1 floors · 1,507 sq ft · built 1931 · class K1 · owner of record: Share Equities Corp
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 67 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2024-06-04 (Accepted). Agency page | Dec 31, 2026 in 67 days | 1 of 1 without an accepted 2026 report yet |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 798 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| May 23, 2007 | Construction Non-Hazardous WORK W/O PERMIT.WORK NOTED:AT REAR PROPERTY APPROX 10'LONG & 2' HIGH A SECTION OF RETAINING WALL WAS CUT & DEMOLISHED.REMEDY:OBTAIN PERMIT OR RESTORE TO PRIOR LEGAL CONDITION. #34580577J | Jul 10, 2007 IN VIOLATION | $0 |
| Feb 9, 2007 | Boilers Hazardous 50A,B, BQ9.50A-FIRE RATED MATERIAL ABOVE BOILER MISSING EXPOSED WOOD BEAMS.50B-DEFECTIVE FLU PIPE ON BOILER INLET NOW PROPERLY FASTENED.BQ9-INSTALLATION OF A 1996 FULTON HIGH PRESSURE GAS FIRED BOILER W/ OBTAIN #32053092Y | Aug 4, 2009 WRITTEN OFF | $0 |
| Apr 20, 2005 | Boilers Non-Hazardous 18B38/40/48B/50A/50B/50C/30D/50E/50F/-1984 FULTON NATL BO.44276. 50A-COVER THE EXPOSED WOOD IN THE CEILING.50B-ENCLOSE THE BOILER IN A FIRE RATED ROOM.50C-THE SAFETY VALVE DISCHARGE PIPE THREADS ON THE END.50D- #32047676R | Jun 7, 2005 WRITTEN OFF | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION #00924 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #04437 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #03301 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #02082 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION #02183 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION #04515 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION #03367 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION #00972 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00904 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #02027 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION #01028 | DOB VIOLATION - ACTIVE |
| Apr 6, 2018 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT #16857 | DOB VIOLATION - ACTIVE |
| Jun 23, 2017 | HIGH PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE 2015 ANNUAL HIGH PRESSURE BOILER INSPECTION #00356 | DOB VIOLATION - ACTIVE |
| Mar 3, 2015 | HIGH PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE 2013 ANNUAL HIGH PRESSURE BOILER INSPECTION #00995 | DOB VIOLATION - ACTIVE |
| Dec 31, 2009 | LOW PRESSURE BOILER #21386 | DOB VIOLATION - ACTIVE |
| Jan 19, 2007 | LOCAL LAW 62/91 - BOILERS #23160 | DOB VIOLATION - ACTIVE |
| Jan 6, 2006 | LOCAL LAW 62/91 - BOILERS #22633 | DOB VIOLATION - ACTIVE |
| Mar 26, 2002 | LOCAL LAW 62/91 - BOILERS #27325 | DOB VIOLATION - ACTIVE |
| Sep 6, 2001 | CONSTRUCTION #ZSTF04RR | DOB VIOLATION - ACTIVE |
| Sep 6, 2001 | CONSTRUCTION #ZSTF05RR | DOB VIOLATION - ACTIVE |
| Sep 6, 2001 | CONSTRUCTION #ZSTF03RR | DOB VIOLATION - ACTIVE |
| Feb 27, 2001 | LOCAL LAW 62/91 - BOILERS #26135 | DOB VIOLATION - ACTIVE |
| Feb 27, 2001 | LOCAL LAW 62/91 - BOILERS #26136 | DOB VIOLATION - ACTIVE |
| Feb 27, 2001 | LOCAL LAW 62/91 - BOILERS #26134 | DOB VIOLATION - ACTIVE |
None open.
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)