Manhattan · Block 2250 · Lot 58 · 10034

600 West 218 Street

6 floors · 108 apartments · 124,174 sq ft · built 1936 · class D7 · owner of record: 600 West 218th Street Associates, L.L.C.

66open violations
$15,655ECB/OATH penalties owed
6HPD class C (immediately hazardous)
46dto Bedbug annual filing

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 46 days
Keep the report on file (not filed with DOB)
Bedbug annual filing Applies
Local Law 69 · December 1 to 31 each year
What this is

Owners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page

Dec 31, 2026
in 46 days
Annual
Annual notice: window guards and lead paint Applies
HPD / Health Code · January 1 to 16 each year
What this is

Deliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page

Jan 16, 2027
in 62 days
Annual
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 124,174 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 167 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 167 days
Annual filing
Annual property registration Applies
HPD registration · September 1 each year
What this is

Residential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page

Sep 1, 2027
in 290 days
Registered through 2027-09-01
Gas piping inspection (2027 cycle) Likely applies
Local Law 152 · During 2027
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 12 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2027
in 411 days
Next cycle year 2027
Energy audit and retro-commissioning (2030) Likely applies
Local Law 87 · Calendar year 2030
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 2250). Agency page

Dec 31, 2030
in 1507 days
Next due 2030
Annual boiler inspection (1 boiler) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-04-27 (Accepted). Agency page

