16 floors · 222 apartments · 246,521 sq ft · built 1962 · class D6 · owner of record: London Leasing Company Limited Partnersh Ip
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 4 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 70 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 70 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 70 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 86 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 246,521 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 191 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 191 days | Annual filing |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. DOB facade records for this building show $50,000 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2028 in 487 days | No Cycle 10 report on record yet |
| Energy audit and retro-commissioning (2028) Likely applies Local Law 87 · Calendar year 2028 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1918). Agency page | Dec 31, 2028 in 801 days | Next due 2028 |
| Annual boiler inspection (3 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-01-21 (Accepted). Agency page | On file | 2026 reports accepted |
None open.
| Issued | Violation | Status |
|---|---|---|
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #23657 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #41567 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #41566 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #11871 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #18418 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #21017 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #21018 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #42326 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #42327 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #22406 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #22407 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #20131 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #20132 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #01193 | DOB VIOLATION - ACTIVE |
| Nov 16, 2021 | ELEVATOR CEASE USE DUE TO FLOOD DAMAGE #21-01532 | DOB VIOLATION - ACTIVE |
| May 3, 2002 | CONSTRUCTION #STF03EC | DOB VIOLATION - ACTIVE |
| May 21, 1992 | BOILER #H97648-01 | VIOLATION UNSERVED ECB-ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Sep 23, 2026 | A | Apt 6L · § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE CERAMIC BASEBOARD TILES AT EAST WALL IN THE 3rd BATHROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Dec 27, 2026 |
| Sep 23, 2026 | A | Apt 6L · § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE REGROUT TILE AT SOUTH WALL IN THE BATHROOM LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Dec 27, 2026 |
| Sep 23, 2026 | B | Apt 6L · § 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... GREATER THEN 10SQ FT AT CEILING IN THE BATHROOM LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Oct 28, 2026 |
| Sep 23, 2026 | A | Apt 6L · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR ALL WALLS AND CEILING IN THE BATHROOM LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Dec 27, 2026 |
| Sep 23, 2026 | A | Apt 6L · § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK EAST WALL IN THE PRIVATE HALLWAY LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Dec 27, 2026 |
| Sep 23, 2026 | A | Apt 6L · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR EAST WALL IN THE PRIVATE HALLWAY LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Dec 27, 2026 |
| Sep 23, 2026 | B | Apt 6L · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR CEILING AND NORTH WALL IN THE 3rd ROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Oct 28, 2026 |
