| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 8 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 68 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 68 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 68 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 84 days | Annual |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Aug 9, 2024 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING WALLS & APPURTENANCES. AT TIME OF INSPECTION OBSERVED EXPO#3 4TH FL. BALCONY DRYWALL/STUCCO CEILING HAS COLLAPSED, SECTION APPROX: 8'X4'. OBSERVED WATER PENETRATION FROM 5TH FL. BAL #39121480M | Nov 20, 2024 DEFAULT | $12,500 |
| Apr 18, 2022 | Construction CLASS - 1 SIDEWALK SHED NOT AS PER APPROVED PLANS.NOTE:AT TIME OF INSPECTION OF NEW 5 STORY BUILDING OBSERVED SHED & PIPE SCAFFOLD INSTALLED AT EXP #1 #4 SUPPORTED PIPE SCAFFOLD CONTRARY TO PLANS UPON REVIEW SWS AT EXP # #35646151H | Oct 26, 2022 IN VIOLATION | $625 |
| Apr 18, 2022 | Construction CLASS - 1 SUPPORTED SCAFFOLD DOES NOT CONFORM TO APPROVED PLANS NOTE:AT TIME OF INSPECTION OF NEW 5 STORY ACTIVE JOBSITE OBSERVED SUPPORTED SCAFFOLD INSTALLED ON SIDEWALK SHED WITH 5 OR MORE WORKING PLATFORM AT A TIME OF #35646152J | Oct 26, 2022 IN VIOLATION | $625 |
| Oct 29, 2021 | Construction CLASS - 1 SEC. BC 3309.1 FAILURE TO PROTECT OR ADEQUATELY PROTECT ADJOINING PROPERTIES DURING CONSTRUCTION OR DEMOLITION OPERATION. AT TIME OF INSPECTION OF A PROPODED 5 STY NEW BLDG UNDER CONSTRUCTION(4TH FL COMPLETED,5 #35504181P | Mar 9, 2022 IN VIOLATION | $2,500 |
| Oct 29, 2021 | Site Safety CLASS - 1 FAILURE TO MAINTAIN/DISPLAY ON SITE DOCUMENTS REQUIRED BY CHAPTER 33. AT TIME OF INSPECTION OF A PROPOSED 5 STY NEW BLDG UNDER CONSTRUCTION (4TH FL COMPLETED,5TH WORKING),I OBSERVED A SIDEWALK SHED(SWS)AT EXP#1 #35504183Z | Mar 9, 2022 IN VIOLATION | $1,250 |
| Oct 29, 2021 | Construction CLASS - 1 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS &/OR APPROVEDAMENDMENTS. AT TIME OF INSPECTION OF A PROPOSED 5 STY NEW BLDG UNDER CONSTRUCTION(4TH FL COMPLETED,5TH WORKING),I OBSERVED THE 1ST FL C-JOIS #35504180N | Mar 9, 2022 IN VIOLATION | $2,500 |
| Oct 29, 2021 | Construction CLASS - 2 WORK DOES NOT CONFORM TO APPROVED CONSTRUCTION DOCUMENTS &/OR APPROVEDAMENDMENTS. AT TIME OF INSPECTION OF A PROPOSED 5 STY NEW BLDG UNDER CONSTRUCTION,I OBSERVED THAT A PART OF THE CONSTRUCTION FENCE AT EXP#4 #35504182R | Mar 9, 2022 IN VIOLATION | $625 |
| Sep 21, 2021 | Construction CLASS - 1 WORK DOES NOT CONFORM TO APPROVED P.E. CONSTRUCTION DOCUMENTS.NOTED:AT TIME OF INSPECTION AT ACTIVE CONSTRUCTION SITE OBSERVED STEEL STAIRCASE AND STEEL FRAMING UP TO 4TH FLOOR LEVEL. REVIEW OF APPROVED P.E. CO #35588875K | Sep 19, 2022 DEFAULT | $6,250 |
| May 24, 2021 | Construction CLASS - 2 3304.4.4 FAIL TO MAINTAIN GUARDRAILS AROUND EXCAVATION SITE WHEN 6' ORGREATER IN DEPTH. AT THE TIME OF INSPECTION I OBSERVED SUPPORT OF EXCAVATION BEING DONE. THE BUILDING IS AT FOUNDATION PHASE. THE COMPETENT #35547374L | Oct 6, 2021 DEFAULT | $3,125 |
| Nov 23, 2020 | Construction CLASS - 2 FAILURE TO POST OR PROPERTY POST PERMIT FOR WORK AT PREMISES.NOTED:AT TIME OF INSPECTION ACTIVE PERMITS ON FILE FOR FENCE AND SIDEWALK SHED NOT POSTED AT WORKSITE IN A READILY VISIBLE OR OBSERVABLE PLACE.REM:PO #35410947M | Apr 7, 2021 DEFAULT | $1,562 |
| Issued | Violation | Status |
|---|---|---|
| Oct 16, 2024 | FAIL TO CERTIFY CLASS 1 FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION #00105 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 16, 2024 | AEUHAZ FTC-AEU-HAZ | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 24, 2026, 2:07 PM ET. BBL 3012197504.