4 floors · 134,957 sq ft · built 1971 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 43 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 43 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2023-10-05 (Accepted). Agency page | Dec 31, 2026 in 43 days | 2 of 2 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 134,957 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 164 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 164 days | Annual filing |
| Energy audit and retro-commissioning (2029) Likely applies Local Law 87 · Calendar year 2029 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 3109). Agency page | Dec 31, 2029 in 1139 days | Next due 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| May 8, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: ON THE ROOF, THERE ARE SECTIONS WHERE INSULATION IS TORN AND WEEDS ARE GROWINGIN VARIOUS AREAS ON THE ROOF. REMEDY: REPAIR AND/OR REPLACE, #35732807M | Jun 26, 2026 POP/IN-VIO | $0 |
| May 8, 2026 | Construction CLASS - 2 28-301.1 UNLAWFUL PLACEMENT OF FURNISHINGS,DECORATIONS OR OTHER OBJECTS AT EXITS THAT OBSTRUCT ACCESS TO,EGRESS FROM OR VISIBLITY THEREOF PER FDNY 2008 CODE;FC 1027.4.NOTED:OBSERVED AT EXIT 4 EGRESS WAS BLOCKED #35732774P | Jul 24, 2026 POP/IN-VIO | $0 |
| May 8, 2026 | Construction CLASS - 2 REISSUE#35721572N FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:FPSC DOORS DO NOT SELF-CLOSE PROPERLY.INTERIOR STAIRCASE 3RD FLR-STAIRCASE E,D.2ND FLR-STAIRCASE E.1ST FLR-EXIT 7 INTERIOR CLASSROOM #35732805Z | Jul 24, 2026 POP/IN-VIO | $0 |
| May 8, 2026 | Construction CLASS - 2 REISSUE#35721574R EXIT DOOR NOT SELF-CLOSING.NOTED:EXTERIOR FPSC DOORS#2,4,5,13,14,15 DO NOT SELF-CLOSE PROPERLY WITHOUT BEING FORCED CLOSE WHEN TESTED.REM:REPAIR/REPLACE DOOR. #35732804R | Jul 24, 2026 POP/IN-VIO | $0 |
| May 8, 2026 | Construction CLASS - 2 REISSUE#35721576K FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:AT 3RD FLOOR STAIRCASE D AND E THERE ARE CRACKS GOING THRU GLAZED BLOCKS AROUND STAIR DOORS.REM:REPAIR AND/OR REPLACE. #35732803P | Jul 24, 2026 POP/IN-VIO | $0 |
| May 8, 2026 | Construction CLASS - 2 REISSUE#35721577M FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NO FIRESTOPPING PER BC 712.3;27-345.NOTED:IN GAS METER ROOM,THERE ISA 2FT PENETRATION IN CMU BLOCK WALL WITH NO FIRESTOP APPLIED.REM:PROVI #35732802N | Jul 24, 2026 POP/IN-VIO | $0 |
| May 8, 2026 | Construction CLASS - 2 REISSUE#35721579X FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:GRAVEL ROOF'S RIGID FOAM INSULATION IS PEELING AND VEGITATION /MOSS IS GROWNING IN SEVERAL AREAS ON ROOF.REM:REPAIR AND/OR REPLACE. #35732800J | Jul 24, 2026 POP/IN-VIO | $0 |
| May 8, 2026 | Construction CLASS - 2 REISSUE#35721578Y FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED:CRACKS AND SPALLING ON EXTERIOR WALLS CEMENT FINISH AT EXP#1,2ND FLR LEVEL ABOVE EXIT#2 AND AT EXP#3 ABOVE EXIT#12.REM:REPAIR AND/OR #35732801L | Jul 24, 2026 POP/IN-VIO | $0 |