| Sep 23, 2026 | B | Apt 6L · § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK CEILING AND NORTH WALL IN THE 3rd ROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Oct 28, 2026 |
| Sep 23, 2026 | B | Apt 6L · § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK EAST AND SOUTH WALL IN THE 3rd BATHROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Oct 28, 2026 |
| Sep 23, 2026 | A | Apt 6L · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR NORTH WALL AT CLOSET IN THE FOYER LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Dec 27, 2026 |
| Sep 23, 2026 | A | Apt 6L · § 27-2005 ADM CODE PROPERLY SECURE THE LOOSE TOILET SEAT IN THE BATHROOM LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Dec 27, 2026 |
| Sep 23, 2026 | C | Apt 6L · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF MICE IN THE ENTIRE APARTMENT LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Oct 19, 2026 |
| Sep 23, 2026 | C | Apt 6L · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Oct 19, 2026 |
| Sep 23, 2026 | B | Apt 6L · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR EAST AND SOUTH WALL IN THE 3rd BATHROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Oct 28, 2026 |
| Aug 28, 2026 | B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE VINYL FLOOR TILES AT PUBLIC HALL AT CELLAR | Oct 2, 2026 |
| Aug 28, 2026 | B | Apt 1K · § 27-2010, 2011, 2012 ADM CODE REMOVE THE ACCUMULATION OF REFUSE AND/OR RUBBISH AND MAINTAIN IN A CLEAN CONDITION THE FLOOR AND STORM DRAIN IN THE TERRACE LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Oct 2, 2026 |
| Aug 24, 2026 | B | Apt 1K · § 27-2045(B)(1)(B) HMC, § 12-06, § 12-07, § 12-09 RCNY REPAIR, REPLACE OR PROVIDE AN APPROVED AND OPERATIONAL CARBON MONOXIDE DETECTING DEVICE, INSTALLED IN ACCORDANCE WITH APPLICABLE LAW AND RULES . DETECTOR DEFECTIVE IN THE ENTIRE APARTMENT LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NOR | Sep 28, 2026 |
| Aug 24, 2026 | A | Apt 1K · § 27-2011 ADM CODE CLEANSE TO THE SATISFACTION OF THIS DEPARTMENT THE FLOOR THROGHOUT IN THE ENTIRE APARTMENT LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Nov 27, 2026 |
| Aug 24, 2026 | A | Apt 1K · § 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... LESS THAN 10 SQUARE FEET OBSERVED AT CEILING IN THE 1st BATHROOM FROM EAST LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Nov 27, 2026 |
| Aug 24, 2026 | B | Apt 1K · § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK AT CEILING IN THE FOYER LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Sep 28, 2026 |
| Aug 24, 2026 | B | Apt 1K · § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK AT NORTH AND WEST WALLS IN THE ENTIRE APARTMENT LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Sep 28, 2026 |
| Aug 24, 2026 | B | Apt 1K · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR AT CEILING AND SOUTH WALL IN THE FOYER LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Sep 28, 2026 |
| Aug 24, 2026 | B | Apt 1K · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR AT CEILING IN THE 1st BATHROOM FROM EAST LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Sep 28, 2026 |
| Aug 21, 2026 | B | Apt 8D · 566 (B) 27-2021.4 HMC: ABATE THE NUISANCE CONSISTING OF PESTS. EVIDENCE OF SPIDERS IN THE ENTIRE APARTMENT LOCATED AT APT 8D, 8th STORY, 1st APARTMENT FROM NORTH AT EAST | Sep 25, 2026 |
| Aug 21, 2026 | C | Apt 8D · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 8D, 8th STORY, 1st APARTMENT FROM NORTH AT EAST | Sep 16, 2026 |
| Jul 10, 2026 | B | § 27-2033.3(E) CORRECT FAILURE TO MAINTAIN REQUIRED RECORDS REGARDING INTERNET CAPABLE TEMPERATURE REPORTING DEVICES AND SUBMIT SUCH RECORDS TO THE DEPARTMENT UPON REQUEST. DATA REQUESTED FOR THE PERIOD OF MAY 2026 | Aug 14, 2026 |
| Jul 10, 2026 | B | § 27-2033.3(E) CORRECT FAILURE TO MAINTAIN REQUIRED RECORDS REGARDING INTERNET CAPABLE TEMPERATURE REPORTING DEVICES AND SUBMIT SUCH RECORDS TO THE DEPARTMENT UPON REQUEST. DATA REQUESTED FOR THE PERIOD OF APRIL 2026 | Aug 14, 2026 |
