Brooklyn · Block 2130 · Lot 7502 · 11249

75 South 8th Street

5 floors · 8 apartments · 28,581 sq ft · built 2023 · class RM · owner of record: S8-6977, Llc

17open violations
$161,250ECB/OATH penalties owed
0HPD class C (immediately hazardous)
59dto Bedbug annual filing

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 59 days
Keep the report on file (not filed with DOB)
Bedbug annual filing Applies
Local Law 69 · December 1 to 31 each year
What this is

Owners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page

Dec 31, 2026
in 59 days
Annual
Annual notice: window guards and lead paint Applies
HPD / Health Code · January 1 to 16 each year
What this is

Deliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page

Jan 16, 2027
in 75 days
Annual
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 28,581 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 180 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 180 days
Annual filing
Annual property registration Applies
HPD registration · September 1 each year
What this is

Residential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page

Sep 1, 2027
in 303 days
Registered through 2027-09-01
Gas piping inspection (2028 cycle) Likely applies
Local Law 152 · During 2028
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2028
in 790 days
Next cycle year 2028

Open violations

ECB / OATH (14) · $161,250 owed
IssuedViolationHearingBalance
Sep 10, 2026Construction CLASS - 1
UNLAWFUL CONTINUANCE OF WORK WHILE ON NOTICE OF A STOP WORK ORDER ISSUED ON 8/12/2026 VIO #039200329P. ATOI OBSERVED CONSTRUCTION WORK IN PROGRESS WITH SEVERAL WORKERS THROUGHOUT THE 5TH, 6TH AND 7TH FLOORS OF
#39203672X
Nov 18, 2026
PENDING
$10,000
Aug 26, 2026Construction CLASS - 1
AT TIME OF INSPECTION OBSERVED SEVERAL PUMP JACK SCAFFOLDING INSTALLED ON TOP OF ROOF AT EXPOSURE 1, USING STANDARD LADDERS AS PLATFORMS. THERE IS ACTIVE STOP WORK ORDER SINCE 8/12/2026., COMPLY WITH STOP WORK
#39202023L
Nov 4, 2026
PENDING
$25,000
Aug 25, 2026Construction CLASS - 1
AT TIME OF INSPECTION OBSERVED TWO MALE WORKERS WORKING ON ROOF EXTENSION. ACTIVE STOP WORK ORDER WAS ISSUED ON 8/19/2026., COMPLY WITH STOP WORK ORDER
#39201849N
Nov 4, 2026
PENDING
$25,000
Aug 25, 2026Construction CLASS - 1
UNLAWFUULY CONTINUED WORK WHILE ON NOTICE OR STOP WORK ORDER. ATOI OBSERVED CONSTRUCTION WORK IN PROGRESS ON ADDITION TO ROOF. WORKERS WORKING ON SUSPENDED SCAFFOLD. ALL IN VIOLATION OF PSWO ISSUED ON 8/12/2026
#35728381M
Nov 4, 2026
PENDING
$25,000
Aug 21, 2026Construction CLASS - 1
