Bronx · Block 3070 · Lot 34 · 10457

611 East 180 Street

1 floors · 6,630 sq ft · built 1925 · class K1 · owner of record: Pad Partnership Corp

8open violations
$3,750ECB/OATH penalties owed
0HPD class C (immediately hazardous)
43dto Gas piping inspection (2026 cycle)

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Gas piping inspection (2026 cycle) Likely applies
Local Law 152 · During 2026
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 6 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2026
in 43 days
Due this year
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 43 days
Keep the report on file (not filed with DOB)

Open violations

ECB / OATH (8) · $3,750 owed
IssuedViolationHearingBalance
Nov 5, 2026Construction CLASS - 2
OCCUPANCY CONTRARY. I OBSERVED THE PREMISES WAS CHANGED FROM A USE GROUP 6 FACTORY AS PER C OF O #27561 INTO A USE GROUP 4 PLACE OF WORSHIP. NO PERMIT ON FILE, DISCONTINUE ILLEGAL OCCUPANCY OR AMEND C OF O; SUB
#39210695Y
Jan 15, 2027
PENDING
$1,250
Nov 5, 2026Construction CLASS - 1
OPERATION OF A PLACE OF ASSEMBLY WITHOUT A CURRENT CERTIFICATE OF OPERATION. I OBSERVED THE PREMISES SET UP AND ARRANGED AS A PLACE OF WORSHIP WITH 63 CHAIRS SET UP AND AROUND 50 CHAIRS STACKED INTO TWO SECTION
#39210689H
Jan 15, 2027
PENDING
$2,500
Oct 6, 2016Construction CLASS - 1
FAILURE TO MAINTAIN BLDG WALLS OR APPURTENANCES. RE-ISSUE NOV#35197505P ISSUED ON 8/3/16 FOR FAILURE TO MAINTAIN BLDG WALLS OR APPURTENANCES@ EXP#1(EAST 180TH ST)& EXP#4(HUGHES AVE)OBSERVED CRACK/MISSING MORTAR
#35214179K
Dec 2, 2016
WRITTEN OFF
$0
Aug 3, 2016Construction CLASS - 1
FAILURE TO MAINTAIN EXTERIOR WALLS & APPURTENANCES. NOTED: @ TIME OF INSP, @ EXP#1 (E 180 ST) & EXP#4 (HUGHES AVE) I OBSERVED CRACKED/MISSING MORTAR JOINTS, MISSING BRICK, LOOSE BRICK & LARGE AREAS OF BULGING B
#35197505P
Sep 30, 2016
WRITTEN OFF
$0
Jul 10, 2009Construction CLASS - 1
FAILURE TO MAINTAIN BRICK WORK AT FACADE IS IN DISREPAIR AND BURNED OUT AT BRICK AT GROUND LEVEL W/ SETTING AND SEPERATED CRACKS AND MORTAR MISSING ON TRUST SIDE & HUGHES AVE SIDE REMEDY: MAINTAIN BLDG WALL
#34793488R
Dec 18, 2009
WRITTEN OFF
$0
Dec 23, 2008Construction CLASS - 1
FAILURE TO MAINTAIN EXTERIOR BRICK WALL. NOTED: AT FRONT EXPOSER SEVERE BRICK DAMAGE WITH BRICK COLUMN BOWED. ENTIRE FRONT FACADE SETTING MAKE SAFE!! REM: REPLACE ENTIRE FRONT FACADE FORTHWITH. OBTAIN ALL NECCE
#34742651H
Feb 20, 2009
WRITTEN OFF
$0
Jun 12, 2008Construction Hazardous
FAILURE TO MAINTAIN HAZ DEFECT SOUTH WEST END OF STRUCTURE HAS BOWED BRICK COLUMN CRACKED FACADE UN KEYED BRICK LEANING FOLDING GATE METAL IS LEANING TOWARD PUBLIC SIDEWALK THIS VIOLATION CONCERNS THE 2 COMMERC
#34647342Z
Aug 1, 2008
WRITTEN OFF
$0
Jul 1, 1998Plumbing Non-Hazardous
DRAINAGE SYSTEM NOT IN ACCORDANCE W/R S 16, IN THAT THERE ARE NO LEGALMEANS OF CONVEYING STROM WATER FROM ROOF TO DRAINAGE SYSTEM. HOLES HAVE BEEN CUT INTO MASONARY PARAPIT, STROM WATER TO DUMP ONTO ADJACENT
#34149793X
Jun 11, 1999
WRITTEN OFF
$0
DOB (0)

None open.

DOB NOW Safety (0)

None open.

HPD (0)

None open.

Issued in the last 120 days

DateSourceWhatNow
Nov 5, 2026ECBConstruction: OCCUPANCY CONTRARY. I OBSERVED THE PREMISES WAS CHANGED FROM A USE GROUP 6 FACTORY AS PER C OF O #27561 INTO A USE GROUP 4 PLACE OF WORSHIP. NO PERMIT ON FILE, DISCONTINUE ILLEGAL OCCUPANCY OR AMEND C OF O; SUBOpen
Nov 5, 2026ECBConstruction: OPERATION OF A PLACE OF ASSEMBLY WITHOUT A CURRENT CERTIFICATE OF OPERATION. I OBSERVED THE PREMISES SET UP AND ARRANGED AS A PLACE OF WORSHIP WITH 63 CHAIRS SET UP AND AROUND 50 CHAIRS STACKED INTO TWO SECTIONOpen

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 18, 2026, 6:34 AM ET. BBL 2030700034.