| Jul 9, 2026 | A | Apt 16K · § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE WOOD ENTRANCE DOOR IN THE 2nd ROOM FROM NORTH LOCATED AT APT 16K, 15th STORY, 1st APARTMENT FROM SOUTH AT WEST | Oct 12, 2026 |
| Jul 9, 2026 | A | Apt 10A · § 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... LESS THAN 10 SQ.FT AT CEILING IN THE BATHROOM LOCATED AT APT 10A, 10th STORY, 3rd APARTMENT FROM SOUTH AT WEST | Dec 11, 2026 |
| Jul 9, 2026 | B | Apt 16K · § 27-2005 ADM CODE PROPERLY SECURE THE LOOSE CLOSET DOORS IN THE 1st ROOM FROM NORTH LOCATED AT APT 16K, 15th STORY, 1st APARTMENT FROM SOUTH AT WEST | Aug 13, 2026 |
| Jul 6, 2026 | C | Apt 9L · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 9L, 8th STORY, 7th APARTMENT FROM EAST AT SOUTH | Aug 1, 2026 |
| May 20, 2026 | B | § 27-2033.3(E) CORRECT FAILURE TO MAINTAIN REQUIRED RECORDS REGARDING INTERNET CAPABLE TEMPERATURE REPORTING DEVICES AND SUBMIT SUCH RECORDS TO THE DEPARTMENT UPON REQUEST. DATA REQUESTED FOR THE PERIOD OF MARCH 2026. | Jun 24, 2026 |
| Jan 8, 2026 | B | § 27-2033.3(E) CORRECT FAILURE TO MAINTAIN REQUIRED RECORDS REGARDING INTERNET CAPABLE TEMPERATURE REPORTING DEVICES AND SUBMIT SUCH RECORDS TO THE DEPARTMENT UPON REQUEST. DATA REQUESTED FOR THE PERIOD OF NOVEMBER 2025. | Feb 12, 2026 |
| Jan 8, 2026 | B | § 27-2033.3(E) CORRECT FAILURE TO MAINTAIN REQUIRED RECORDS REGARDING INTERNET CAPABLE TEMPERATURE REPORTING DEVICES AND SUBMIT SUCH RECORDS TO THE DEPARTMENT UPON REQUEST. DATA REQUESTED FOR THE PERIOD OF OCTOBER 2025. | Feb 12, 2026 |
| Apr 25, 2025 | C | Apt 11F · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 11F, 10th STORY, 4th APARTMENT FROM WEST AT NORTH | May 21, 2025 |
| Feb 20, 2025 | B | § 27-2033.3(E) CORRECT FAILURE TO MAINTAIN REQUIRED RECORDS REGARDING INTERNET CAPABLE TEMPERATURE REPORTING DEVICES AND SUBMIT SUCH RECORDS TO THE DEPARTMENT UPON REQUEST. DATA REQUESTED FOR THE PERIOD OF NOVEMBER 2024 | Mar 27, 2025 |
| Feb 20, 2025 | B | § 27-2033.3(E) CORRECT FAILURE TO MAINTAIN REQUIRED RECORDS REGARDING INTERNET CAPABLE TEMPERATURE REPORTING DEVICES AND SUBMIT SUCH RECORDS TO THE DEPARTMENT UPON REQUEST. DATA REQUESTED FOR THE PERIOD OF DECEMBER 2024 | Mar 27, 2025 |
| Feb 20, 2025 | B | § 27-2033.3(E) CORRECT FAILURE TO MAINTAIN REQUIRED RECORDS REGARDING INTERNET CAPABLE TEMPERATURE REPORTING DEVICES AND SUBMIT SUCH RECORDS TO THE DEPARTMENT UPON REQUEST. DATA REQUESTED FOR THE PERIOD OF JANUARY 2025 | Mar 27, 2025 |
| Feb 20, 2025 | B | § 27-2033.3(E) CORRECT FAILURE TO MAINTAIN REQUIRED RECORDS REGARDING INTERNET CAPABLE TEMPERATURE REPORTING DEVICES AND SUBMIT SUCH RECORDS TO THE DEPARTMENT UPON REQUEST. DATA REQUESTED FOR THE PERIOD OF OCTOBER 2024 | Mar 27, 2025 |
| Jan 9, 2025 | C | Apt 5H · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 5H, 4th STORY, 2nd APARTMENT FROM WEST AT NORTH | Feb 4, 2025 |
| Dec 9, 2024 | B | Apt 8D · §27-2033.3(B) CORRECT FAILURE TO INSTALL AN INTERNET CAPABLE TEMPERATURE REPORTING DEVICE IN ONE LIVING ROOM IN APARTMENT ... LOCATED AT APT 8D, 7th STORY, 1st APARTMENT FROM NORTH AT EAST | Jan 13, 2025 |
| Dec 5, 2024 | C | Apt 11L · § 27-2005, 27-2007, 27-2041.1 HMC, §238, § 309; § 107 (2) ( C) MDL AND 28 RCNY §25-171: REPLACE OR REPAIR THE SELF-CLOSING DOORS THAT IS MISSING OR DEFECTIVE LATCH SET IN THE ENTRANCE LOCATED AT APT 11L, 10th STORY, 7th APARTMENT FROM EAST AT SOUTH | Dec 19, 2024 |
| Dec 2, 2024 | B | Apt 11M · §27-2033.3(B) CORRECT FAILURE TO INSTALL AN INTERNET CAPABLE TEMPERATURE REPORTING DEVICE IN ONE LIVING ROOM IN APARTMENT ... LOCATED AT APT 11M, 10th STORY, 6th APARTMENT FROM EAST AT SOUTH | Jan 6, 2025 |
