| Requirement | Due | Status |
|---|---|---|
| Annual property registration Check HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 308 days | Required only if the owner doesn't live there |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 15, 2026 | Construction CLASS - 1 NOTED: VIOLATION ISSUED FOR UNLAWFUL CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER: ATOI OBSERVED IN THE RESIDENTS GARAGE WORK IS 100% COMPLETED SHEET ROCK WALLS AND CEILING ELECTRICAL CEILING LIGHTING . #39204128R | Nov 25, 2026 PENDING | $10,000 |
| Aug 25, 2026 | Unknown CLASS - 1 WORK WITHOUT PERMIT. PSWO ISSUED FOR ALL ELECTRICAL WORK BEING DONE ON THE INTERIOR AND EXTERIOR OF THE RESIDENT. ATOI OBSERVED AT 8 AM ON THE 1ST AND 2ND FLOOR IN THE INTERIOR AND EXTERIOR OF THE RESIDENT UNPE #39201683M | Nov 4, 2026 PENDING | $2,500 |
| Aug 25, 2026 | Construction CLASS - 1 NOTED: VIOLATION ISSUED FOR OCCUPANCY CONTRARY TO THAT ALLOWED BY THE CERTIFICATE OF OCCUPANCY AS PER SECTION OF LAW 28-118.3.2. ATOI OBSERVED AT EXPO # 2 THE GARAGE ATTACHED TO THE RESIDENT AT THE STREET LEVEL #39201684Y | Nov 4, 2026 PENDING | $2,500 |
| Aug 25, 2026 | Construction CLASS - 1 WORK WITHOUT PERMIT PSWO ISSUED FOR ALL GENERAL CONSTRUCTION, CARPENTRY STRUCTURAL WORK. ATOI OBSERVED IN THE RESIDENTS GARAGE AT EXPO # 4 NEWLY INSTALLED WOOD FRAMING SPRAY FOAMING ON THE WALLS AND CEILING SHE #39201682K | Nov 4, 2026 PENDING | $2,500 |
None open.
None open.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 15, 2026 | ECB | Construction: NOTED: VIOLATION ISSUED FOR UNLAWFUL CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER: ATOI OBSERVED IN THE RESIDENTS GARAGE WORK IS 100% COMPLETED SHEET ROCK WALLS AND CEILING ELECTRICAL CEILING LIGHTING . | Open |
| Aug 25, 2026 | ECB | Unknown: WORK WITHOUT PERMIT. PSWO ISSUED FOR ALL ELECTRICAL WORK BEING DONE ON THE INTERIOR AND EXTERIOR OF THE RESIDENT. ATOI OBSERVED AT 8 AM ON THE 1ST AND 2ND FLOOR IN THE INTERIOR AND EXTERIOR OF THE RESIDENT UNPE | Open |
| Aug 25, 2026 | ECB | Construction: NOTED: VIOLATION ISSUED FOR OCCUPANCY CONTRARY TO THAT ALLOWED BY THE CERTIFICATE OF OCCUPANCY AS PER SECTION OF LAW 28-118.3.2. ATOI OBSERVED AT EXPO # 2 THE GARAGE ATTACHED TO THE RESIDENT AT THE STREET LEVEL | Open |
| Aug 25, 2026 | ECB | Construction: WORK WITHOUT PERMIT PSWO ISSUED FOR ALL GENERAL CONSTRUCTION, CARPENTRY STRUCTURAL WORK. ATOI OBSERVED IN THE RESIDENTS GARAGE AT EXPO # 4 NEWLY INSTALLED WOOD FRAMING SPRAY FOAMING ON THE WALLS AND CEILING SHE | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)