7 floors · 1444 apartments · 1,136,208 sq ft · built 1954 · class D3 · owner of record: Nyc Housing Authority
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 64 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 64 days | Annual |
| Annual boiler inspection (8 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-01-15 (Accepted). Agency page | Dec 31, 2026 in 64 days | 1 of 8 without an accepted 2026 report yet |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 80 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 1,136,208 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 185 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 185 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | No current registration found |
| Facade inspection report (Cycle 10C) Applies Local Law 11 / FISP · Feb 21, 2027 to Feb 21, 2029 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 1, 2 or 3 are in sub-cycle 10C. Agency page | Feb 21, 2029 in 847 days | Filing window not open yet |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1160 days | Next cycle year 2029 |
| Energy audit and retro-commissioning (2032) Likely applies Local Law 87 · Calendar year 2032 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 4292). Agency page | Dec 31, 2032 in 2256 days | Next due 2032 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 17, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. OBSERVED SPALLING PAINT FROM METER DAMAGE AT FRONT ENTRANCE, CLASS ROOM 1, 3 AND HALLWAY INSIDE UPN CENTER. REMEDY: REPAIR AND/OR REPLACE. #35720806M | Sep 8, 2025 POP/IN-VIO | $0 |
| Jul 17, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. EXTERIOR WALLS HAVE BECOME POROUS AND PIPE LEAKING IN HALLWAY WELL. CAUSING DAMAGE TOINTERIOR WALL OF CLASS ROOM AND HALLWAY. REMEDY: REPAIR AND/OR REPLACE #35720807Y | Sep 8, 2025 POP/IN-VIO | $0 |
| Aug 19, 2024 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING EXTERIOR WALL(S) OR APPURTENANCES. NOTE:-AT THE TIME OF INSPECTION OBSERVED AT EXPO #1, 2 AND 3 NORTH, EAST ANDSOUTH ELEVATION DAMAGED/DETERIORATING MORTAR JOINT AT SEVERAL LOCATION #35718439R | Sep 4, 2025 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #15037 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00537 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01367 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #15035 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION #15036 | DOB VIOLATION - ACTIVE |
| May 7, 2025 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS #00045 | DOB VIOLATION - ACTIVE |
| May 7, 2025 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS #00046 | DOB VIOLATION - ACTIVE |
| May 7, 2025 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS #00047 | DOB VIOLATION - ACTIVE |
| May 7, 2025 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS #00043 | DOB VIOLATION - ACTIVE |
| May 7, 2025 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS #00049 | DOB VIOLATION - ACTIVE |
| May 7, 2025 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS #00044 | DOB VIOLATION - ACTIVE |
| May 7, 2025 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS #00048 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01453 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION #13752 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION #00570 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION #13753 | DOB VIOLATION - ACTIVE |
| Aug 1, 2024 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) FAILURE TO CORRECT SWARMP CONDITIONS #00206 | DOB VIOLATION - ACTIVE |
| Aug 1, 2024 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) FAILURE TO CORRECT SWARMP CONDITIONS #00205 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #01358 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #01362 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #00719 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #00718 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #01359 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #00717 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #01361 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #00722 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #00723 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #00721 | DOB VIOLATION - ACTIVE |
| Feb 22, 2024 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 #00720 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #01764 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #38525 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION #18432 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #04109 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #02977 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION #00611 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION #04227 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION #00659 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION #03084 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION #01869 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01707 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00558 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00613 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION #00634 | DOB VIOLATION - ACTIVE |