| Dec 2, 2024 | C | Apt 11M · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 11M, 10th STORY, 6th APARTMENT FROM EAST AT SOUTH | Dec 28, 2024 |
| Apr 26, 2024 | B | Apt 6H · §27-2033.3(B) CORRECT FAILURE TO INSTALL AN INTERNET CAPABLE TEMPERATURE REPORTING DEVICE IN ONE LIVING ROOM IN APARTMENT ... IN THE ENTIRE APARTMENT LOCATED AT APT 6H, 6th STORY, 2nd APARTMENT FROM WEST AT NORTH | May 31, 2024 |
| Mar 15, 2024 | B | Apt 4G · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR THE CEILING IN THE BATHROOM LOCATED AT APT 4G, 4th STORY, 3rd APARTMENT FROM NORTH AT EAST | Apr 19, 2024 |
| Mar 15, 2024 | B | Apt 4G · § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK AT CEILING IN THE BATHROOM LOCATED AT APT 4G, 4th STORY, 3rd APARTMENT FROM NORTH AT EAST | Apr 19, 2024 |
| May 15, 2023 | C | Apt 9L · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 9L, 8th STORY, 7th APARTMENT FROM SOUTH AT WEST | Jun 10, 2023 |
| May 2, 2023 | C | Apt 2H · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 2H, 1st STORY, 2nd APARTMENT FROM NORTH AT EAST | May 28, 2023 |
| Nov 15, 2022 | C | Apt 5A · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 5A, 4th STORY, 3rd APARTMENT FROM SOUTH AT WEST | Dec 11, 2022 |
| Nov 3, 2022 | B | Apt 4C · § 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... APPROXIMATELY 5 SQ FT AT CEILING IN THE 1st BATHROOM FROM NORTH LOCATED AT APT 4C, 3rd STORY, 1st APARTMENT FROM EAST AT SOUTH ORIGINAL VIOLATION 15357114 ISSUED 10-SEP-22 HAS BEEN UPGRADED TO CLASS B PER ADMINISTRA | Dec 8, 2022 |
| Sep 12, 2022 | C | Apt 18O · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 18O, 16th STORY, 4th APARTMENT FROM SOUTH AT WEST | Oct 8, 2022 |
| Jan 27, 2022 | C | Apt 2C · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF MICE IN THE ENTIRE APARTMENT LOCATED AT APT 2C, 1st STORY, 1st APARTMENT FROM EAST AT SOUTH | Feb 22, 2022 |
| Mar 19, 2021 | C | Apt 4E · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES LOCATED AT APT 4E, 3rd STORY, 5th APARTMENT FROM NORTH AT EAST | Apr 14, 2021 |
| Feb 22, 2021 | C | Apt 4L · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 4L, 3rd STORY, 4th APARTMENT FROM EAST AT SOUTH , SECTION AT WEST | Mar 20, 2021 |
| Nov 22, 2019 | B | Apt 5A · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR CEILING & ALL WALLS IN THE ENTIRE APARTMENT LOCATED AT APT 5A, 4th STORY, 3rd APARTMENT FROM SOUTH AT WEST | Dec 27, 2019 |
| Jul 26, 2019 | B | Apt 7M · § 27-2005 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE AT LOWER SASH WINDOW COUNTER BALANCE IN THE 1st LIVING ROOM FROM NORTH LOCATED AT APT 7M, 6th STORY | Aug 30, 2019 |
| Jul 26, 2019 | B | Apt 7M · § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE CEMENT LANDING AT BALCONY LOCATED AT APT 7M, 6th STORY | Aug 30, 2019 |
| Jul 25, 2019 | B | Apt 7M · § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE RUBBER GASKET SEAL AT OVEN DOOR. IN THE KITCHEN LOCATED AT APT 7M, 6th STORY, 6th APARTMENT FROM SOUTH AT WEST | Aug 29, 2019 |
| Jul 25, 2019 | A | Apt 7M · § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT AT CEILING IN THE KITCHEN LOCATED AT APT 7M, 6th STORY, 6th APARTMENT FROM SOUTH AT WEST | Oct 28, 2019 |
Showing 60 of 65. Full list on the agency site.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 23, 2026 | HPD A | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE CERAMIC BASEBOARD TILES AT EAST WALL IN THE 3rd BATHROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD A | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE REGROUT TILE AT SOUTH WALL IN THE BATHROOM LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD B | § 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... GREATER THEN 10SQ FT AT CEILING IN THE BATHROOM LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD A | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR ALL