3 floors · 12,775 sq ft · built 1910 · class K4 · owner of record: J & C 739 Realty Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 8 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 47 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 47 days | Keep the report on file (not filed with DOB) |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 24, 2026 | Construction CLASS - 1 OBSERVED AT CELLAR AND FIRST FLOOR, INSTALLED NEW H BEAMS AND WELDED. JACK POSTS INSTALLED ON THE FIRST FLOOR TO SHORE UP THE EXISTING ROOF. NO PERMIT FOR THIS STRUCTURAL WORK AT THE TIME OF INSPECTION., OBTAIN #39197622J | Oct 7, 2026 DEFAULT | $2,530 |
| Jul 24, 2026 | Construction CLASS - 1 OBSERVED ON THE SECOND FLOOR, THERE WAS NO PROTECTIVE RAILING AROUND THE STAIRS. GAPING HOLE OBSERVED IN THE FLOOR COVERED WITH PLYWOOD. BLACK GARBAGE BAGS PILED UP ON THE 2ND FLOOR ALONG WITH CONSTRUCTION DEBR #39197623L | Oct 7, 2026 DEFAULT | $2,530 |
| Jul 24, 2026 | Construction CLASS - 1 OBSERVED AT FIRST FLOOR AT FULLY OPERATIONAL SUPERMARKET, REMOVED FIRE STOPPINGS AT THE CEILING TO EXPOSE THE WOOD MEMBERS OF THE BUILDING. NO PERMIT FOR THIS WORK AT THE TIME OF INSPECTION., PROVIDE/MAINTAIN F #39197624N | Oct 7, 2026 DEFAULT | $2,530 |
| Issued | Violation | Status |
|---|---|---|
| Sep 24, 2026 | CONSTRUCTION UNPERMITTED/UNDOCUMENTED ST & FO WORK AT 3 STORY BRICK MASONRY MIXED- USED BUILDING. REMEDY:RETAIN NYS PE & GC TO STABILIZE AND SAFEGUARD BUILDING.COMMENCE STABILIZATION WORK UNDER PERMIT BY 10/30/26 #CE30804YU | DOB VIOLATION - ACTIVE |
| Sep 24, 2026 | CONSTRUCTION UNPERMITTED/UNDOCUMENTED ST & FO WORK AT 3 STORY BRICK MASONRY MIXED- USED BUILDING. REMEDY:RETAIN NYS PE & GC TO STABILIZE AND SAFEGUARD BUILDING. COMMENCE STABILIZATION WORK UNDER PERMIT BY 10/30/26 #CE30802YU | DOB VIOLATION - ACTIVE |
| Sep 24, 2026 | CONSTRUCTION UNPERMITTED/UNDOCUMENTED ST & FO WORK AT 3 STORY BRICK MASONRY MIXED- USED BUILDING.REMEDY:RETAIN NYS PE TO PERFORM MONTHLY STRUCTURAL STABILITY INSPECTIONS. FIRST REPORT BY 10/15/26 #CE30801YU | DOB VIOLATION - ACTIVE |
| Sep 24, 2026 | CONSTRUCTION UNPERMITTED/UNDOCUMENTED ST & FO WORK AT 3 STORY BRICK MASONRY MIXED- USED BUILDING. REMEDY:RETAIN NYS PE TO PERFORM MONTHLY STRUCTURAL STABILITY INSPECTIONS. FIRST REPORT BY 10/15/26 #CE30803YU | DOB VIOLATION - ACTIVE |
| Aug 21, 2026 | CONSTRUCTION *** CSE AUDIT ***. ATOI ON 07/24/26, BADGE #: 2647 OBSERVED UNPERMITTED, UNDOCUMENTED STRUCTURAL STEEL BEAMS, H BEAMS INSTALLED AT CELLAR AND 1ST FLOOR. ALSO JACK POSTS INSTALLED TO SHORE UP THE EXISTING ROOF. FIRE STOPPING REMOVED. PSWO ISSUED. #26-02082 | DOB VIOLATION - ACTIVE |
| Aug 21, 2026 | CONSTRUCTION ATOI ON 07/24/26 BADGE #: 2647 OBSERVED AT CELLAR AND FIRST FLOOR, INSTALLED NEW UNPERMITTED, UNDOCUMENTED H BEAMS AND WELDED. JACK POSTS INSTALLED ON THE FIRST FLOOR TO SHORE UP THE EXISTING ROOF. NO PERMIT FOR THIS STRUCTURAL WORK AT THE TIME OF INSPECTION. FULL VACATE #26-02087 | DOB VIOLATION - ACTIVE |
