7 floors · 177,455 sq ft · built 1918 · class I1 · owner of record: 699 92nd Street Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 68 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (6 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-04-24 (Accepted). Agency page | Dec 31, 2026 in 68 days | 1 of 6 without an accepted 2026 report yet |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. DOB facade records for this building show $669,060 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2027 in 120 days | No Cycle 10 report on record yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 177,455 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 189 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 189 days | Annual filing |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 10 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 799 days | Next cycle year 2028 |
| Energy audit and retro-commissioning (2034) Likely applies Local Law 87 · Calendar year 2034 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 6094). Agency page | Dec 31, 2034 in 2990 days | Next due 2034 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jan 16, 2024 | Local Law CLASS - 2 FAILURE TO ACCEPTABLE AMENDED CYCLE 8A AND 9A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIREDBY 28.302.5 FOR CONTROL #910086. REMEDY: FILE ACCEPTABLE REPORT. #37026475J | Jun 7, 2024 IN VIOLATION | $1,250 |
| Apr 1, 2021 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 8A REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL & APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#810085. AGG 1 PRIOR NOV 37010716P UNDER 2 #37021252J | Dec 27, 2021 IN VIOLATION | $3,125 |
| May 18, 2018 | Local Law CLASS - 2 FAILURE TO SUBMIT ACCEPTABLE 8TH ROUND REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALLS & APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#810086. REMEDY: SUBMIT REQUIREMENT TECHNICAL REPORT #37010716P | Nov 5, 2018 DEFAULT | $6,250 |
| Jan 27, 2010 | Construction CLASS - 2 FAILURE TO FILE AN ARCHITECT/ENGINEER REPORT CERTIFYING EXIT/DIRECTIONAL SIGNS ARE CONNECTED TO EMERGENCY POWER SOURCE/STORAGE BATTERY EQUIPMENT.REM:FILE ARCHITECT/ENGINEER REPORT. #36012541P | Aug 9, 2010 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Apr 22, 2025 | CONSTRUCTION FAILURE TO MAINTAIN BUILDING EXTERIOR FACADE AND/OR APPURTENANCES IN A CODE COMPLIANT MANNER.AT TIME OF INSPECTION,OBSERVED AT EXP1 WEST ELEV ,SPALLED AND CRACKS ON CORNICE.REMEDY:REPAIR AND/OR REPLACE #SR31002MA | DOB VIOLATION - ACTIVE |
| Dec 1, 2024 | FAILURE TO POST ENERGY GRADE/SCORE FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3 #2401398 | DOB VIOLATION - ACTIVE |
| Aug 2, 2024 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #00517 | DOB VIOLATION - ACTIVE |
| May 2, 2024 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #01061 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #02367 | DOB VIOLATION - ACTIVE |
| May 31, 2018 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017 #00636 | DOB VIOLATION - ACTIVE |
| Jan 31, 2013 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012 #01236 | DOB VIOLATION - ACTIVE |
| May 3, 2012 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #02330 | DOB VIOLATION - ACTIVE |
| Jun 16, 2010 | ELEVATOR #9027H342586 | DOB VIOLATION - ACTIVE |
| Jun 7, 1999 | ELEVATOR 3P5541 #9011/109297 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #28655 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #28654 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #28653 | DOB VIOLATION - ACTIVE |
| Apr 25, 1991 | LOCAL LAW 10/81 - ELEVATOR 6 #02803 | DOB VIOLATION - ACTIVE |
| Jun 29, 1990 | LOCAL LAW 10/81 - ELEVATOR 6 #04021 | DOB VIOLATION - ACTIVE |
| Oct 12, 1989 | LOCAL LAW 10/81 - ELEVATOR 1 #05231 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 10) | Active |
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 10) | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Feb 28, 2025 | Benchmarking - LL84 FTF-EN-BENCH FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 | Active |
| Dec 2, 2024 | Benchmarking - LL84 FTF-EN-BENCH FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 | Active |
| Dec 1, 2024 | Energy Grade - LL33 FTP-EN-EGRDEA | Active |
| Aug 2, 2024 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| May 2, 2024 | Benchmarking - LL84 FTF-EN-BENCH | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-INT-HP Violation Issued-Failure To File 2022 Internal Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-INT-HP Violation Issued-Failure To File 2021 Internal Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION | Active |
| May 31, 2018 | Facades FISPNRF FAILED TO FILE FISP CYCLE 8A TECHNICAL REPORT BY 02/21/2017 | Active |
| Jan 31, 2013 | Facades FISPNRF FAILED TO FILE FISP CYCLE 7A TECHNICAL REPORT BY 02/21/2012 | Active |
| May 3, 2012 | Benchmarking - LL84 FTF-EN-BENCH | Active |
None open.