMOLITION.COMPLY W #39530889P | Oct 8, 2024 DEFAULT | $6,250 |
| Jul 29, 2024 | Construction CLASS - 1 AT TIME OF MY INSPECTION I OBSERVED 1 STORY BUILDING BEEN DEMOLISHED; SEARCH OF DOB RECORDS SHOW NO NOTIFICATION AS REQUIRED.APPLICANT FAILS TO GIVE NOTICE 24-48 HOURS BEFORE COMMENCEMENT OF DEMOLITION.COMPLY W #39530894J | Oct 8, 2024 DEFAULT | $6,250 |
| Jul 29, 2024 | Construction CLASS - 1 AT TIME OF MY INSPECTION I OBSERVED 1 STORY BUILDING BEEN DEMOLISHED; SEARCH OF DOB RECORDS SHOW NO NOTIFICATION AS REQUIRED.APPLICANT FAILS TO GIVE NOTICE 24-48 HOURS BEFORE COMMENCEMENT OF DEMOLITION.COMPLY W #39530892X | Oct 8, 2024 DEFAULT | $6,250 |
| Jun 30, 2023 | Construction CLASS - 1 FAILURE TO MAINTAIN BLDG IN A CODE COMPLIANT MANNER.PREMISES IS A YARDWITH NUMEROUS STORAGE AS SCAFFOLDING PRESENT AT VARIOUS LOCATIONS SCAFFOLDINGS/EQUIPMENT STACKED VERY HIGH TO PROTRUDE ABOVE LEGAL 8 FENCE.S #35667678R | Sep 15, 2023 IN VIOLATION | $625 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Oct 14, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Sep 25, 2026 | Benchmarking - LL84 DQ-EN-BENCH FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 | Active |
| Mar 17, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 14, 2026 | DOB Safety | AEUHAZ: | Open |
| Sep 25, 2026 | DOB Safety | Benchmarking - LL84: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 | Open |
| Aug 29, 2026 | ECB | Construction: OBSERVED: ACTIVE SITE UPON INSPECTION REQUESTED A FTER HOUR VARIANCE PERMIT TO CP ALEX GONZALEZ AFTER HE MAKE A CALL I WAS NOTIFYED NO SUCH PERMIT WAS GET IN ADVANCE . | Open |
| Jul 13, 2026 | ECB | Construction: OBSERVED: FENCE ERECTED ON EXP 1,4 UPON INSPECTION NOTED IT NOT STRAIGHT LENNING INWARD AT EXPOSURE4, NOT UNIFORM PAINTED AND SOME FRAFITI AT EXPOSURE 4, CONTRARY TO BUILING CODE MAINTAING FENCE | Closed |
| Jul 13, 2026 | ECB | Construction: OBSERVED: HOUSEKEEPING ISSUES OBSERVED AT EXP 2 BACK YARD LIKE SHETROC, WOOD, METAL AND PLASTIC BAGS BROKEN CONCRETE IN PLASTIC 5 GALONS CONTAINERS CONTRARY TO BUILDING CODE MAINTAIN CHOPUSEKEEPING | Closed |