| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 70 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 54,500 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 191 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 191 days | Annual filing |
| Energy audit and retro-commissioning (2027) Likely applies Local Law 87 · Calendar year 2027 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 2787). Agency page | Dec 31, 2027 in 435 days | Next due 2027 |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 801 days | Next cycle year 2028 |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-08-04 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jun 5, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT THE TIME OF INSPECTION OBSERVED AND NOTED EXIT DOOR/FPSC DOORS NOT SELF CLOSING PROPERLY FOR HARDWARE(DIFECTIVE),DOOR CLOSURE OR HINGES AT 2ND FL.STAIRWA #35732040X | Jul 15, 2026 POP/IN-VIO | $0 |
| Jun 5, 2026 | Construction CLASS - 2 REISSUE#35717460R DATE OF ISSUE:04.17.2025 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.ILLUMINATION FOR EXITS,EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1;27-381.AT THE TIME OF INSPECTION OBSERV #35734102L | Jul 15, 2026 POP/IN-VIO | $0 |
| Jun 5, 2026 | Construction CLASS - 2 REISSUE#35717459J DATE OF ISSUE:04.17.2025 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT THE TIME OF INSPECTION OBSERVED AND NOTED LANDING ARE BETWEEN 3RD AND 4TH FLOOR STAIR A AND BETWEEN 3RD AND 2N #35734103N | Jul 15, 2026 POP/IN-VIO | $0 |
| Jun 5, 2026 | Construction CLASS - 2 REISSUE:35717457X DATE OF ISSUE:04.17.2025 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT THE TIME OF INSPECTION OBSERVED AND NOTED AT JUNGLE GYM(OUTSIDE)OR PLAY AREA RUBBER FLOOR MATS HAVE SEVERAL LA #35732039Z | Jul 15, 2026 POP/IN-VIO | $0 |
| Jun 5, 2026 | Construction CLASS - 2 REISSUE#35717458H DATE OF ISSUE:04.17.2025 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NO FIRESTOPPING PER BC 712.3;27-345 AT THE TIME OF INSPECTION OBSERVED AND NOTED AT BASEMENT LEVEL ELECTRICAL ROO #35734104P | Jul 15, 2026 POP/IN-VIO | $0 |
| Apr 17, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. ILLUMINATION FOR EXITS, EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1; 27-381. AT THE TIME OF INSPECTION OBSERVED AND NOTED. THAT AT 5TH FL NEAR RM-55 #35717460R | May 27, 2025 POP/IN-VIO | $0 |
| Apr 17, 2025 | Construction CLASS - 2 REISSUE #35651085P DATE OF ISSUE: 04-08-2025. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER AT THE TIME OF INSPECTION OBSERVED AND NOTED AT OUTSIDE LARGE GAPS AND SOME TOWARDS THE BACK AREA HAVE LIFTED #35717457X | May 27, 2025 POP/IN-VIO | $0 |
| Apr 17, 2025 | Construction CLASS - 2 REISSUE #35651084N DATE OF ISSUE #35651084N. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER NO FIRE STOPPING PER BC 712.3; 27-345. ATTHE TIME OF INSPECTION NOTED AND OBSERVED AT BASEMENT AT ELECTRICAL RO #35717458H | May 27, 2025 POP/IN-VIO | $0 |
| Apr 17, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION OBSERVED AND NOTED LANDING AREA BETWEEN 3RD AND 4TH FL AT STAIR "A" ONE STAIR PANEL IS MISSING(GLASS PANEL). PLACE IS UNSAFE COND #35717459J | May 27, 2025 POP/IN-VIO | $0 |
| Apr 8, 2022 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED:OBSERVED AT JUNGLE GYM RUBBER FLOOR MATS HAVE SEVERAL LARGE GAPS & SOME TOWARDS THE BACK AREA HAVE LIFTED UP SEVERAL INCHES CAUSING TRIPPING HAZARD.RE #35651085P | Sep 21, 2022 POP/IN-VIO | $0 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 1) | Active |
None open.