On file2026 reports accepted

Open violations

ECB / OATH (10) · $15,655 owed
IssuedViolationHearingBalance
Oct 30, 2026Construction CLASS - 2
AT TIME OF INSPECTION OBSERVED THAT PLYWOOD AND STUD ERECTED FAR FROM ELECTRIC STOVE HOWEVER FAILURE TO SUBMIT CERTIFICATE OF CORRECTION FOR VIOLATION #39180460P ISSUED ON 03-14-2026, FILE A CERTIFICATE OF CORR
#39210117M
Jan 7, 2027
PENDING
$1,250
Sep 1, 2026Construction CLASS - 2
B263 FAILURE TO COMPLY WITH THE COMMISSIONER ORDER TO FILE A CERT.OF CORRECTION WITH THE DEPT.OF BUILDINGS FOR VIOLATION #039153799K, FILE A CERTIFICATE OF CORRECTION; FILE A CERT,OF CORRECTION
#39202531H
Nov 5, 2026
DEFAULT
$1,280
Jul 16, 2025Plumbing CLASS - 2
FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. EXHAUST DISCHARGE MUST BE NO CLOSER THAN 10' FROM BUILDING OPENINGS AS PER MC 501.2 AND RS 13-1 SEC. 2-2.1.4. NOTED: KITCHEN EXHAUST VENT FOR GROUND FLR RE
#39153799K
Sep 25, 2025
IN VIOLATION
$0
Jul 16, 2025Construction CLASS - 1
FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. NOTED: AT TIME OF INSPECTION - WOOD PLYWOOD & STUDS OBSERVED ERECTED AT KITCHEN STOVE AREA CREATING A FIRE HAZARD CONDITION., REPAIR AND/REPLACE
#39153798Z
Dec 11, 2026
PENDING
$2,500
Dec 2, 2024Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONERS ORDER TO FILE A CERT OF CORRECTION WITH DOB. NO CERT OF CORRECTION FILED FOR ECB VIO #39071572R ISSUED 10/06/2022 AND HEARING DATE PASSED. ISSUED AT AGG II DUE TO CONTINUED
#39131742M
Mar 6, 2025
IN VIOLATION
$6,250
Apr 15, 2024Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONERS ORDER TO FILE A CERT OF CORRECTION WITH DOB. NO CERT OF CORRECTION FILED FOR ECB VIO #39071572R ISSUED 10/06/2022 AND HEARING DATE PASSED. ISSUED AT AGG I DUE TO CONTINUED N
#39111675N
Jun 20, 2024
IN VIOLATION
$3,125
Dec 29, 2023Plumbing CLASS - 2
FAILURE TO MAINTAIN. BUILDING IN CODE COMPLIANT MANNER. EXHAUST DISCHARGE MUST BE NO CLOSER THAN 10 FEET FROM BUILDING OPENINGS AS PER MC 501.2 AND RS 13-1 SEC. 2-2.1.4. NOTED: AT EXPOSURE #2 EXHAUST DISCHARGE
#39102455R
Mar 7, 2024
IN VIOLATION
$0
Jun 29, 2023Construction CLASS - 2
FAILURE TO COMPLY WITH COMMISSIONERS ORDER TO FILE A CERT OF CORRECTION FOR ECB #39071572R. NOTED NO CERT OF CORRECTION FILED FOR ECB VIOLATION #39071572R ISSUED 10/06/2022 WITH HEARING DATE PASSED AND EXHAUST
#39089410J
Sep 7, 2023
IN VIOLATION
$1,250
Oct 6, 2022Plumbing CLASS - 2
FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER. EXHAUST DISCHARGE MUST BE NO CLOSER THAN 10 FEET FROM BUILDING OPENINGS PER MC 501.2, MC 401.5.2. GROUND FLOOR RESTAURANT "INWOOD FARM" HAS KITCHEN EXHAUST SYS
#39071572R
May 4, 2023
IN VIOLATION
$0
Nov 6, 2020Construction CLASS - 2
OCCUPANCY CONTRARY TO THAT ALLOWED BY THE CERTIFICATE OF OCCUPANCY OR BUILDINGS DEPARTMENT RECORDS. EATING AND DRINKING ESTABLISHMENT WITH FULL BAR AND KITCHEN AND SEATING FOR APPROX 25 PERSONS LOCATED ON GROUN
#39031668P
Jun 17, 2021
IN VIOLATION
$0
DOB (1)
IssuedViolationStatus
May 1, 1991ELEVATOR
DEVICE #1P20389
#0252C01
VIOLATION UNSERVED ECB-ACTIVE
DOB NOW Safety (8)
IssuedViolationStatus
Oct 10, 2025Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction
Active
Oct 11, 2024Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction
Active
Oct 23, 2023Elevators FTC-VT-CAT1-CO
Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction
Active
Oct 2, 2023Elevators FTC-VT-PER-CO
Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction
Active
HPD (47) · C 6 · B 41 · A 0
IssuedClassViolationCorrect by
Jul 17, 2025C§ 27-2005 ADM CODE & 309 M/D LAW ABATE THE NUISANCE CONSISTING OF CANOPY OBSTRUCTING DROP LADDER TO FULLY EXTEND TO GROUND AT BUILDING FRONT AT FIRE ESCAPEJul 23, 2025
