8 floors · 596,475 sq ft · built 1957 · class Z1 · owner of record: Nyc Department Of Transportation
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 9 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 58 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 58 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (4 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-10-22 (QA Supervisor Review). Agency page | Dec 31, 2026 in 58 days | 4 of 4 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 596,475 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 179 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 179 days | Annual filing |
| Energy audit and retro-commissioning (2027) Likely applies Local Law 87 · Calendar year 2027 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 9657). Agency page | Dec 31, 2027 in 423 days | Next due 2027 |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. DOB facade records for this building show $987,000 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2028 in 475 days | No Cycle 10 report on record yet |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 18, 2026 | Unknown CLASS - 2 BC3304.7 ACCESS.IN RESPONSE TO INCIDENT OF WORKER INJURED&TRANSPORTED TO HOSPITAL OBSERVE APPROX. 5'DEPTH EXCAVATION FOR NEW SEWER PIT WITHOUT SAFE ADEQUATE MEANS OF INGRESS/EGRESS W/TOP OF LADDER LANDING ON PI #39559365N | Nov 24, 2026 ADMIT/IN-VIO | $0 |
| Aug 4, 2025 | Construction CLASS - 1 NOTICE OF ORDER TO STOP WORK IMMEDIATELY DUE TO LICENSED MASTER PLUMBER WITHDRAWAL UNDER APPLICATION # Q00516010-I1 BC SWO ISSUED., OBTAIN PERMIT #39155911K | Aug 25, 2025 POP/IN-VIO | $0 |
| Jun 13, 2023 | Elevators CLASS - 2 REPAIR AND RESTORE TO SERVICE. ____________________________________________________________________________________________________________________________________________ #39088435L | Jun 15, 2023 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #00838 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #00837 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #04012 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 29, 2026 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Affirmation of Correction | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Sep 3, 2019 | Sprinklers FTF-SP-FINAL | Active |
| Apr 30, 2019 | Facades FISPNRF FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019 | Active |
| May 25, 2018 | Facades FISP CYCLE 8C UNSAFE REPORT FILED | Active |
| May 25, 2018 | Facades FISP CYCLE 7C UNSAFE REPORT FILED | Active |
| Jun 10, 2015 | Elevators EVCAT1 | Active |
| Mar 5, 2014 | Facades LL11/98 CYCLE 6 UNSAFE REPORT FILED | Active |
| Mar 5, 2014 | Facades LL11/98 CYCLE 7C UNSAFE REPORT FILED | Active |
| Oct 1, 2012 | Elevators EVCAT1 | Active |
| Oct 1, 2012 | Elevators EVCAT1 | Active |
| Oct 1, 2012 | Elevators EVCAT1 | Active |
| Oct 1, 2012 | Elevators EVCAT1 | Active |
| Oct 1, 2012 | Elevators EVCAT1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
| Aug 15, 2012 | Elevators ACC1 | Active |
| Dec 13, 2011 | Elevators EVCAT1 | Active |
| Dec 13, 2011 | Elevators EVCAT1 | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |
Showing 60 of 86. Full list on the agency site.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Affirmation of Correction | Open |
| Sep 18, 2026 | ECB | Unknown: BC3304.7 ACCESS.IN RESPONSE TO INCIDENT OF WORKER INJURED&TRANSPORTED TO HOSPITAL OBSERVE APPROX. 5'DEPTH EXCAVATION FOR NEW SEWER PIT WITHOUT SAFE ADEQUATE MEANS OF INGRESS/EGRESS W/TOP OF LADDER LANDING ON PI | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 3, 2026, 4:38 AM ET. BBL 4096570001.