| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 47 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 108,169 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 168 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 168 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1143 days | Next cycle year 2029 |
| Energy audit and retro-commissioning (2034) Likely applies Local Law 87 · Calendar year 2034 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 3534). Agency page | Dec 31, 2034 in 2969 days | Next due 2034 |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-03-17 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Mar 5, 2026 | Construction CLASS - 2 REISSUE ECB#35691761H FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED:2ND FLOOR NEW BUILDING ROOF MISSING/PEELING INSULATION PANELS AROUND ROOF DRAIN AREA.REM:REPAIR AND/OR REPLACE. #35728999Y | Mar 23, 2026 POP/IN-VIO | $0 |
| Mar 5, 2026 | Construction CLASS - 2 REISSUE ECB #35691758R. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANTMANNER. NOTED: CLASSROOM DOORS #408, #407, #207, #205, #105 AND SMOKE DOOR BY EXIT #3 IN DISREPAIR. DOORS ARE CRACKED AND SPLITTING. REMEDY: #35722301X | Mar 20, 2026 POP/IN-VIO | $0 |
| Mar 5, 2026 | Construction CLASS - 2 REISSUE ECB #35691759Z. EXIT DOOR NOT SELF-CLOSING. NOTED: EXIT DOOR #3, #6, #7 AND #10 NOT SELF-CLOSING. REMEDY: REPAIR/REPLACE DOOR. #35722300Y | Mar 20, 2026 POP/IN-VIO | $0 |
| Mar 5, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: CRACKED AND SPALLING PLASTER ON WALLS. STAIR C-2ND FLOOR. REMEDY: REPAIR AND/OR REPLACE. #35722302H | Mar 20, 2026 POP/IN-VIO | $0 |
| Feb 28, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED INTERIOR FPSC DOOR AT CLASSROOM #408, 406, 304, 207, 209, 105 AND EXIT #3 INTERIOR SMOKE DOOR IN DISREPAIR. MENTIONED DOORS ARE CRACKED, SPLITTING WI #35691758R | Apr 18, 2025 POP/IN-VIO | $0 |
| Feb 28, 2025 | Construction CLASS - 2 EXIT DOOR NOT SELF-CLOSING. NOTED EXTERIOR DOORS AT EXIT #3 AND 7 NOT PROPERLY SELF CLOSING WHEN TESTED. REMEDY: REPAIR/REPLACE DOOR. #35691759Z | Apr 18, 2025 POP/IN-VIO | $0 |
| Feb 28, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN IN CODE-COMPLIANT MANNER. NOTED AT FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED AT EAST 2ND FLOOR ROOF(NEW BUILDING SIDE) MISSING AND PEELING SECTIONS OF COAT INSULATION GRAV #35691761H | Apr 18, 2025 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #03859 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 29, 2026 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2022 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2018 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2018 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Aug 25, 2023 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Report | Active |
| Aug 25, 2023 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Report | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Affirmation of Correction | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)