17 floors · 1162 apartments · 700,175 sq ft · built 1958 · class D3 · owner of record: Nyc Housing Authority
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 47 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 47 days | Annual |
| Annual boiler inspection (7 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-11-09 (Accepted). Agency page | Dec 31, 2026 in 47 days | 7 of 7 without an accepted 2026 report yet |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 63 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 700,175 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 168 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 168 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | No current registration found |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1143 days | Next cycle year 2029 |
| Energy audit and retro-commissioning (2035) Likely applies Local Law 87 · Calendar year 2035 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1855). Agency page | Dec 31, 2035 in 3334 days | Next due 2035 |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $6,000 in late-filing or failure-to-file penalties. Agency page | On file | Cycle 10 filing on record: SWARMP (2025-03-31) |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Aug 20, 2026 | Construction CLASS - 2 OBSERVED AT THE TIME OF INSPECTION IN THE BASEMENT THAT THE GAS PIPING SYSTEM WAS ALTERED WITHOUT A PERMIT, WITH WORK 100% COMPLETE. MODIFICATIONS INCLUDE A LOCKED GAS SHUT-OFF VALVE THAT WAS CAPPED, AND A CUT #39201241P | Sep 3, 2026 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Sep 16, 2021 | HAZARDOUS CONDITION (FACADE) NYCHA CYCLE 9A UNSAFE REPORT FILED #909450 | DOB VIOLATION - ACTIVE |
| Jun 5, 2021 | CONSTRUCTION VEHICLE IMPACTING SIDEWALK SHED #ER04JM | DOB VIOLATION - ACTIVE |
| Oct 9, 2019 | FACADE SAFETY PROGRAM #HAZ88394 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #01571 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #01572 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #01568 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #01567 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #01569 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #01570 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Sep 16, 2021 | Facades FISPHAZ NYCHA CYCLE 9A UNSAFE REPORT FILED | Active |
| Oct 9, 2019 | Facades FISP CYCLE 8A UNSAFE REPORT FILED | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Sep 28, 2015 | B | Apt 14D · § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK AT SOUTH WALL IN THE FOYER LOCATED AT APT 14D, 14th STORY, 2nd APARTMENT FROM EAST AT SOUTH | Nov 2, 2015 |
| Sep 28, 2015 | B | Apt 14D · § 27-2018 ADMIN. CODE: ABATE THE NUISANCE CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 14D, 14th STORY, 2nd APARTMENT FROM EAST AT SOUTH | Nov 2, 2015 |
| Sep 28, 2015 | B | Apt 14D · § 27-2005 ADM CODE REPLACE WITH NEW THE BROKEN OR DEFECTIVE GASKET AT LOWER DOOR OF REFRIGERATOR IN THE KITCHEN LOCATED AT APT 14D, 14th STORY, 2nd APARTMENT FROM EAST AT SOUTH | Nov 2, 2015 |
| Sep 28, 2015 | B | Apt 14D · § 27-2005 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE BASE CABINETS AT WEST WALL IN THE KITCHEN LOCATED AT APT 14D, 14th STORY, 2nd APARTMENT FROM EAST AT SOUTH | Nov 2, 2015 |
| Sep 28, 2015 | B | Apt 14D · § 27-2005 HMC:TRACE AND REPAIR THE SOURCE AND ABATE THE NUISANCE CONSISTING OF MOLD ... AT SOUTH WALL. APPROX. = 15 SQ.FT. IN THE FOYER LOCATED AT APT 14D, 14th STORY, 2nd APARTMENT FROM EAST AT SOUTH | Nov 2, 2015 |
| Sep 28, 2015 | B | Apt 14D · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR SOUTH WALL IN THE FOYER LOCATED AT APT 14D, 14th STORY, 2nd APARTMENT FROM EAST AT SOUTH | Nov 2, 2015 |
| Sep 28, 2015 | B | Apt 14D · § 27-2005 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE CLOSET DOOR AT WEST WALL IN THE PRIVATE HALLWAY LOCATED AT APT 14D, 14th STORY, 2nd APARTMENT FROM EAST AT SOUTH | Nov 2, 2015 |
| Sep 28, 2015 | B | Apt 14D · § 27-2005 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE CLOSET DOOR AT NORTH WALL IN THE 5th ROOM FROM EAST LOCATED AT APT 14D, 14th STORY, 2nd APARTMENT FROM EAST AT SOUTH | Nov 2, 2015 |
| Sep 28, 2015 | B | Apt 14D · § 27-2005 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE CLOSET DOOR AT NORTH WALL IN THE 4th ROOM FROM EAST LOCATED AT APT 14D, 14th STORY, 2nd APARTMENT FROM EAST AT SOUTH | Nov 2, 2015 |
| Date | Source | What | Now |
|---|---|---|---|
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Closed |
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Closed |
| Aug 20, 2026 | ECB | Construction: OBSERVED AT THE TIME OF INSPECTION IN THE BASEMENT THAT THE GAS PIPING SYSTEM WAS ALTERED WITHOUT A PERMIT, WITH WORK 100% COMPLETE. MODIFICATIONS INCLUDE A LOCKED GAS SHUT-OFF VALVE THAT WAS CAPPED, AND A CUT | Open |