| Feb 20, 2020 | FACADE SAFETY PROGRAM NYCHA UNSAFE CYCLE 8 REPORT FILED #HAZ88805 | DOB VIOLATION - ACTIVE |
| Jan 8, 2020 | FACADE SAFETY PROGRAM #HAZ88760 | DOB VIOLATION - ACTIVE |
| Jun 1, 2016 | NYCHA ELEVATOR PERIODIC INSPECTION/TEST FAILURE TO PERFORM CATEGORY 5 INSPECTION #00056 | DOB VIOLATION - ACTIVE |
| Mar 3, 2015 | HIGH PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE 2013 ANNUAL HIGH PRESSURE BOILER INSPECTION #00609 | DOB VIOLATION - ACTIVE |
| Nov 30, 2007 | LOCAL LAW 11/98 - FACADE #NRF45835 | DOB VIOLATION - ACTIVE |
| Aug 8, 2002 | LOCAL LAW 11/98 - FACADE #NRF53226 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #19236 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #19237 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #19233 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #21341 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #19234 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #19235 | DOB VIOLATION - ACTIVE |
| Jul 1, 1992 | LL10/80-LOCAL LAW 10/80 - FACADE #0414NRF | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION | Active |
| May 7, 2025 | Facades FISPFCS CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| May 7, 2025 | Facades FISPFCS CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| May 7, 2025 | Facades FISPFCS CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| May 7, 2025 | Facades FISPFCS CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| May 7, 2025 | Facades FISPFCS CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| May 7, 2025 | Facades FISPFCS CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| May 7, 2025 | Facades FISPFCS CYCLE 9 FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| Sep 23, 2024 | Boiler HBLVIO Violation Issued-Failure To File 2023 Internal High Pressure Inspection Report | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler LBLVIO Violation Issued-Failure To File 2023 External Low Pressure Inspection Report | Active |
| Sep 23, 2024 | Boiler LBLVIO Violation Issued-Failure To File 2023 External Low Pressure Inspection Report | Active |
| Aug 1, 2024 | Facades FISPFCS FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| Aug 1, 2024 | Facades FISPFCS FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Feb 22, 2024 | Facades FISPNRF FAILED TO FILE FISP CYCLE 9C TECHNICAL REPORT BY 2/21/2024 | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Feb 20, 2020 | Facades FISP NYCHA UNSAFE CYCLE 8 REPORT FILED | Active |
| Jan 8, 2020 | Facades FISP CYCLE 8C UNSAFE REPORT FILED | Active |
| Apr 30, 2019 | Facades FISPNRF FAILED TO FILE FISP CYCLE 8C TECHNICAL REPORT BY 02/21/2019 | Active |
| Mar 3, 2015 | Boiler HBLVIO VIOLATION ISSUED FOR FAILURE TO FILE 2013 ANNUAL HIGH PRESSURE BOILER INSPECTION | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Mar 6, 2019 | A | Apt 10E · § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT THE WEST WALL IN THE PRIVATE HALLWAY LOCATED AT APT 10E, 1st STORY, 1st APARTMENT FROM NORTH AT EAST | Jun 9, 2019 |
| Mar 6, 2019 | A | Apt 10E · § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT THE NORTH WALL IN THE 1st ROOM FROM NORTH LOCATED AT APT 10E, 1st STORY, 1st APARTMENT FROM NORTH AT EAST | Jun 9, 2019 |
| Mar 6, 2019 | A | Apt 10E · § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT THE EAST WALL, WEST WALL IN THE FOYER LOCATED AT APT 10E, 1st STORY, 1st APARTMENT FROM NORTH AT EAST | Jun 9, 2019 |
| Mar 6, 2019 | A | Apt 10E · § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT THE SOUTH WALL IN THE 3rd ROOM FROM NORTH LOCATED AT APT 10E, 1st STORY, 1st APARTMENT FROM NORTH AT EAST | Jun 9, 2019 |
| Mar 6, 2019 | A | Apt 10E · § 27-2013 ADM CODE PAINT WITH LIGHT COLORED PAINT TO THE SATISFACTION OF THIS DEPARTMENT THE WEST WALL IN THE BATHROOM LOCATED AT APT 10E, 1st STORY, 1st APARTMENT FROM NORTH AT EAST | Jun 9, 2019 |
| Aug 25, 2016 | B | Apt 6D · § 27-2018 ADMIN. CODE: ABATE THE NUISANCE CONSISTING OF ROACHES LOCATED AT APT 6D, 6th STORY | Sep 29, 2016 |
| Aug 25, 2016 | B | Apt 6D · § 27-2026, 2027 HMC: PROPERLY REPAIR THE SOURCE AND ABATE THE EVIDENCE OF A WATER LEAK AT CEILING IN THE BATHROOM LOCATED AT APT 6D, 6th STORY, 1st APARTMENT FROM EAST AT SOUTH | Sep 29, 2016 |
| Aug 25, 2016 | B | Apt 6D · § 27-2005 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE INTERCOM LOCATED AT APT 6D, 6th STORY, 1st APARTMENT FROM EAST AT SOUTH | Sep 29, 2016 |
| Aug 25, 2016 | B | § 27-2005 ADM CODE PROPERLY REPAIR THE BROKEN OR DEFECTIVE LOCKING DEVICE AT ENTRANCE DOOR AT LOBBY, 1st STORY | Sep 29, 2016 |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 28, 2026, 1:19 PM ET. BBL 3042920061.