4 floors · 3 apartments · 4,704 sq ft · built 1920 · class S3 · owner of record: Corticchia , Michael
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 68 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 68 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 68 days | Annual |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-12-17 (Accepted). Agency page | Dec 31, 2026 in 68 days | 1 of 1 without an accepted 2026 report yet |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 84 days | Annual |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Oct 19, 2026 | Construction CLASS - 2 AT THE TIME OF INSPECTION, THE PROPOSED 17-STORY NEW BUILDING WAS IN THE EXCAVATION/FOUNDATION PHASE. ACCUMULATED DEBRIS WAS OBSERVED ON-SITE, CREATING A HAZARD TO THE PUBLIC AND PROPERTY AND A POTENTIAL FIRE A #39560732Y | Dec 23, 2026 PENDING | $1,250 |
| Dec 19, 2025 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPARTMENT OF BUILDINGS.NO CERTIFICATE OF CORRECTION ON FILE FOR VIO#35506705X AS OF 12/19/25.., FILE A CERTIFICATE O #39171017X | Mar 2, 2027 DEFAULT | $6,250 |
| Jan 6, 2023 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED EXP2-4 AVEFACADE IN STATE OF DISREPAIR WITH CRACKS IN BRICKS ON 2ND FLOOR LEVEL,CRACKED AND SPALLING STONE WINDOW SILLS AND LINTELS ON 2ND,3RD,AND 4TH #35506705X | Aug 21, 2023 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Aug 4, 2026 | IMMEDIATE EMERGENCY INSTALL 2 LINES OF VERTICAL SHORING WITH TRANSVERSE CROSS BRACING IN BOTH DIRECTIONS EXTENDING THE FULL LENGTH & FULL OF THE BUILDING FROM TOP OF CELLAR SLAB TO UNDERSIDE OF ROOF: INSTALL 1 LINE OF SHORING OUT SIDE OF UNDERMINED AREA (SLAB CRACK) & THE 2ND LINE OF SHORING APPROX 6 FT AWAY FROM THE F #20489 | DOB VIOLATION - ACTIVE |
| Aug 3, 2026 | CONSTRUCTION EMERGENCY WORK ORDER.DURING SOE/UNDERPINING WRK@ADJ CONSTRUCTION SITE (EXP2),OBSRVD DMH TO BLDG INCL SETTLEMNT,UNDEPINNING OF FOUNDTN,CRCKS IN EXT WALLS,LEANING&SHIFTNG OF WALLS.SOFT STRY CNDTN.COMPLY WITH COMMISSIONER'S ORDER:DOB VIOLATION # STABILIZE 073126FEU0601AK(CONTROL #350827) IMMEDIATELY #FEU30601AK | DOB VIOLATION - ACTIVE |
| Jul 31, 2026 | CONSTRUCTION EMERGENCY WORK ORDER.DURING SOE/UNDERPINING WRK@ADJ CONSTRUCTION SITE (EXP2),OBSRVD DMG TO BLDG INCL SETTLEMNT,UNDERPINING OF FOUNDTN,CRCKS IN EXT WALLS,LEANING&SHIFTNG OF WALLS.SOFT STRY CNDTN.COMPLY WITH COMMISSIONER;S ORDER:DOB VIOLATION # STABILIZE 073126FEU30601AK (CONTROL #350827) IMMEDIATELY #FEU30601AK | DOB VIOLATION - ACTIVE |
| Jul 31, 2026 | CONSTRUCTION FAILURE TO MAINTAIN.DURNG SOE/UNDERPINING WRK@ADJ CNSTRCTN SITE(EXP2), OBSRVD DMG TO BLDG INCL SETTLEMENT,UNDERPINING OF FOUNDTN,CRCKS IN EXT WALLS,LEANING,&SHIFTNG OF WALLS.SOFT STRY CNDTN.OWNR TO ENGAGE NYSPE &ENDRSD CNTRCTR TO EVAL THE ENT BLDG&PERM STRCTRLLY RPAIR UNDR PRMT FILE FOR PRMTS BY 8/3 #FEU30602AK | DOB VIOLATION - ACTIVE |
