Brooklyn · Block 903 · Lot 43 · 11232

775 39 Street

1 floors · 7,950 sq ft · built 1945 · class K1 · owner of record: 775 39 Street Property Llc

36open violations
$13,750ECB/OATH penalties owed
0HPD class C (immediately hazardous)
1164dto Gas piping inspection (2029 cycle)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 68 days
Keep the report on file (not filed with DOB)
Gas piping inspection (2029 cycle) Likely applies
Local Law 152 · During 2029
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2029
in 1164 days
Next cycle year 2029

Open violations

ECB / OATH (4) · $13,750 owed
IssuedViolationHearingBalance
Oct 7, 2026Construction CLASS - 1
WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS. TEMP CONSTRUCTION FENCE ERECTED UNDER APPLICATION # B01265518-S2-FN, APPROVED CONSTRUCTION DOCUMENTS SHOW FENCE TO BE 8 FEET
#39207177R
Dec 16, 2026
PENDING
$6,250
Apr 14, 2026Unknown CLASS - 2
ATOI OBSERVED OVER FILLED DEBRIS DUMPSTER FROM CONSTRUCTION AT 775 39 STREET, BK. UPON REVIEW OF RECORDS NO DOT PERMIT ISSUED FOR THE DEBRIS CONTAINER TO BE PLACED ON STREET.; BC CHAPTER 33, COMPLY WITH CODE
#39184523L
Dec 1, 2026
$2,500
Apr 14, 2026Construction CLASS - 1
ATOI OBSERVED WORK WITHOUT A PERMIT. UNPERMITTED/UNAPPROVED SIGNS INSTALLED AT FACADE OF BUILDING. 4 SIGNS FACING 8TH AVE AND 2 SIGNS FACING 39 STREET DISPLAYING "M2 PARTY K", OBTAIN PERMIT
#39184522J
Jun 24, 2026
IN VIOLATION
$2,500
Apr 14, 2026Construction CLASS - 1
ATOI OBSERVED NON-CONFORMING CONSTRUCTION FENCE. FENCE TO BE INSTALLED AROUND ENTIRE SITE ALONG 39TH STREETB & 8TH AVE FENCE. FENCE NOT INSTALLED TO SECURE ENTIRE SITE. ADDITIONAL 6 FT HIGH WOODEN STUDS EXTENDE
#39184524N
Dec 1, 2026
PENDING
$2,500
DOB (17)
IssuedViolationStatus
Nov 14, 2025HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
#01138
DOB VIOLATION - ACTIVE
Nov 14, 2025HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
#00327
DOB VIOLATION - ACTIVE
Sep 23, 2024HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
#01207
DOB VIOLATION - ACTIVE
Sep 23, 2024HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
#00340
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
#04638
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
#02312
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
#01086
DOB VIOLATION - ACTIVE
Jun 30, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
#03456
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
#04747
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION
#01154
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION
#02403
DOB VIOLATION - ACTIVE
Jun 20, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION
#03559
DOB VIOLATION - ACTIVE
Apr 25, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION
#01843
DOB VIOLATION - ACTIVE
Apr 25, 2023HIGH PRESSURE BOILER
VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION
#00710
DOB VIOLATION - ACTIVE
Mar 16, 2020HIGH PRESSURE BOILER
VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
#00812
DOB VIOLATION - ACTIVE
Mar 16, 2020HIGH PRESSURE BOILER
VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION
#00773
DOB VIOLATION - ACTIVE
Aug 16, 1993LOCAL LAW 62/91 - BOILERS

#29214
DOB VIOLATION - ACTIVE
DOB NOW Safety (16)
IssuedViolationStatus
Nov 14, 2025Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION
Active
Nov 14, 2025Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION
Active
Sep 23, 2024Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION
Active
Sep 23, 2024Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 30, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION
Active
Jun 20, 2023Boiler HBLVIO
VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION
Active
Apr 25, 2023Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Apr 25, 2023Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Mar 16, 2020Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION
Active
Mar 16, 2020Boiler HBLVIO
VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION
Active
HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Oct 7, 2026ECBConstruction: WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS AND/OR APPROVED AMENDMENTS. TEMP CONSTRUCTION FENCE ERECTED UNDER APPLICATION # B01265518-S2-FN, APPROVED CONSTRUCTION DOCUMENTS SHOW FENCE TO BE 8 FEETOpen

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Oct 24, 2026, 1:39 PM ET. BBL 3009030043.

Look up another building