Manhattan · Block 2149 · Lot 84 · 10033

90 Laurel Hill Terrace

6 floors · 86 apartments · 94,428 sq ft · built 1960 · class D1 · owner of record: Dy 90 Laurel Hill Llc

16open violations
$8,750ECB/OATH penalties owed
0HPD class C (immediately hazardous)
61dto Bedbug annual filing

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 61 days
Keep the report on file (not filed with DOB)
Bedbug annual filing Applies
Local Law 69 · December 1 to 31 each year
What this is

Owners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page

Dec 31, 2026
in 61 days
Annual
Annual notice: window guards and lead paint Applies
HPD / Health Code · January 1 to 16 each year
What this is

Deliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page

Jan 16, 2027
in 77 days
Annual
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 94,428 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 182 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 182 days
Annual filing
Annual property registration Applies
HPD registration · September 1 each year
What this is

Residential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page

Sep 1, 2027
in 305 days
Registered through 2027-09-01
Gas piping inspection (2027 cycle) Likely applies
Local Law 152 · During 2027
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 12 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2027
in 426 days
Next cycle year 2027
Energy audit and retro-commissioning (2029) Likely applies
Local Law 87 · Calendar year 2029
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 2149). Agency page

Dec 31, 2029
in 1157 days
Next due 2029
Annual boiler inspection (1 boiler) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-01-17 (Accepted). Agency page

On file2026 reports accepted

Open violations

ECB / OATH (3) · $8,750 owed
IssuedViolationHearingBalance
Sep 9, 2025Unknown CLASS - 2
FAILURE TO MAINTAIN PARKING STRUCTURE IN SAFE CONDITION. AS NOTED: AT TIME OF INSPECTION ON AN OCCUPIED PARKING STRUCTURE CONSISTING OF 1 LEVEL BELOW THE BUILGING. OBSERVED SOME CRACKS ON THE WALLS AND SOME BEA
#35718216J
Nov 13, 2025
DEFAULT
$6,250
Dec 2, 2022Local Law CLASS - 2
FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9A REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#916379.REM:SUBMIT ACCEPTABLE REQUIRED T
#37024358L
Nov 13, 2025
IN VIOLATION
$1,250
Nov 2, 2022Construction CLASS - 2
FAILURE TO MAINTAIN EXTERIOR OF BLDG FACADE&APPURTENANCES.NOTE:OBSERVED VERT CRACK IN BRICK MASONRY UNDER EACH WINDOW ON RIGHT SIDE OF LEFT SIDE OF EXP1.LONGITUDINAL CRACK (JOINT ONLY),STEP CRACK&VERT CRACK IN
#35669140Y
Nov 21, 2023
IN VIOLATION
$1,250
DOB (2)
IssuedViolationStatus
Feb 22, 2022NO REPORT AND / OR LATE FILING (FACADE)
FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022
#01907
DOB VIOLATION - ACTIVE
Jun 25, 2008ELEVATOR

#1P8242
DOB VIOLATION - ACTIVE
DOB NOW Safety (4)
IssuedViolationStatus
Oct 10, 2025Elevators FTC-VT-CAT1-NJ
Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction
Active
Oct 10, 2025Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction
Active
Oct 10, 2025Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction
Active
Feb 22, 2022Facades FISPNRF
FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022
Active
HPD (7) · C 0 · B 5 · A 2
IssuedClassViolationCorrect by
Feb 21, 2018B§ 27-2005 ADM CODE PROPERLY REPAIR WITH SIMILAR MATERIAL THE BROKEN OR DEFECTIVE BRICKWORK POINTING EAST & SOUTH WALLS NORTH ENTRANCE TO CELLAR NORTH YARD.Mar 28, 2018
Feb 21, 2018B§ 27-2005, 2007 ADM CODE ARRANGE AND MAKE SELF-CLOSING THE DOORS COMPACTOR CELLAR NORTH & SOUTH SECTIONS.Mar 28, 2018
Feb 21, 2018BApt 2A · § 27-2005, 2007 ADM CODE FIRE EGRESS DEFECTIVE. REMOVE OBSTRUCTING BARS OR UNLAWFUL GATES FROM WINDOW TO FIRE ESCAPE OR PROVIDE APPROVED TYPE GATE 2 STY EAST APT 2A SOUTH SECTION. LOCATED AT APT 2AMar 28, 2018
Feb 21, 2018BApt 2A · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR AT WALLS AND CEILING IN THE BATHROOM LOCATED AT APT 2A, 2nd STORY, 1st APARTMENT FROM NORTH AT EASTApr 11, 2008
Feb 21, 2018BApt 2A · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR AT WALLS AND CEILING IN THE BATHROOM LOCATED AT APT 2A, 2nd STORY, 1st APARTMENT FROM NORTH AT EASTApr 11, 2008
Feb 21, 2018AApt 2A · § 27-2005 ADM CODE REFIT WOOD DOOR IN THE 4th ROOM FROM EAST LOCATED AT APT 2A, 2nd STORY, 1st APARTMENT FROM NORTH AT EASTMay 27, 2018
Feb 21, 2018AApt 3K · § 300 M/D LAW FILE PLANS AND APPLICATION AND LEGALIZE THE FOLLOWING ALTERATION OR RESTORE TO THE LEGAL CONDITION EXISTING PRIOR TO THE MAKING OF SAID ALTERATION ****PARTITION WALL ERRECTED, CREATING ADDITIONAL ROOM.*** IN THE 1st ROOM FROM NORTH AT WEST LOCATED AT APT 3K, 3rd STORY, 2nd APARTMENT FRMay 27, 2018

Issued in the last 120 days

DateSourceWhatNow
Sep 23, 2026DOB SafetyParking Structures: Failure to file parking structures compliance report by 12/31/2025 as required per 1 RCNY 103-13Closed

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Oct 31, 2026, 6:39 PM ET. BBL 1021490084.