| Jul 30, 2026 | CONSTRUCTION STRUCTURE RENDERED NON-COMPLIANT DUE TO CONSTRUCTION ACTIVITY AT 67 4TH AVENUE. VERTICAL AND HORIZONTAL CRACKS WERE PRESENT THROUGHOUT THE INTERIOR AND EXTERIOR WALLS AT EXPOSURES 1 AND 2 ON ALL STORIES, INCLUDING THE BASEMENT. #26-01889 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #21418 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #42232 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION #42592 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION #23252 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #18491 | DOB VIOLATION - ACTIVE |
| Jan 6, 2023 | IMMEDIATE EMERGENCY INSTALL APPROXIMATELY 20 FEET IN LENGTH AT THE FRONT (4TH AVENUE) #17357 | DOB VIOLATION - ACTIVE |
| Nov 8, 2019 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT #11270 | DOB VIOLATION - ACTIVE |
| Oct 1, 2015 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2014 INSPECTION REPORT #10133 | DOB VIOLATION - ACTIVE |
| Mar 3, 2015 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT #13092 | DOB VIOLATION - ACTIVE |
| May 15, 2014 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT #09668 | DOB VIOLATION - ACTIVE |
| Jan 1, 2009 | LOCAL LAW 62/91 - BOILERS #18279 | DOB VIOLATION - ACTIVE |
| Jan 3, 2008 | LOCAL LAW 62/91 - BOILERS #18245 | DOB VIOLATION - ACTIVE |
| Jan 6, 2006 | LOCAL LAW 62/91 - BOILERS #17993 | DOB VIOLATION - ACTIVE |
| Jan 31, 2005 | LOCAL LAW 62/91 - BOILERS #19211 | DOB VIOLATION - ACTIVE |
| Mar 26, 2002 | LOCAL LAW 62/91 - BOILERS #14582 | DOB VIOLATION - ACTIVE |
| Feb 27, 2001 | LOCAL LAW 62/91 - BOILERS #13633 | DOB VIOLATION - ACTIVE |
| Jul 25, 1994 | LOCAL LAW 62/91 - BOILERS #04918 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 6) | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
| Nov 8, 2019 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2017 INSPECTION REPORT | Active |
| Oct 1, 2015 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2014 INSPECTION REPORT | Active |
| Mar 3, 2015 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2013 INSPECTION REPORT | Active |
| May 15, 2014 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT | Active |
| Jan 1, 2009 | Boiler LL6291 | Active |
| Jan 3, 2008 | Boiler LL6291 | Active |
| Jan 6, 2006 | Boiler LL6291 | Active |
| Jan 31, 2005 | Boiler LL6291 | Active |
| Mar 26, 2002 | Boiler LL6291 | Active |
| Feb 27, 2001 | Boiler LL6291 | Active |
| Jul 25, 1994 | Boiler LL6291 | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Apr 30, 2026 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Aug 3, 2026 |
| Jun 5, 2025 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Sep 8, 2025 |
| Apr 3, 2024 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Jul 7, 2024 |
| Mar 17, 2023 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Jun 20, 2023 |