WALLS AND CEILING IN THE BATHROOM LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD A | § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK EAST WALL IN THE PRIVATE HALLWAY LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD A | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR EAST WALL IN THE PRIVATE HALLWAY LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD B | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR CEILING AND NORTH WALL IN THE 3rd ROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD B | § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK CEILING AND NORTH WALL IN THE 3rd ROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD B | § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK EAST AND SOUTH WALL IN THE 3rd BATHROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD A | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR NORTH WALL AT CLOSET IN THE FOYER LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD A | § 27-2005 ADM CODE PROPERLY SECURE THE LOOSE TOILET SEAT IN THE BATHROOM LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD C | HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF MICE IN THE ENTIRE APARTMENT LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD C | HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Sep 23, 2026 | HPD B | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR EAST AND SOUTH WALL IN THE 3rd BATHROOM FROM EAST LOCATED AT APT 6L, 6th STORY, 4th APARTMENT FROM EAST AT SOUTH | Open |
| Aug 28, 2026 | HPD B | § 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE VINYL FLOOR TILES AT PUBLIC HALL AT CELLAR | Open |
| Aug 28, 2026 | HPD B | § 27-2010, 2011, 2012 ADM CODE REMOVE THE ACCUMULATION OF REFUSE AND/OR RUBBISH AND MAINTAIN IN A CLEAN CONDITION THE FLOOR AND STORM DRAIN IN THE TERRACE LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Open |
| Aug 24, 2026 | HPD B | § 27-2045(B)(1)(B) HMC, § 12-06, § 12-07, § 12-09 RCNY REPAIR, REPLACE OR PROVIDE AN APPROVED AND OPERATIONAL CARBON MONOXIDE DETECTING DEVICE, INSTALLED IN ACCORDANCE WITH APPLICABLE LAW AND RULES . DETECTOR DEFECTIVE IN THE ENTIRE APARTMENT LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NOR | Open |
| Aug 24, 2026 | HPD A | § 27-2011 ADM CODE CLEANSE TO THE SATISFACTION OF THIS DEPARTMENT THE FLOOR THROGHOUT IN THE ENTIRE APARTMENT LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Open |
| Aug 24, 2026 | HPD A | § 27-2017.3 HMC: TRACE AND REPAIR THE SOURCE AND ABATE THE VISIBLE MOLD CONDITION... LESS THAN 10 SQUARE FEET OBSERVED AT CEILING IN THE 1st BATHROOM FROM EAST LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Open |
| Aug 24, 2026 | HPD B | § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK AT CEILING IN THE FOYER LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Open |
| Aug 24, 2026 | HPD B | § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK AT NORTH AND WEST WALLS IN THE ENTIRE APARTMENT LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Open |
| Aug 24, 2026 | HPD B | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR AT CEILING AND SOUTH WALL IN THE FOYER LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Open |
| Aug 24, 2026 | HPD B | § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR AT CEILING IN THE 1st BATHROOM FROM EAST LOCATED AT CELLAR APT 1K, 1st CELLAR APT FROM WEST AT NORTH | Open |
| Aug 21, 2026 | HPD B | 566 (B) 27-2021.4 HMC: ABATE THE NUISANCE CONSISTING OF PESTS. EVIDENCE OF SPIDERS IN THE ENTIRE APARTMENT LOCATED AT APT 8D, 8th STORY, 1st APARTMENT FROM NORTH AT EAST | Open |
| Aug 21, 2026 | HPD C | HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 8D, 8th STORY, 1st APARTMENT FROM NORTH AT EAST | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 22, 2026, 12:28 PM ET. BBL 4019180050.