2 floors · 2 apartments · 2,048 sq ft · built 1915 · class B9 · owner of record: 8th Ave Brooklyn Realty Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Check HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 313 days | Required only if the owner doesn't live there |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Aug 20, 2026 | Unknown CLASS - 2 . SITE FAILED TO MAINTAIN A SAFE AND ACCESSIBLE FORM OF EGRESS FOR WORKERS WHILE CONCRETE OPERATIONS WERE IN PROGRESS. THE LACK OF A MAINTAINED MEANS OF EGRESS CREATES A HAZARDOUS CONDITION PREVENTING WORKERS F #39558204H | Oct 28, 2026 PENDING | $2,500 |
| Aug 20, 2026 | Construction CLASS - 2 . OBSERVED ACTIVE CONCRETE OPERATIONS TAKING PLACE WITHOUT PROVIDING REQUIRED FLAGMEN TO DIRECT AND CONTROL PEDESTRIAN TRAFFIC DURING CONCRETE OPERATIONS. NO FLAGMEN PUTS PEDESTRIAN IN DANGER OF CONCRETE OPERAT #39558202Y | Oct 28, 2026 PENDING | $2,400 |
| Aug 20, 2026 | Construction CLASS - 2 . OBSERVED ACTIVE CONCRETE OPERATION @ SITE WITH AN INADEQUATE CONCRETE WASHOUT BOX. THE WASHOUT BOX WAS OBSERVED OVERFLOWING WITH CONCRETE AND CONCRETE-CONTAMINATED WATER, ALLOWING THE WASHOUT WATER TO DISCHAR #39558203X | Oct 28, 2026 PENDING | $2,500 |
| Aug 20, 2026 | Construction CLASS - 2 OBSERVED ACTIVE SITE WITH AN ON-GOING CONCRETE OPERATIONS. AFTER CHECKING DOB SYSTEM IT WAS DETERMINED THAT GC PERMIT ( B01072946-I1-GC) HAS EXPIRED ON 8/12/26.STOP ALL WORK. PROVIDE/MAINTAIN PERMIT #39558208P | Oct 28, 2026 PENDING | $1,250 |
| May 12, 2026 | Construction CLASS - 2 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING, I OBSERVED SIDEWALK SHED IN PLACE AT EXPOSURE #1 WITH A VALID PERMIT EXPIRATION DATE 05-19-2026 AND WITH THE FOLLOWING OBJECTIVE INOPERABLE LIGHT BULBS, FAILU #39554005R | Jul 22, 2026 IN VIOLATION | $2,400 |
| Mar 6, 2025 | Construction CLASS - 2 OBSERVED TEMPORARY RAMP WAS INSTALLED OVER THE SIDEWALK FOR REMOVAL OF HEAVY CONSTRUCTION MATERIALS/DEBRIS INTO DEBRIS CONTAINER PARKED AT STREET. NO SAFETY MEASURES WERE PROVIDED FOR PEDESTRIANS USING THE SIDE #39537697M | Nov 7, 2025 IN VIOLATION | $0 |
None open.
None open.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Aug 20, 2026 | ECB | Unknown: . SITE FAILED TO MAINTAIN A SAFE AND ACCESSIBLE FORM OF EGRESS FOR WORKERS WHILE CONCRETE OPERATIONS WERE IN PROGRESS. THE LACK OF A MAINTAINED MEANS OF EGRESS CREATES A HAZARDOUS CONDITION PREVENTING WORKERS F | Open |
| Aug 20, 2026 | ECB | Construction: . OBSERVED ACTIVE CONCRETE OPERATIONS TAKING PLACE WITHOUT PROVIDING REQUIRED FLAGMEN TO DIRECT AND CONTROL PEDESTRIAN TRAFFIC DURING CONCRETE OPERATIONS. NO FLAGMEN PUTS PEDESTRIAN IN DANGER OF CONCRETE OPERAT | Open |
| Aug 20, 2026 | ECB | Construction: . OBSERVED ACTIVE CONCRETE OPERATION @ SITE WITH AN INADEQUATE CONCRETE WASHOUT BOX. THE WASHOUT BOX WAS OBSERVED OVERFLOWING WITH CONCRETE AND CONCRETE-CONTAMINATED WATER, ALLOWING THE WASHOUT WATER TO DISCHAR | Open |
| Aug 20, 2026 | ECB | Construction: OBSERVED ACTIVE SITE WITH AN ON-GOING CONCRETE OPERATIONS. AFTER CHECKING DOB SYSTEM IT WAS DETERMINED THAT GC PERMIT ( B01072946-I1-GC) HAS EXPIRED ON 8/12/26.STOP ALL WORK. PROVIDE/MAINTAIN PERMIT | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 23, 2026, 3:08 AM ET. BBL 3008500057.