Bronx · Block 2709 · Lot 1 · 10459

991 Longwood Avenue

3.75 floors · 36,700 sq ft · built 1995 · class P3 · owner of record: Nyc Department Of Citywide Administrative Services

27open violations
$0ECB/OATH penalties owed
0HPD class C (immediately hazardous)
45dto Annual boiler inspection (1 boiler)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 45 days
Keep the report on file (not filed with DOB)
Annual boiler inspection (1 boiler) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2021-08-25 (Accepted). Agency page

Dec 31, 2026
in 45 days
1 of 1 without an accepted 2026 report yet
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 36,700 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 166 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 166 days
Annual filing
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1141 days
Next cycle year 2029

Open violations

ECB / OATH (16)
IssuedViolationHearingBalance
Jul 22, 2026Construction CLASS - 2
REISSUE#35692530P FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:INTERIOR FPSC DOORS DO NOT SELF-CLOSE PROPERLY WHEN TESTED AT 1ST FLR-STAIRCASE C,2ND FLR STAFF BATHROOM.CLASSROOM DOORS DO NOT SELF
#35734384Z
Aug 21, 2026
POP/IN-VIO
$0
Jul 22, 2026Construction CLASS - 2
REISSUE#35692391M FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED AT THE TIME OF INSPECTION OBSERVED AT ROOF,THERE ARE AIR POCKETS THROUGHOUT THE ENTIRE ROOF CREATING WATER PENETRATIONS.REM:REPAIR A
#35734385K
Aug 21, 2026
POP/IN-VIO
$0
Jul 22, 2026Construction CLASS - 2
FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.USE OF PROHIBITED DOOR AND/OR HARDWARE PER BC 1008.1.8;27-371(J).NOTED:OBSERVED PROHIBITED HARDWARE(KICK-STOPS)INSTALLED ON FPSC DOORS AT 2ND FLR-STAIRCASE
#35734387Y
Aug 21, 2026
POP/IN-VIO
$0
Jul 22, 2026Construction CLASS - 2
REISSUE#35692373K EXIT DOOR NOT SELF-CLOSING.NOTED:EXTERIOR EXIT DOORSDO NOT SELF-CLOSE PROPERLY AT 1ST FLR STAIRCASE A EXIT.BASEMENT-CAFETERIA EXIT.REM:REPAIR/REPLACE DOOR.
#35734386M
Aug 21, 2026
POP/IN-VIO
$0
Aug 27, 2025Construction CLASS - 2
FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: NO FIRESTOPPINGPER BC 712.3; 27-345. NOTED: DURING INSPECTION OBSERVED FIRESTOPPING WAS MISSING IN A FEW SPOTS IN ELECTRICAL ROOM. REMEDY: PROVIDE/MAINTAIN
#35693545M
Sep 12, 2025
POP/IN-VIO
$0
Aug 27, 2025Construction CLASS - 2
FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: USE OF PROHIBITED DOOR AND/OR HARDWARE PER BC 1008.1.8; 27-371(J). NOTED: DURING INSPECTION, OBSERVED KICK STOP ON RM "302" DOOR. REMEDY: PROVIDE LEGAL HAR
#35693544K
Sep 12, 2025
POP/IN-VIO
$0
Aug 27, 2025Construction CLASS - 2
REISSUE #35692373K. EXIT DOOR NOT SELF-CLOSING. NOTED: AT 1 FLOOR EXITA AT STAIR C AND FOX STREET, CAFETERIA EXITS ARE NOT CLOSING CORRECTLY. REMEDY: REPAIR AND/OR REPLACE DOORS.
#35693543Z
Sep 12, 2025
POP/IN-VIO
$0
Aug 27, 2025Construction CLASS - 2
RE-ISSUE #35692530P. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: AT 3RD FLOOR PADIO DOORS, STAIR(A), 3RD FLR-304. 1ST FLR-110, 109 DOORS DO NOT SELF-CLOSE PROPERLY. REMEDY: REPAIR AND/OR REPLA
#35693541P
Sep 12, 2025
POP/IN-VIO
$0
Aug 27, 2025Construction CLASS - 2
REISSUE #35692374M. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: AT ROOF AIR POCKETS THROUGHOUT CAUSING WATER PENETRATION AT CEILING OF YOUTH ROOM. REMEDY: REPAIR AND/OR REPLACE ROOF MATERIAL.
#35693542R
Sep 12, 2025
POP/IN-VIO
$0
Nov 4, 2024Construction CLASS - 2
REISSUE #35672332X. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: AT ROOF AIR POCKETS THROUGHOUT CAUSING WATERPENETRATION ATCEILINGS AT YOUTH LINK ROOM, MAIN ENTRANCE LOBBY, GYM. REMEDY: REPAIR
#35692374M
Dec 6, 2024
POP/IN-VIO
$0
Nov 4, 2024Construction CLASS - 2
FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: AT 3 FLOOR PADIO DOORS, STAIR A, 2FL. STAIR A, MENS RM, GAME RM, 1FL. 109, GYMENTRANCE AND BACK, STAIR A, BASE 017 AND STAIR A DOORS ARE NOT CLOSING
#35692530P
Dec 6, 2024
POP/IN-VIO
$0
Nov 4, 2024Construction CLASS - 2
REISSUE #35672333H. EXIT DOOR NOT SELF-CLOSING. NOTED: AT 1 FLOOR EXITA AT STAIR C AMD FOX STREET ARE NOT CLOSING CORRECTLY. REMEDY: REPAIR/REPLACE DOOR.
#35692373K
Dec 6, 2024
POP/IN-VIO
$0
Jul 13, 2023Construction CLASS - 2
EXIT DOOR NOT SELF-CLOSING. NOTED: AT CELLAR CAFETERIA EXIT DOOR AND FOX STREET SIDE EXIT DOORS DO NOT CLOSE PROPERLY. REMEDY: REPAIR/REPLACE DOOR
#35672333H
Sep 22, 2023
POP/IN-VIO
$0
Jul 13, 2023Construction CLASS - 2
FAILURE TO MAINTIAN BUILDING IN CODE-COMPLIANT MANNER. NOTED: AT ROOFTOP, AIRPOCKETS OBSERVED THROUGHOUT THR ROOF. REMEDY: MAKE NECESSARY REPAIRS
#35672332X
Sep 22, 2023
POP/IN-VIO
$0
Jul 19, 2021Construction CLASS - 2
REISSUED#35500755R.FAILURE TO MAINTAIN BUILDLING IN CODE COMPLIANT MANNER.NOTED:AT CELLAR LEVEL ROOM#011 AND 010 DOORS ARE NOT CLOSING PROPERLY DUET DEFECTIVE HANDWARE.REMEDY:REPAIR AND/OR REPLACE.
#35582376Z
Nov 5, 2021
POP/IN-VIO
$0
Aug 9, 2019Construction CLASS - 2
REISSUE #35335109X NOTED: @MAIN ENTRANCE TO THE BUILDING GYMNASIUM; ANEXITS CAFETERIA EXTERIOR EXIT DOOR & BASEMENT LVL STAIR A, EXIT DOORS ARE NOT WORKING PROPERLY. REM; REPAIR/REPLACE DOOR.
#354442799
Nov 1, 2019
POP/IN-VIO
$0
DOB (5)
IssuedViolationStatus
Sep 23, 2024LOW PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION
#07052
DOB VIOLATION - ACTIVE
Jun 30, 2023LOW PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION
#10115
DOB VIOLATION - ACTIVE
Jun 20, 2023LOW PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION
#43316
DOB VIOLATION - ACTIVE
Apr 25, 2023LOW PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION
#09889
DOB VIOLATION - ACTIVE
Jan 13, 1997LOCAL LAW 10/81 - ELEVATOR