OBSERVED ON 6TH AND 7TH FLOOR WORK CONTINUED AND HOUSE KEEPING NOT IN EFFECT WITH MULTIPLE AREAS WITH CONSTRUCTION DEBRIS MAKING IT A FIRE AND TRIPPING HAZARDOUS CONDITION FOR ALL PERSONAL. REMEDY: CLEAN SITE A
#35721976J
Dec 9, 2026
PENDING
$2,500
Aug 21, 2026Unknown CLASS - 1
ATOI OBSERVED 3 CENTRAL AC CONDENSERS INSTALLED, 1 ON 4TH-FLR BALCONY & 2 LOCATED ON ROOF, AND 9 SPLIT AC UNITS INSTALLED & DISTRIBUTED BETWEEN 4TH, 5TH FLRS AT EXPO.3 & ROOF. ALL AC UNITS, ASSOCIATED WITH THEI
#39201358Z
Dec 9, 2026
PENDING
$2,500
Aug 21, 2026Construction CLASS - 1
UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. PSWO IN EFFECT ON THIS PROPERTY, HOWEVER OBSERVED CONSTRUCTION WORK IN PROGRESS ON 6TH AND 7TH FLOORS IN VIOLATION OF PSWO RELATED TO COMPLAINT #3
#35721975H
Dec 9, 2026
PENDING
$25,000
Aug 21, 2026Construction CLASS - 2
ATOI OBSERVED AT BUILDING REAR, EXPO.3, APRX 12FT X 5FT TWO MASONERY BALCONIES WITH METAL RAILINGS HAD BEEN CONSTRUCTED AND ATTACHED TO FACADE ON 4TH FLOOR. NO PERMIT ON FILE FOR THIS WORK. VIOLATION ISSUED., O
#39201374Z
Dec 9, 2026
PENDING
$1,250
Aug 21, 2026Construction CLASS - 1
ATOI OBSERVED 3 CENTRAL AC CONDENSERS INSTALLED, ONE ON 4TH-FLR BALCONY & TWO LOCATED ON ROOF OF 6TH FLOOR. NO MICHANICAL PERMIT FOUND IN DOB RECORDS. VIOLATION ISSUED., OBTAIN PERMIT
#39201363N
Dec 9, 2026
PENDING
$2,500
Aug 21, 2026Construction CLASS - 1
PSWO IN EFFICT ON THIS PROPERTY. ATOI OBSERVED SWO RELATED TO COMPLAINT #3A75657 POSTING HAD BEEN REMOVED FROM WHERE IT WAS POSTED ON MAIN ENTRY DOOR OF RESIDENTIAL PORTION OF THE BUILDING. VIOLATION ISUUED. SW
#39201348P
Dec 9, 2026
PENDING
$5,000
Aug 21, 2026Construction CLASS - 1
PSWO IN EFFECT ON THIS PROPERTY. HOWEVER, ATOI OBSERVED CONSTRUCTION WORK IN PROGRESS ON 6TH & 7TH FLOORS, IN VIOLATION OF PSWO RELATED TO COMPLAINT #3A75657. STOP ALL CONSTRUCTION WORK IMMEDIATELY, ONLY TO MAK
#39201345J
Dec 9, 2026
PENDING
$25,000
Aug 21, 2026Construction CLASS - 2
ATOI OBSERVED HANGING SCAFFOLD INSTALLED AT EXPO.4 OF THE BUIDING. NO PERMIT ON FILE FOR SCAFFOLD INSTALLATION. VIOLATION ISSUED., OBTAIN ALL PERMITS
#39201382Z
Dec 9, 2026
PENDING
$1,250
Aug 19, 2026Construction CLASS - 1
ATOI OBSERVED THE STRUCTURE ON THE ROOF BEING EXTENDED VERTICALLY 2 FLOORS ABOVE EXISTING BUILDING. WORK CONTINUES DESPITE PSWO ISSUED ON 08/12/2026., COMPLY WITH STOP WORK ORDER
#39201142J
Dec 9, 2026
PENDING
$10,000
Aug 12, 2026Construction CLASS - 2
PSWO ISSUED FOR WW/OP. ATOI APRX. 15' X 30' & 15' HIGH METAL & WOODEN STRUCTURE OBSERVED BEING ERECTED ON 6TH FLR OF ABOVE MIXED-USE BUILDING. WORK APRX 50% COMPLETE. NO PERMIT FOUND IN DOB RECORDS FOR THIS WOR
#39200329P
Oct 28, 2026
PENDING
$1,250
DOB (0)

