class G7 · owner of record: Roseate Tern Landco Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
We couldn't find building attributes for this lot, so no deadlines are listed.
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 8, 2026 | Unknown CLASS - 2 BC 3304.4 AT INSPECTION OF THE BATTERY STORAGE FACILITY, EXCAVATION WORK WAS OBSERVED. AT EXPOSURE #1, EXCAVATION EXCEEDED FIVE FEET WITHOUT REQUIRED SUPPORT, SLOPING, OR PILING. THIS CONDITION CREATES A POTEN #39558886Y | Nov 17, 2026 PENDING | $2,500 |
| Sep 8, 2026 | Construction CLASS - 2 AT INSPECTION OF THE BATTERY STORAGE FACILITY, A CONSTRUCTION FENCE WAS OBSERVED. REVIEW OF APPROVED PLANS SHOWS THE FENCE SHALL FOLLOW THE APPROVED CURVED LINE. SECTIONAL FENCING AT THE CORNERS OF EXPOSURES #1 #39558885M | Nov 17, 2026 PENDING | $1,250 |
| Jul 2, 2026 | Construction CLASS - 1 UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. ATOI OBSERVED WORKERS HAVE INSTALLED A VAULT WHILE UNDER A PSWO UNDER COMPLAINT# 4A40100 THAT WAS ISSUED 07/01/2026. THERE SHOULD BE NO EARTHWORK #39194695R | Sep 8, 2026 ADMIT/IN-VIO | $0 |
| Jul 1, 2026 | Construction CLASS - 1 ATOI OBSERVED EARTHWORK IN PROGRESS. GAINED ACCESS, NOTICED THEY DUG / TRENCH OUT EXP 1 OF PROPERTY. APPROX DEPTH 5' FEET. ACTIVE PERMIT FOR GC - Q01221950-I1-GC-CX. EARTHWORK PERMIT IS REQUIRED PER CHAPTER 330 #39194614X | Sep 8, 2026 ADMIT/IN-VIO | $0 |
None open.
| Issued | Violation | Status |
|---|---|---|
| Aug 5, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| Aug 5, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 8, 2026 | ECB | Unknown: BC 3304.4 AT INSPECTION OF THE BATTERY STORAGE FACILITY, EXCAVATION WORK WAS OBSERVED. AT EXPOSURE #1, EXCAVATION EXCEEDED FIVE FEET WITHOUT REQUIRED SUPPORT, SLOPING, OR PILING. THIS CONDITION CREATES A POTEN | Open |
| Sep 8, 2026 | ECB | Construction: AT INSPECTION OF THE BATTERY STORAGE FACILITY, A CONSTRUCTION FENCE WAS OBSERVED. REVIEW OF APPROVED PLANS SHOWS THE FENCE SHALL FOLLOW THE APPROVED CURVED LINE. SECTIONAL FENCING AT THE CORNERS OF EXPOSURES #1 | Open |
| Aug 5, 2026 | DOB Safety | AEUHAZ: | Open |
| Aug 5, 2026 | DOB Safety | AEUHAZ: | Open |
| Jul 2, 2026 | ECB | Construction: UNLAWFULLY CONTINUED WORK WHILE ON NOTICE OF A STOP WORK ORDER. ATOI OBSERVED WORKERS HAVE INSTALLED A VAULT WHILE UNDER A PSWO UNDER COMPLAINT# 4A40100 THAT WAS ISSUED 07/01/2026. THERE SHOULD BE NO EARTHWORK | Open |
| Jul 1, 2026 | ECB | Construction: ATOI OBSERVED EARTHWORK IN PROGRESS. GAINED ACCESS, NOTICED THEY DUG / TRENCH OUT EXP 1 OF PROPERTY. APPROX DEPTH 5' FEET. ACTIVE PERMIT FOR GC - Q01221950-I1-GC-CX. EARTHWORK PERMIT IS REQUIRED PER CHAPTER 330 | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 28, 2026, 8:20 AM ET. BBL 4030250034.