Brooklyn · Block 1976 · Lot 18 · 11238

899 Fulton Street

2 floors · 6,353 sq ft · built 1930 · class K2 · owner of record: Clinton Garden Partners Llc

1open violations
$28,550ECB/OATH penalties owed
0HPD class C (immediately hazardous)
1159dto Gas piping inspection (2029 cycle)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 63 days
Keep the report on file (not filed with DOB)
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1159 days
Next cycle year 2029

Open violations

ECB / OATH (7) · $28,550 owed
IssuedViolationHearingBalance
Apr 1, 2026Construction CLASS - 1
AT THE TIME OF MY INSPECTION OF A 6 STORY BUILDING, I OBSERVED 2 WORKERS INSTALLING ELEVATOR ON THE 6 FLOOR AND AT THE 1ST FLOOR ELEVATOR DOOR OPENING TO THE SHAFT WAS MISSING GUARDRAILS. FAILURE TO PROVIDE AND
#39552488L
Dec 1, 2026
$5,000
Apr 1, 2026Construction CLASS - 1
AT THE TIME OF MY INSPECTION, I OBSERVED FACADE INSTALLATION AT EXPOSURE #1&4 UPON REVIEW OF THE DEPARTMENT RECORD IT REVEAL THAT THERE IS A PARTIAL STOP WORK ORDER IN EFFECT, TO STOP ALL EXTERIOR WORK AT THE C
#39552486H
Dec 1, 2026
$10,000
Apr 1, 2026Construction CLASS - 2
AT THE TIME OF MY INSPECTION OF A 6 STORY BUILDING, I OBSERVED FACADE WORK IN OPERATION AND FOAM INSTALLATION AT EXPOSURE #1&4, LARGE AMOUNT FOAM PARTICLES WAS ON STREET, AT ADJACENT PROPERTY AND ALL OVER THE N
#39552487J
Dec 1, 2026
$5,000
Aug 9, 2025Construction CLASS - 2
PEDESTRIAN PROTECTION IS INADEQUATE AS PER CODE SPECIFICATION OBSERVED SIDEWALK SHED INSTALLED AT EXP#1 4 NOTE: SIDEWALK SHED AT EXP# 1 NOT EXTENDED 5FT AS REQUIRED PER CODE. STOP ALL EXTERIOR WORK 20FT EXP#1 C
#39543508P
Feb 4, 2027
$2,400
Jun 19, 2025Construction CLASS - 2
AT THE TIME OF MY INSPECTION I OBSERVED THE PEDESTRIAN PROTECTION WAS INADEQUATELY PROVIDED AS PER CODE SPECIFICATIONS. PEDESTRIANS USING SIDEWALK AND WALKWAYS WERE NOT ADEQUATELY PROTECTED FROM FALLING DEBRIS
#39541552N
Mar 5, 2026
IN VIOLATION
$2,400
Feb 4, 2025Construction CLASS - 2
AT TIME OF INSPECTION, I OBSERVED SHORING ON 1ST AND 2ND FLOOR FOR WHICH NO DESIGN DRAWING WERE PROVIDED UPON REQUEST. / STOP ALL STRUCTURAL WORK. ENTIRE SITE.
#39536637X
May 14, 2026
IN VIOLATION
$1,250
Nov 22, 2024Unknown CLASS - 2
MISC VIO. AT TIME OF INSPECTION OBSERVED DISLODGING AND MISSING BRICKS AT EXPOSURE#3 WALL. NO PROTECTION PROVIDED FOR EXPOSURE#3 WALL LEAVING AREA OPEN AND UNGUARDED. STOP ALL CONSTRUCTION OPERATIONS. ONLY ALLO
#39131141R
Aug 26, 2025
IN VIOLATION
$2,500
DOB (0)

None open.

DOB NOW Safety (1)
IssuedViolationStatus
Sep 18, 2025Gas Piping - LL152 FTF-PL-PER
Cycle 1, Sub-cycle B (premises is in Community District 2)
Active
HPD (0)

None open.

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Oct 29, 2026, 10:01 AM ET. BBL 3019760018.

Look up another building