| May 8, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: INTERIORFPSC DOORS DO NOT SELF-CLOSE PROPERLY. AT 1ST FLR-STAIRCASE "A". CLASSROOM DOORS DO NOT SELF-CLOSE PROPERLY WHEN TESTED AT 4TH FLR RM #S, 42 #35732806K | Jun 26, 2026 POP/IN-VIO | $0 |
| Aug 1, 2025 | Construction CLASS - 2 REISSUE #35684943N. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED CRACKS IN GLAZED BLOCK WALLS IN STAIRCASE D AND E ON THE 3RD FLOOR AND AT EXIT-15 VESTIBULE GLAZED BLOCK WALL CRACKED AND SEPERAT #35721576K | Sep 5, 2025 POP/IN-VIO | $0 |
| Aug 1, 2025 | Construction CLASS - 2 EXIT DOOR NOT SELF-CLOSING. EXTERIOR DOORS AT EXIT #13, 5, 4, 2, 14, 15, 16 AND 11 WERE NOT PROPERLY SELF-CLOSING WHEN TESTED. REMEDY: REPAIR AND/OR REPLACE. #35721574R | Sep 5, 2025 POP/IN-VIO | $0 |
| Aug 1, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: INTERIORFPSC DOORS NOT CLOSING PROPERLY AT: 3RD FL STAIR D AND E. 2ND FL SMOKEDOOR BY #215. 1ST FL STAIR E, A, C, AND B, SMOKE DOORS AT EXITS #3, 4, #35721572N | Sep 5, 2025 POP/IN-VIO | $0 |
| Aug 1, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: NO FIRE STOPPING PER BC 712.3; 27-345. AT CELLAR LEVEL GAS METER/SPRINKLER VALVE ROOMOBSERVED AN APPROX. 2FT PENETRATION THROUGH CMU BLOCK WALL WITH NO FIR #35721577M | Sep 5, 2025 POP/IN-VIO | $0 |
| Aug 1, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED SPALLING EXTERIOR WALL CEMENT FINISH AT EXP #1, 2ND FL LEVEL ABOVE EXIT #2 AND AT EXP #3 ABOVE EXIT #12. MAPES AVE AND PROSPECT AVE. REMEDY: REPAIR A #35721578Y | Sep 5, 2025 POP/IN-VIO | $0 |
| Aug 1, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED GRAVEL ROOFS IN STATE OF DISREPAIR. MISSING AND PEELING RIGID FOAM INSULATION AND VEGITATION/MOSS GROWING THROUGHOUT SEVERAL AREAS. REMEDY: REPAIR AN #35721579X | Sep 5, 2025 POP/IN-VIO | $0 |
| Oct 8, 2024 | Construction CLASS - 2 REISSUE:35676324Y DATE OF ISSUE:07.11.2023 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER AT THE TIME OF INSPECTION OBSERVED & NOTED ON 3RD FLOOR STAIR D AND E CRACKS GOING THROUGH GLAZED BLOCKS AROUND S #35684943N | Dec 20, 2024 POP/IN-VIO | $0 |
| Jul 11, 2023 | Construction CLASS - 2 REISSUE #35657868Z DATE OF ISSUE:06.06.22 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION OBSERVED THAT AND NOTED ON 3RD FLOOR STAIR "D" AND "E" CRACKS GOING THORUGH AT STAIR "D #35676324Y | Nov 3, 2023 POP/IN-VIO | $0 |
| Jun 6, 2022 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED OBSERVED ON 3RD FLOOR STAIR D AND E CRACKS GOING THROUGH GLAZED BLOCKS AROUND STAIR DOORS.REMEDY:REPAIR AND/OR REPLACE. #35657868Z | Sep 2, 2022 POP/IN-VIO | $0 |
| Jan 10, 2022 | Boilers CLASS - 2 FOUND THAT MUD LEGS ON LEFT REAR AND RIGHT FRONT ARE LEAKING. CIRCULATING PUMP ON LEFT SIDE UNDER MOTOR IS LEAKING. #39053985X | Jan 12, 2022 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #06454 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #06455 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 6) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 6) | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2018 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 18, 2026, 1:49 AM ET. BBL 2031090001.