6 floors · 115 apartments · 77,160 sq ft · built 1980 · class D1 · owner of record: Hope Gardens 1 Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 4 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 46 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 46 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 46 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 62 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 77,160 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 167 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 167 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 290 days | Registered through 2027-09-01 |
| Energy audit and retro-commissioning (2030) Likely applies Local Law 87 · Calendar year 2030 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 3340). Agency page | Dec 31, 2030 in 1507 days | Next due 2030 |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-05-08 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL #909664. REMEDY: SUBMIT ACCEPTABLE REQU #37028049X | Aug 21, 2024 IN VIOLATION | $625 |
| Issued | Violation | Status |
|---|---|---|
| Jun 23, 2024 | FAILURE TO SUBMIT EER FAILURE TO SUBMIT AN EER PER AD. CODE SEC. 28-308.4 - MULTIPLE YEARS (2023) #00462 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #18584 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #18585 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #38858 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #38859 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00355 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 4) | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Jun 23, 2024 | Retro-Commissioning - LL87 FTF-EN-EARCX | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Aug 26, 2023 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Report | Active |
| Aug 26, 2023 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Report | Active |
| Aug 12, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 12, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Feb 4, 2025 | C | Apt 1F · 567 (C) § 27-2017, 27-2017.1, 27-2017.4, 27-2017.5, 27-2017.8, 27-2019, 27-2021 HMC: ABATE THE NUISANCE CONSISTING OF EVIDENCE OF RATS AND ALL UNDERLYING CAUSES CREATING THE PEST INFESTATIONS, BY USING INTEGRATED PEST MANAGEMENT (IPM), ELIMINATE ALL BURROW ENTRY AND PASSAGEWAYS, PEST NESTS, HOLES, G | Mar 2, 2025 |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)