6 floors · 37 apartments · 38,934 sq ft · built 1934 · class D7 · owner of record: East 53rd L.L.C.
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 64 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 64 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 64 days | Annual |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-06-24 (Accepted). Agency page | Dec 31, 2026 in 64 days | 1 of 1 without an accepted 2026 report yet |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 80 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 38,934 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 185 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 185 days | Annual filing |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Dec 9, 2022 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9A REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#904708.REMEDY:SUBMIT ACCEPTABLE REQUIRE #37025190L | Mar 23, 2023 ADMIT/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2022 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022 #00444 | DOB VIOLATION - ACTIVE |
| Dec 13, 2021 | PLUMBING I OBSERVED NO SPRINKLER SYSTEM FOR LAUNDRY ROOM AREA WITH SEVERAL COMMERCIAL GAS DRYERS. YOU ARE HEAR BY ORDERED TO IMMEDIATELY CORRECT THE ABOVE CONDITIONS BY RETAINING A LICENSE PROFESSIONAL TO PERFORM ALL WORK NECESSARY TO RESTORE THE NON-COMPLIANT CONDITION TO A CODE COMPLAINT STATE #21-01760 | DOB VIOLATION - ACTIVE |
| May 26, 2021 | PLUMBING COMMISSIONERS REQUEST FOR IMMEDIATE CORRECTIVE ACTION I OBSERVED GAS PIPING WITH FLEX HOSE FOR COMMERCIAL GAS DRYER CELLAR AND GAS FUTURE. OBSERVED CONDITION(S) DOES NOT COMPLY WITH SECTION 28-301.1OF THE B102 AND PRESENTS AN IMMINENT RISK TO PUBLIC SAFETY. CORRECT THE SITUATION WITHIN 48 HOURS #21-00532 | DOB VIOLATION - ACTIVE |
| Apr 29, 2021 | FAILURE TO POST ENERGY GRADE/SCORE FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3 #2001011 | DOB VIOLATION - ACTIVE |
| May 20, 2020 | ELEVATOR #9028/680298 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #02699 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Feb 22, 2022 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022 | Active |
| Apr 29, 2021 | Energy Grade - LL33 FTP-EN-EGRDEA | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 28, 2026, 5:47 AM ET. BBL 1013460023.