| Jul 24, 2026 | CONSTRUCTION OBSERVED AT CELLAR AND FIRST FLOOR, INSTALLED NEW UNPERMITTED, UNDOCUMENTED H BEAMS AND WELDED. JACK POSTS INSTALLED ON THE FIRST FLOOR TO SHORE UP THE EXISTING ROOF. NO PERMIT FOR THIS STRUCTURAL WORK AT THE TIME OF INSPECTION. COMPROMISING THE STABILITY OF THE BUILDING TO OCCUPY. #26-01851 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 8) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 8) | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 24, 2026 | DOB | CONSTRUCTION: UNPERMITTED/UNDOCUMENTED ST & FO WORK AT 3 STORY BRICK MASONRY MIXED- USED BUILDING. REMEDY:RETAIN NYS PE & GC TO STABILIZE AND SAFEGUARD BUILDING.COMMENCE STABILIZATION WORK UNDER PERMIT BY 10/30/26 | Open |
| Sep 24, 2026 | DOB | CONSTRUCTION: UNPERMITTED/UNDOCUMENTED ST & FO WORK AT 3 STORY BRICK MASONRY MIXED- USED BUILDING. REMEDY:RETAIN NYS PE & GC TO STABILIZE AND SAFEGUARD BUILDING. COMMENCE STABILIZATION WORK UNDER PERMIT BY 10/30/26 | Open |
| Sep 24, 2026 | DOB | CONSTRUCTION: UNPERMITTED/UNDOCUMENTED ST & FO WORK AT 3 STORY BRICK MASONRY MIXED- USED BUILDING.REMEDY:RETAIN NYS PE TO PERFORM MONTHLY STRUCTURAL STABILITY INSPECTIONS. FIRST REPORT BY 10/15/26 | Open |
| Sep 24, 2026 | DOB | CONSTRUCTION: UNPERMITTED/UNDOCUMENTED ST & FO WORK AT 3 STORY BRICK MASONRY MIXED- USED BUILDING. REMEDY:RETAIN NYS PE TO PERFORM MONTHLY STRUCTURAL STABILITY INSPECTIONS. FIRST REPORT BY 10/15/26 | Open |
| Aug 21, 2026 | DOB | CONSTRUCTION: *** CSE AUDIT ***. ATOI ON 07/24/26, BADGE #: 2647 OBSERVED UNPERMITTED, UNDOCUMENTED STRUCTURAL STEEL BEAMS, H BEAMS INSTALLED AT CELLAR AND 1ST FLOOR. ALSO JACK POSTS INSTALLED TO SHORE UP THE EXISTING ROOF. FIRE STOPPING REMOVED. PSWO ISSUED. | Open |
| Aug 21, 2026 | DOB | CONSTRUCTION: ATOI ON 07/24/26 BADGE #: 2647 OBSERVED AT CELLAR AND FIRST FLOOR, INSTALLED NEW UNPERMITTED, UNDOCUMENTED H BEAMS AND WELDED. JACK POSTS INSTALLED ON THE FIRST FLOOR TO SHORE UP THE EXISTING ROOF. NO PERMIT FOR THIS STRUCTURAL WORK AT THE TIME OF INSPECTION. FULL VACATE | Open |
| Jul 24, 2026 | DOB | CONSTRUCTION: OBSERVED AT CELLAR AND FIRST FLOOR, INSTALLED NEW UNPERMITTED, UNDOCUMENTED H BEAMS AND WELDED. JACK POSTS INSTALLED ON THE FIRST FLOOR TO SHORE UP THE EXISTING ROOF. NO PERMIT FOR THIS STRUCTURAL WORK AT THE TIME OF INSPECTION. COMPROMISING THE STABILITY OF THE BUILDING TO OCCUPY. | Open |
| Jul 24, 2026 | DOB | CONSTRUCTION: OBSERVED AT CELLAR AND FIRST FLOOR, INSTALLED NEW UNPERMITTED, UNDOCUMENTED H BEAMS AND WELDED. JACK POSTS INSTALLED ON THE FIRST FLOOR TO SHORE UP THE EXISTING ROOF. NO PERMIT FOR THIS STRUCTURAL WORK AT THE TIME OF INSPECTION. | Closed |
| Jul 24, 2026 | ECB | Construction: OBSERVED AT CELLAR AND FIRST FLOOR, INSTALLED NEW H BEAMS AND WELDED. JACK POSTS INSTALLED ON THE FIRST FLOOR TO SHORE UP THE EXISTING ROOF. NO PERMIT FOR THIS STRUCTURAL WORK AT THE TIME OF INSPECTION., OBTAIN | Open |
| Jul 24, 2026 | ECB | Construction: OBSERVED ON THE SECOND FLOOR, THERE WAS NO PROTECTIVE RAILING AROUND THE STAIRS. GAPING HOLE OBSERVED IN THE FLOOR COVERED WITH PLYWOOD. BLACK GARBAGE BAGS PILED UP ON THE 2ND FLOOR ALONG WITH CONSTRUCTION DEBR | Open |
| Jul 24, 2026 | ECB | Construction: OBSERVED AT FIRST FLOOR AT FULLY OPERATIONAL SUPERMARKET, REMOVED FIRE STOPPINGS AT THE CEILING TO EXPOSE THE WOOD MEMBERS OF THE BUILDING. NO PERMIT FOR THIS WORK AT THE TIME OF INSPECTION., PROVIDE/MAINTAIN F | Open |