Brooklyn · Block 6143 · Lot 1 · 11228

9216 7 Avenue

1 floors · 152,440 sq ft · built 2003 · class W3 · owner of record: Poly Prep Ctry Day Sc

10open violations
$0ECB/OATH penalties owed
0HPD class C (immediately hazardous)
67dto Annual boiler inspection (11 boilers)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 67 days
Keep the report on file (not filed with DOB)
Annual boiler inspection (11 boilers) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-08-26 (Accepted). Agency page

Dec 31, 2026
in 67 days
1 of 11 without an accepted 2026 report yet
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 152,440 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 188 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 188 days
Annual filing
Gas piping inspection (2028 cycle) Likely applies
Local Law 152 · During 2028
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 10 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2028
in 798 days
Next cycle year 2028
Energy audit and retro-commissioning (2033) Likely applies
Local Law 87 · Calendar year 2033
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 6143). Agency page

Dec 31, 2033
in 2624 days
Next due 2033

Open violations

ECB / OATH (2)
IssuedViolationHearingBalance
Jan 14, 2023Construction CLASS - 1
AT THE TIME OF MY INSPECTION I OBSERVED STRUCTURAL BEAMS INSTALLED APPROXIMATELY 8 FEET HIGHER THAN ADJACENT ROOF AT EXP#3 AND THERE WERE NO ROOF PROTECTION IN PLACE AS REQUIRE. FAILURE TO PROVIDE AND MAINTAIN
#39511661P
Mar 21, 2024
IN VIOLATION
$0
Jan 14, 2023Construction CLASS - 1
AT THE TIME OF MY INSPECTION CONSTRUCTION WORK IN PROGRESS I OBSERVED THAT ADJACENT PROPERTY WINDOWS AT EXP#2 WAS NOT PROVIDED WITH WINDOWS PROTECTION TO SAFEGUARD WINDOWS FROM HAZARDOUS DAMAGING CONDITION.STOP
#39511662R
Mar 21, 2024
IN VIOLATION
$0
DOB (1)
IssuedViolationStatus
Nov 14, 2025LOW PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
#15001
DOB VIOLATION - ACTIVE
DOB NOW Safety (7)
IssuedViolationStatus
Nov 14, 2025Boiler LBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
Active
Oct 10, 2025Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction
Active
Oct 10, 2025Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction
Active
HPD (0)

None open.

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)