| Feb 18, 2022 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | May 24, 2022 |
| Apr 5, 2021 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Jul 9, 2021 |
| Aug 7, 2008 | A | D26-10.01 ADM CODE PROVIDE PROPER SECURING SCUTTLE BY MEANS OF A SLIDE BOLT HOOK OR LOCK WHICH DOES NOT REQUIRE A KEY TO OPEN PUBLIC HALL ROOF. | Nov 10, 2008 |
| Aug 7, 2008 | B | D26-10.01, 10.05 ADM CODE REMOVE ALL ENCUMBRANCES CONSISTING OF HOUSEHOLD ITEMS CLOTHESLINE 4 STY PUBLIC HALL. | Sep 11, 2008 |
| Dec 12, 2006 | B | § 27-2040 ADM CODE PROVIDE ADEQUATE LIGHTING AT OR NEAR THE OUTSIDE OF THE FRONT ENTRANCEWAY OF THE BUILDING AND KEEP SAME BURNING FROM SUNSET EVERY DAY TO SUNRISE ON THE DAY FOLLOWING , 100 WATTS MINIMUM REQUIRED | Jan 21, 2007 |
| Date | Source | What | Now |
|---|---|---|---|
| Oct 19, 2026 | ECB | Construction: AT THE TIME OF INSPECTION, THE PROPOSED 17-STORY NEW BUILDING WAS IN THE EXCAVATION/FOUNDATION PHASE. ACCUMULATED DEBRIS WAS OBSERVED ON-SITE, CREATING A HAZARD TO THE PUBLIC AND PROPERTY AND A POTENTIAL FIRE A | Open |
| Aug 4, 2026 | DOB | IMMEDIATE EMERGENCY: INSTALL 2 LINES OF VERTICAL SHORING WITH TRANSVERSE CROSS BRACING IN BOTH DIRECTIONS EXTENDING THE FULL LENGTH & FULL OF THE BUILDING FROM TOP OF CELLAR SLAB TO UNDERSIDE OF ROOF: INSTALL 1 LINE OF SHORING OUT SIDE OF UNDERMINED AREA (SLAB CRACK) & THE 2ND LINE OF SHORING APPROX 6 FT AWAY FROM THE F | Open |
| Aug 3, 2026 | DOB | CONSTRUCTION: EMERGENCY WORK ORDER.DURING SOE/UNDERPINING WRK@ADJ CONSTRUCTION SITE (EXP2),OBSRVD DMH TO BLDG INCL SETTLEMNT,UNDEPINNING OF FOUNDTN,CRCKS IN EXT WALLS,LEANING&SHIFTNG OF WALLS.SOFT STRY CNDTN.COMPLY WITH COMMISSIONER'S ORDER:DOB VIOLATION # STABILIZE 073126FEU0601AK(CONTROL #350827) IMMEDIATELY | Open |
| Jul 31, 2026 | DOB | CONSTRUCTION: EMERGENCY WORK ORDER.DURING SOE/UNDERPINING WRK@ADJ CONSTRUCTION SITE (EXP2),OBSRVD DMG TO BLDG INCL SETTLEMNT,UNDERPINING OF FOUNDTN,CRCKS IN EXT WALLS,LEANING&SHIFTNG OF WALLS.SOFT STRY CNDTN.COMPLY WITH COMMISSIONER;S ORDER:DOB VIOLATION # STABILIZE 073126FEU30601AK (CONTROL #350827) IMMEDIATELY | Open |
| Jul 31, 2026 | DOB | CONSTRUCTION: FAILURE TO MAINTAIN.DURNG SOE/UNDERPINING WRK@ADJ CNSTRCTN SITE(EXP2), OBSRVD DMG TO BLDG INCL SETTLEMENT,UNDERPINING OF FOUNDTN,CRCKS IN EXT WALLS,LEANING,&SHIFTNG OF WALLS.SOFT STRY CNDTN.OWNR TO ENGAGE NYSPE &ENDRSD CNTRCTR TO EVAL THE ENT BLDG&PERM STRCTRLLY RPAIR UNDR PRMT FILE FOR PRMTS BY 8/3 | Open |
| Jul 30, 2026 | DOB | CONSTRUCTION: STRUCTURE RENDERED NON-COMPLIANT DUE TO CONSTRUCTION ACTIVITY AT 67 4TH AVENUE. VERTICAL AND HORIZONTAL CRACKS WERE PRESENT THROUGHOUT THE INTERIOR AND EXTERIOR WALLS AT EXPOSURES 1 AND 2 ON ALL STORIES, INCLUDING THE BASEMENT. | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 24, 2026, 4:41 PM ET. BBL 3009320001.