5 floors · 9 apartments · 9,321 sq ft · built 1940 · class C7 · owner of record: Columbus Equities, Inc.
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 51 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 51 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 67 days | Annual |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 295 days | Registered through 2027-09-01 |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1147 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jun 24, 2026 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. LACK OF REQUIRED NUMBER OF MEANS OF EGRESS FOR EVERY FLOOR PER BC 1018.1; 27-366; 1021 BC 1006.3 AT CELLAR LEVEL. REMEDY: DISCONTINUE ILLEGAL USE. #35728035J | Mar 18, 2027 PENDING | $2,500 |
| Jun 24, 2026 | Construction CLASS - 1 WORK WITHOUT A PERMIT. NOTED AT UNIT 1A INSTALLED A SPIRAL STAIRCASE FROM FIRST FLOOR OF UNIT 1A TO CELLAR LEVEL NAD INSTALL FULL HEIGHT PARTITION WALLS TO CREATE TWO SLEEPING QUARTERS/BEDROOMS. REMEDY: OBTAIN #35728037N | Mar 18, 2027 PENDING | $2,500 |
| Jun 24, 2026 | Construction CLASS - 1 OCCUPANCY CONTRARY TO THE ALLOWED BY DEPT NUILDING RECORDS. NOTED AT UNIT 1A CELLAR LEVEL HAS BEEN CONVERTED USED AS SLEEPING QUARTERS HAVE 2 BEDROOMS WITH 2 PEOPLE C OF O HAS BEEN CONVERTED/USED AS SLEEPING QU #35728034H | Mar 18, 2027 PENDING | $2,500 |
| Issued | Violation | Status |
|---|---|---|
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #35308 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #15053 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #36311 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #15583 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #07202 | DOB VIOLATION - ACTIVE |
| Nov 8, 2019 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT #03228 | DOB VIOLATION - ACTIVE |
| Apr 6, 2018 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT #04520 | DOB VIOLATION - ACTIVE |
| Jan 31, 2005 | LOCAL LAW 62/91 - BOILERS #05834 | DOB VIOLATION - ACTIVE |
| Feb 13, 2004 | LOCAL LAW 62/91 - BOILERS #05943 | DOB VIOLATION - ACTIVE |
| Mar 19, 2003 | LOCAL LAW 62/91 - BOILERS #05930 | DOB VIOLATION - ACTIVE |
| Mar 26, 2002 | LOCAL LAW 62/91 - BOILERS #06313 | DOB VIOLATION - ACTIVE |
| Feb 27, 2001 | LOCAL LAW 62/91 - BOILERS #06129 | DOB VIOLATION - ACTIVE |
| Feb 7, 2000 | LOCAL LAW 62/91 - BOILERS #06311 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
| Nov 8, 2019 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT | Active |
| Apr 6, 2018 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT | Active |
| Jan 31, 2005 | Boiler LL6291 | Active |
| Feb 13, 2004 | Boiler LL6291 | Active |
| Mar 19, 2003 | Boiler LL6291 | Active |
| Mar 26, 2002 | Boiler LL6291 | Active |
| Feb 27, 2001 | Boiler LL6291 | Active |
| Feb 7, 2000 | Boiler LL6291 | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Aug 31, 2026 | A | Apt 5A · § 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... LESS THAN 10SQFT AT CEILING IN THE BATHROOM LOCATED AT APT 5A, 5th STORY, 1st APARTMENT FROM NORTH AT EAST | Dec 4, 2026 |
| Aug 31, 2026 | C | Apt 5A · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF MICE IN THE ENTIRE APARTMENT LOCATED AT APT 5A, 5th STORY, 1st APARTMENT FROM NORTH AT EAST | Sep 26, 2026 |
| Aug 31, 2026 | B | Apt 5A · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR CEILING IN THE BATHROOM LOCATED AT APT 5A, 5th STORY, 1st APARTMENT FROM NORTH AT EAST | Oct 5, 2026 |
| Date | Source | What | Now |
|---|---|---|---|
| Aug 31, 2026 | HPD A | § 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... LESS THAN 10SQFT AT CEILING IN THE BATHROOM LOCATED AT APT 5A, 5th STORY, 1st APARTMENT FROM NORTH AT EAST | Open |
| Aug 31, 2026 | HPD C | HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF MICE IN THE ENTIRE APARTMENT LOCATED AT APT 5A, 5th STORY, 1st APARTMENT FROM NORTH AT EAST | Open |
| Aug 31, 2026 | HPD B | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR CEILING IN THE BATHROOM LOCATED AT APT 5A, 5th STORY, 1st APARTMENT FROM NORTH AT EAST | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 10, 2026, 7:51 AM ET. BBL 1018430064.