1 floors · 10,800 sq ft · built 1960 · class M1 · owner of record: Northeastern Conference Corp.Of 7th Day Adventists
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 61 days | Keep the report on file (not filed with DOB) |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 13 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1157 days | Next cycle year 2029 |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-10-21 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Feb 4, 2026 | Construction CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH DEPARTMENT OF BUILDING FOR SUMMONS 34958913L., FILE A CERTIFICATE OF CORRECTION #39175953R | Mar 30, 2027 DEFAULT | $3,125 |
| Feb 4, 2026 | Construction CLASS - 1 FAILURE TO OBTAIN PERMITS, COMPLY AND CERTIFY OF CORRECTION FOR SUMMONS 39155096N, WHICH REFERS TO SUMMONS 35204421K ISSUED ON 3/2/2017. FAILURE TO OBTAIN PERMITS FOR THE PERFORMANCE OF NEW REPLACEMENT OF GAS F #39175952P | Mar 30, 2027 DEFAULT | $25,000 |
| Jul 28, 2025 | Construction CLASS - 1 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN VIOLATION #35204421K, ISSUED ON 3/2/2017; TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01., COMPLY WITH COMMISSIONER'S ORDE #39155096N | Jul 20, 2027 DEFAULT | $12,500 |
| Jul 28, 2025 | Construction CLASS - 1 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN VIOLATION #34958913L, SERVED ON 6/20/2012; TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01., COMPLY WITH COMMISSIONER'S ORD #39155095L | Jul 20, 2027 DEFAULT | $6,250 |
| Jul 27, 2017 | Construction CLASS - 2 FAILURE TO COMPLY W/COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION W/DEPT OF BLDGS.NO COMPLIANCE RECORDED FOR VIOLATION #35204421KREM:FILE CERT OF CORRECTION. #37005147H | Mar 20, 2018 IN VIOLATION | $0 |
| Apr 29, 2017 | Construction CLASS - 2 ALTERED/CHANGED BLDG OCCUPIED W/O A VALID C OF O AS PER 28-118.3.1;28-118.3.2. NOTED: AT THE TIME OF INSPECTION,OBSERVED BLDG OCCUPIED AS A HOUSE OF WORSHIP MOST RECENT C OF O HAS EXP ON 12-1-98. C OF O#Q400551 #35245115N | Sep 5, 2017 DEFAULT | $0 |
| Mar 2, 2017 | Construction CLASS - 2 WORK WITHOUT PERMIT. TIME OF INSPECTION 12:10PM. AT TIME OF INSPECTION ON 1ST FLOOR BOILER ROOM I OBSERVED NEW GAS FIRED WATER HEATER. NO PERMIT ON DOB RECORD TO PERFORM THIS JOB. GAS LINE FOR HOT WATER HEARTE #35204421K | Jun 20, 2017 DEFAULT | $0 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Sep 18, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle B (premises is in Community District 13) | Active |
None open.