Aug 10, 2023BApt 6D · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 6D, 6th STORY, 3rd APARTMENT FROM WEST AT NORTH , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 1B · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 1B, 1st STORY, 2nd APARTMENT FROM NORTH AT EAST , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 6P · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 6P, 6th STORY, 1st APARTMENT FROM EAST AT SOUTH , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 5N · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 5N, 5th STORY, 2nd APARTMENT FROM SOUTH AT WESTSep 14, 2023
Aug 10, 2023BApt 3J · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 3J, 3rd STORY, 3rd APARTMENT FROM EAST AT SOUTH , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 1A · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 1A, 1st STORY, 1st APARTMENT FROM EAST AT SOUTH , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 6R · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 6R, 6th STORY, 2nd APARTMENT FROM NORTH AT EAST , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 6C · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 6C, 6th STORY, 1st APARTMENT FROM NORTH AT EAST , SECTION ''Sep 14, 2023
Aug 10, 2023BApt LN · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT BSMT-APT LN, 2nd BSMT-APT FROM SOUTH AT WESTSep 14, 2023
Aug 10, 2023BApt LO · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT BSMT-APT LO, 1st BSMT-APT FROM SOUTH AT WEST , SECTION ''600'', Sep 14, 2023
Aug 10, 2023BApt 1N · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 1N, 1st STORY, 2nd APARTMENT FROM SOUTH AT WESTSep 14, 2023
Aug 10, 2023BApt 4B · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 4B, 4th STORY, 2nd APARTMENT FROM NORTH AT EAST , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 4E · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 4E, 4th STORY, 2nd APARTMENT FROM SOUTH AT WEST , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 3N · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 3N, 3rd STORY, 2nd APARTMENT FROM SOUTH AT WEST , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 2N · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 2N, 2nd STORY, 2nd APARTMENT FROM SOUTH AT WESTSep 14, 2023
Aug 10, 2023BApt 5J · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 5J, 5th STORY, 3rd APARTMENT FROM EAST AT SOUTH , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 5A · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 5A, 5th STORY, 1st APARTMENT FROM EAST AT SOUTH , SECTION ''Sep 14, 2023
Aug 10, 2023BApt 3H · § 27-2056.7, 27-2056.17 AND 27-2056.8 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 3H, 3rd STORY, 1st APARTMENT FROM SOUTH AT WEST , SECTION ''Sep 14, 2023
Aug 3, 2023C§ 27-2056.4(H) AND 27-2056.17 ADM CODE -CORRECT FAILURE TO PROVIDE TO THE DEPARTMENT WITHIN 45 DAYS OF DEMAND ALL RECORDS REQUIRED TO BE MAINTAINED BY OWNER PURSUANT TO LOCAL LAW 1 OF 2004 RELATED TO LEAD-BASED PAINT NOTICES, INSPECTIONS AND REMEDIATION/ABATEMENT ACTIVITIES.Aug 7, 2023
Aug 3, 2023C§ 27-2056.4 ADM CODE- CORRECT FAILURE TO NOTIFY OCCUPANTS AND/OR TO INVESTIGATE LEAD-BASED PAINT HAZARDS.Aug 7, 2023
Oct 12, 2021CApt 2M · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF MICE IN THE ENTIRE APARTMENT LOCATED AT APT 2M, 3rd STORY, 1st APARTMENT FROM SOUTH AT WESTNov 7, 2021
Aug 23, 2021CApt 2O · § 27-2056.6 ADM CODE - CORRECT THE LEAD-BASED PAINT HAZARD - PAINT THAT TESTED POSITIVE FOR LEAD CONTENT AND THAT IS PEELING OR ON A DETERIORATED SUBSURFACE - USING WORK PRACTICES SET FORTH IN 28 RCNY §11-06(B)(2) 1st DOOR FROM NORTH AT EAST WALL IN THE FOYER LOCATED AT APT 2O, 2nd STORY, 1st APARTMSep 16, 2021
Aug 23, 2021BApt 6E · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 6E, 6th STORY, 2nd APARTMENT FROM SOUTH AT WESTSep 27, 2021
Aug 23, 2021BApt 3J · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 3J, 3rd STORY, 3rd APARTMENT FROM EAST AT SOUTHSep 27, 2021
Aug 23, 2021BApt 1N · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 1N, 1st STORY, 2nd APARTMENT FROM SOUTH AT WESTSep 27, 2021
