3 floors · 21,210 sq ft · built 1905 · class W9 · owner of record: Beford Stuyvesant Early Childhood
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 65 days | Keep the report on file (not filed with DOB) |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 796 days | Next cycle year 2028 |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-07-20 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Oct 30, 2025 | Boilers CLASS - 2 HYDROTHERM BLR>COMBUSTION AIR DUCT HAS THE INSIDE SCREEN+OUTSIDE LOUVER 1/2 CLOGGED+ELEVATOR ROOM EXHAUST AIR DUCTED INTO BLR ROOM AIR DUCT+WIRES RUN THRU FIRE DAMPER+OPEN AIR GRATE IN BLR ROOM CEILING+REPLACEM #39165394K | Dec 10, 2026 DEFAULT | $1,280 |
| Aug 20, 2024 | Boilers CLASS - 2 FOUND HYDROTHERM GAS FIRED BOILER MODEL-MR-1200B WITH 4 MODULES ACTIVE WITH DEFECTS. CIRCULATOR PUMP LEAKING AT SEAL. CORRECT ALL VIOLATING CONDITIONS AND SUBMIT A CERTIFICATE OF CORRECTION. #39122544R | Jul 14, 2025 IN VIOLATION | $0 |
| Sep 2, 2020 | Elevators CLASS - 1 NO DOOR LOCK MONITORING INSTALLED IN THIS CONTROLLER AS MANDATED BY 3.10.12 OF APPENDIX K3 OF THE 2014 NYCBC. THIS IS A CONTROLLER FEATURE WHICH ENSURES PASSENGER SAFETY. FILE APPLICATION INSTALL DLM AND PERFOR #39027987K | Mar 4, 2021 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #10129 | DOB VIOLATION - ACTIVE |
| Nov 25, 2020 | FAIL TO CERTIFY CLASS 1 FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION #00380 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #07476 | DOB VIOLATION - ACTIVE |
| Sep 15, 2017 | ELEVATOR ANNUAL INSPECTION / TEST VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2016 INSPECTION/TEST #03892 | DOB VIOLATION - ACTIVE |
| May 15, 2014 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT #13347 | DOB VIOLATION - ACTIVE |
| Dec 13, 2011 | ELEVATOR ANNUAL INSPECTION / TEST VIOLATION ISSUED TO ELEVATOR-FAILURE TO FILE CATEGORY 1 2010 INSPECTION/TEST #02820 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 3) | Active |
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 3) | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Report | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 25, 2020 | AEUHAZ FTC-AEU-HAZ | Active |
| Sep 6, 2019 | Elevators ACC1 | Active |
| Sep 15, 2017 | Elevators EVCAT1 | Active |
| May 15, 2014 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT | Active |
| Dec 13, 2011 | Elevators EVCAT1 | Active |