#02038
DOB VIOLATION - ACTIVE
DOB NOW Safety (6)
IssuedViolationStatus
Oct 10, 2025Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction
Active
Sep 18, 2025Gas Piping - LL152 FTF-PL-PER
Cycle 1, Sub-cycle B (premises is in Community District 2)
Active
Sep 23, 2024Boiler LBLVIO
Violation Issued-Failure To File 2023 External Low Pressure Inspection Report
Active
Jun 30, 2023Boiler LBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION
Active
Jun 20, 2023Boiler LBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION
Active
Apr 25, 2023Boiler LBLVIO
VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT
Active
HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Jul 22, 2026ECBConstruction: REISSUE#35692530P FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:INTERIOR FPSC DOORS DO NOT SELF-CLOSE PROPERLY WHEN TESTED AT 1ST FLR-STAIRCASE C,2ND FLR STAFF BATHROOM.CLASSROOM DOORS DO NOT SELFOpen
Jul 22, 2026ECBConstruction: REISSUE#35692391M FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED AT THE TIME OF INSPECTION OBSERVED AT ROOF,THERE ARE AIR POCKETS THROUGHOUT THE ENTIRE ROOF CREATING WATER PENETRATIONS.REM:REPAIR AOpen
Jul 22, 2026ECBConstruction: FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.USE OF PROHIBITED DOOR AND/OR HARDWARE PER BC 1008.1.8;27-371(J).NOTED:OBSERVED PROHIBITED HARDWARE(KICK-STOPS)INSTALLED ON FPSC DOORS AT 2ND FLR-STAIRCASEOpen
Jul 22, 2026ECBConstruction: REISSUE#35692373K EXIT DOOR NOT SELF-CLOSING.NOTED:EXTERIOR EXIT DOORSDO NOT SELF-CLOSE PROPERLY AT 1ST FLR STAIRCASE A EXIT.BASEMENT-CAFETERIA EXIT.REM:REPAIR/REPLACE DOOR.Open

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 16, 2026, 11:38 AM ET. BBL 2027090001.