Aug 23, 2021BApt 2J · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 2J, 2nd STORY, 3rd APARTMENT FROM EAST AT SOUTHSep 27, 2021
Aug 23, 2021BApt 6J · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 6J, 6th STORY, 3rd APARTMENT FROM EAST AT SOUTHSep 27, 2021
Aug 12, 2021BApt LO · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT BSMT-APT LO, 1st BSMT-APT FROM WEST AT NORTHSep 16, 2021
Aug 12, 2021BApt LN · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT BSMT-APT LN, 2nd BSMT-APT FROM SOUTH AT WESTSep 16, 2021
Aug 10, 2021BApt 3H · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 3H, 3rd STORY, 1st APARTMENT FROM SOUTH AT WESTSep 14, 2021
Aug 10, 2021BApt 4K · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 4K, 4th STORY, 2nd APARTMENT FROM EAST AT SOUTHSep 14, 2021
Aug 10, 2021BApt 4J · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 4J, 4th STORY, 3rd APARTMENT FROM EAST AT SOUTHSep 14, 2021
Aug 10, 2021BApt 4E · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 4E, 4th STORY, 2nd APARTMENT FROM SOUTH AT WESTSep 14, 2021
Aug 10, 2021BApt 6B · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 6B, 6th STORY, 2nd APARTMENT FROM NORTH AT EASTSep 14, 2021
Aug 10, 2021BApt 2B · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 2B, 2nd STORY, 2nd APARTMENT FROM NORTH AT EASTSep 14, 2021
Jul 6, 2021BApt 5N · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 5N, 5th STORY, 2nd APARTMENT FROM SOUTH AT WESTAug 10, 2021
Jul 2, 2021BApt 6N · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 6N, 6th STORY, 2nd APARTMENT FROM SOUTH AT WESTAug 6, 2021
Jul 2, 2021BApt 2M · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 2M, 2nd STORY, 1st APARTMENT FROM WEST AT NORTHAug 6, 2021
Jul 2, 2021BApt 6P · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 6P, 6th STORY, 1st APARTMENT FROM EAST AT SOUTHAug 6, 2021
Jul 2, 2021BApt 2N · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 2N, 2nd STORY, 2nd APARTMENT FROM SOUTH AT WESTAug 6, 2021
Jul 2, 2021BApt 2P · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 2P, 2nd STORY, 1st APARTMENT FROM EAST AT SOUTHAug 6, 2021
Jul 2, 2021BApt 5L · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 5L, 5th STORY, 2nd APARTMENT FROM WEST AT NORTHAug 6, 2021
Jul 2, 2021BApt 3N · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 3N, 3rd STORY, 2nd APARTMENT FROM SOUTH AT WESTAug 6, 2021
Jul 2, 2021BApt 3O · § 27-2056.7 AND 27-2056.17 ADM CODE - CERTIFY COMPLIANCE WITH LEAD-BASED PAINT HAZARD CONTROL REQUIREMENTS DURING PERIOD OF UNIT VACANCY BY SUBMITTING REQUIRED SUPPORTING DOCUMENTATION AND AFFIDAVITS FOR APARTMENT LOCATED AT APT 3O, 3rd STORY, 1st APARTMENT FROM SOUTH AT WESTAug 6, 2021
Jun 25, 2021CApt GR · § 27-2056.7 ADM CODE: CORRECT FAILURE TO PROVIDE TO THE DEPARTMENT WITHIN 45 DAYS OF DEMAND ALL RECORDS REQUIRED TO BE MAINTAINED BY OWNER PURSUANT TO LOCAL LAW 1 OF 2004 RELATED TO LEAD-BASED PAINT NOTICES, INSPECTIONS AND REMEDIATION/ABATEMENT ACTIVITIES.Jun 29, 2021
May 2, 2018BApt 5K · § 27-2005 HMC:TRACE AND REPAIR THE SOURCE AND ABATE THE NUISANCE CONSISTING OF MOLD ... ON THE CEILING IN THE BATHROOM LOCATED AT APT 5K, 5th STORY, 2nd APARTMENT FROM EAST AT SOUTHJun 6, 2018

Issued in the last 120 days

DateSourceWhatNow
Oct 30, 2026ECBConstruction: AT TIME OF INSPECTION OBSERVED THAT PLYWOOD AND STUD ERECTED FAR FROM ELECTRIC STOVE HOWEVER FAILURE TO SUBMIT CERTIFICATE OF CORRECTION FOR VIOLATION #39180460P ISSUED ON 03-14-2026, FILE A CERTIFICATE OF CORROpen
Sep 1, 2026ECBConstruction: B263 FAILURE TO COMPLY WITH THE COMMISSIONER ORDER TO FILE A CERT.OF CORRECTION WITH THE DEPT.OF BUILDINGS FOR VIOLATION #039153799K, FILE A CERTIFICATE OF CORRECTION; FILE A CERT,OF CORRECTIONOpen

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 15, 2026, 1:07 AM ET. BBL 1022500058.