None open.

DOB NOW Safety (3)
IssuedViolationStatus
Sep 25, 2026Benchmarking - LL84 FTF-EN-BENCH
FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
Active
Jun 22, 2026Benchmarking - LL84 FTF-EN-BENCH
FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4
Active
Jan 8, 2026Gas Piping - LL152 FTF-PL-PER
Cycle 2, Sub-cycle A (premises is in Community District 1)
Active
HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Sep 25, 2026DOB SafetyBenchmarking - LL84: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4Open
Sep 10, 2026ECBConstruction: UNLAWFUL CONTINUANCE OF WORK WHILE ON NOTICE OF A STOP WORK ORDER ISSUED ON 8/12/2026 VIO #039200329P. ATOI OBSERVED CONSTRUCTION WORK IN PROGRESS WITH SEVERAL WORKERS THROUGHOUT THE 5TH, 6TH AND 7TH FLOORS OFOpen
Aug 26, 2026ECBConstruction: AT TIME OF INSPECTION OBSERVED SEVERAL PUMP JACK SCAFFOLDING INSTALLED ON TOP OF ROOF AT EXPOSURE 1, USING STANDARD LADDERS AS PLATFORMS. THERE IS ACTIVE STOP WORK ORDER SINCE 8/12/2026., COMPLY WITH STOP WORKOpen
Aug 25, 2026ECBConstruction: AT TIME OF INSPECTION OBSERVED TWO MALE WORKERS WORKING ON ROOF EXTENSION. ACTIVE STOP WORK ORDER WAS ISSUED ON 8/19/2026., COMPLY WITH STOP WORK ORDEROpen
Aug 25, 2026ECBConstruction: UNLAWFUULY CONTINUED WORK WHILE ON NOTICE OR STOP WORK ORDER. ATOI OBSERVED CONSTRUCTION WORK IN PROGRESS ON ADDITION TO ROOF. WORKERS WORKING ON SUSPENDED SCAFFOLD. ALL IN VIOLATION OF PSWO ISSUED ON 8/12/2026Open
Aug 21, 2026ECBConstruction: OBSERVED ON 6TH AND 7TH FLOOR WORK CONTINUED AND HOUSE KEEPING NOT IN EFFECT WITH MULTIPLE AREAS WITH CONSTRUCTION DEBRIS MAKING IT A FIRE AND TRIPPING HAZARDOUS CONDITION FOR ALL PERSONAL. REMEDY: CLEAN SITE AOpen
Aug 21, 2026ECBUnknown: ATOI OBSERVED 3 CENTRAL AC CONDENSERS INSTALLED, 1 ON 4TH-FLR BALCONY & 2 LOCATED ON ROOF, AND 9 SPLIT AC UNITS INSTALLED & DISTRIBUTED BETWEEN 4TH, 5TH FLRS AT EXPO.3 & ROOF. ALL AC UNITS, ASSOCIATED WITH THEIOpen
Aug 21, 2026ECBConstruction: UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. PSWO IN EFFECT ON THIS PROPERTY, HOWEVER OBSERVED CONSTRUCTION WORK IN PROGRESS ON 6TH AND 7TH FLOORS IN VIOLATION OF PSWO RELATED TO COMPLAINT #3Open
Aug 21, 2026ECBConstruction: ATOI OBSERVED AT BUILDING REAR, EXPO.3, APRX 12FT X 5FT TWO MASONERY BALCONIES WITH METAL RAILINGS HAD BEEN CONSTRUCTED AND ATTACHED TO FACADE ON 4TH FLOOR. NO PERMIT ON FILE FOR THIS WORK. VIOLATION ISSUED., OOpen
Aug 21, 2026ECBConstruction: ATOI OBSERVED 3 CENTRAL AC CONDENSERS INSTALLED, ONE ON 4TH-FLR BALCONY & TWO LOCATED ON ROOF OF 6TH FLOOR. NO MICHANICAL PERMIT FOUND IN DOB RECORDS. VIOLATION ISSUED., OBTAIN PERMITOpen
Aug 21, 2026ECBConstruction: PSWO IN EFFICT ON THIS PROPERTY. ATOI OBSERVED SWO RELATED TO COMPLAINT #3A75657 POSTING HAD BEEN REMOVED FROM WHERE IT WAS POSTED ON MAIN ENTRY DOOR OF RESIDENTIAL PORTION OF THE BUILDING. VIOLATION ISUUED. SWOpen
Aug 21, 2026ECBConstruction: PSWO IN EFFECT ON THIS PROPERTY. HOWEVER, ATOI OBSERVED CONSTRUCTION WORK IN PROGRESS ON 6TH & 7TH FLOORS, IN VIOLATION OF PSWO RELATED TO COMPLAINT #3A75657. STOP ALL CONSTRUCTION WORK IMMEDIATELY, ONLY TO MAKOpen
Aug 21, 2026ECBConstruction: ATOI OBSERVED HANGING SCAFFOLD INSTALLED AT EXPO.4 OF THE BUIDING. NO PERMIT ON FILE FOR SCAFFOLD INSTALLATION. VIOLATION ISSUED., OBTAIN ALL PERMITSOpen
Aug 19, 2026ECBConstruction: ATOI OBSERVED THE STRUCTURE ON THE ROOF BEING EXTENDED VERTICALLY 2 FLOORS ABOVE EXISTING BUILDING. WORK CONTINUES DESPITE PSWO ISSUED ON 08/12/2026., COMPLY WITH STOP WORK ORDEROpen
Aug 12, 2026ECBConstruction: PSWO ISSUED FOR WW/OP. ATOI APRX. 15' X 30' & 15' HIGH METAL & WOODEN STRUCTURE OBSERVED BEING ERECTED ON 6TH FLR OF ABOVE MIXED-USE BUILDING. WORK APRX 50% COMPLETE. NO PERMIT FOUND IN DOB RECORDS FOR THIS WOROpen

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 2, 2026, 12:39 AM ET. BBL 3021307502.

Look up another building