11 floors · 250,190 sq ft · built 1975 · class I1 · owner of record: Rutland Nursing Home Inc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 9 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 66 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 66 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 250,190 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 187 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 187 days | Annual filing |
| Facade inspection report (Cycle 10C) Applies Local Law 11 / FISP · Feb 21, 2027 to Feb 21, 2029 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 1, 2 or 3 are in sub-cycle 10C. DOB facade records for this building show $1,010,100 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2029 in 849 days | Filing window not open yet |
| Energy audit and retro-commissioning (2032) Likely applies Local Law 87 · Calendar year 2032 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 4602). Agency page | Dec 31, 2032 in 2258 days | Next due 2032 |
| Annual boiler inspection (3 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-02-10 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Mar 8, 2022 | Elevators CLASS - 1 UPON INSPECTION DEVICE WAS FOUND OUT OF SERVICE. RESTORE TO SERVICE IMMEDIATELY AND CONTACT NYCDOB AT EIR@BUILDINGS.NYC.GOV FOR A COMPLETE INSPECTION. #39057671L | Jul 13, 2022 DEFAULT | $0 |
| Oct 8, 2021 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 7C & 8C REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL#809938. AGG1: PRIOR NOV#37019109Y UNDER 28 #37022304R | Apr 13, 2022 DEFAULT | $0 |
| Jun 3, 2020 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 7C AND 8C REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADE REPORT REQUIRED BY 28-302.5 FOR CONTROL#809938.AGG1:PRIOR NOV37012232H UNDER 28-3 #37019109Y | Nov 4, 2020 ADMIT/IN-VIO | $0 |
| Aug 1, 2018 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8C REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL # 809938. REMEDY: FILE ACCEPTABLE REPORT. #37012232H | Mar 11, 2019 ADMIT/IN-VIO | $0 |
| Jan 11, 2018 | Construction CLASS - 2 FAILURE TO MAINTAIN EXTERIOR BUILDING FACADE AND APPURTENANCES.NOTE:@ THE TIME OF INSPECTION OBSERVE EAST ELEVATION EXPOSURE #4(COURTYARD AREA)CRACK/CHIPPING/SPALLING BRICKS ON 9TH/10TH FL @ SEVERAL LOCATION @ #35265284M | Mar 5, 2018 STIPULATION/IN-VIO | $0 |
| Oct 31, 2015 | Construction CLASS - 2 FAILURE TO MAINTAIN FACADE AND APPURTENANCES. NOTED: AT EAST AND WEST EXPOSURES CRACKED, BROKEN AND DISLODGED BRICKWORK WAS OBSERVED, ESPECIALLY AT 2 BRICK THICK DECORATIVE RIBS RUNNING VERTICALLY.RMDY:MAINTAIN #35133416K | Dec 21, 2015 IN VIOLATION | $0 |
| Oct 31, 2015 | Construction CLASS - 2 REMOVAL OF SAFETY MEASURES W/O DEPT APPROVAL. NOTED: AT FACADE AT WESTAND EAST EXPOSURES CRACKED,BROKEN AND LOOSE BRICKWORK MASONRY WAS OBSERVED.AT TIME OF INSPECTION FACADE IS DECLARED AS "UNSAFE" REQUIRING SA #35133415Z | Dec 21, 2015 IN VIOLATION | $0 |
| May 29, 2015 | Local Law CLASS - 2 FAILURE TO FILE AN ACCEPTABLE AMENDED CYCLE 7 REPORT TO THIS DEPT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW FISP REPORT. REMEDY: FILE AN AMENDED REPORT FOLLOWING REMEDIAL REPAIR #36027734N | Sep 21, 2015 DEFAULT | $0 |
| Dec 23, 2014 | Elevators CLASS - 2 61G07,39X10,40I10,23X10,100I10,12L10,67M07,40R09,16L10,37M07,100B10. 61G-PROVIDE PROPER FUSE IN TEH MAINLINE; 39X-REPAIR RUN BOX ON TOP FO THE CAR; 40I-REPAIR M.R. FLOOR; 23X-REPAIR LIGHT;100I-REPAIR DAMAGED #38233545Y | Feb 9, 2015 IN VIOLATION | $0 |
| Nov 28, 2014 | Local Law CLASS - 2 FAILURE TO FILE AN ACCEPTABLE AMENDED CYCLE 7 REPORT TO THIS DEPT INDICATING CORRECTION OF UNSAFE CONDITION DESCRIBED IN INITIAL LOCAL LAW FISP REPORT.REM:FILE AN AMENDED REPORT FOLLOWING REMEDIAL REPAIRS OF TH #36026584M | Mar 16, 2015 DEFAULT | $0 |
| Issued | Violation | Status |
|---|---|---|
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01344 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01346 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01345 | DOB VIOLATION - ACTIVE |
| Apr 22, 2025 | CONSTRUCTION FAILURE TO MAINTAIN BUILDING IN A CODE COMPLIANT MANNER. OBSERVED MISSING CRACK GLASS PANELS IN MULTIPLE LOCATION AT MULIPLE LEVEL OF ALL EXPOSURE. DAMAGE WEATHERED WINDOW FRAMES. REMEDY: REPAIR AND OR REPLACE #SR30901DO | DOB VIOLATION - ACTIVE |
| Dec 1, 2024 | FAILURE TO POST ENERGY GRADE/SCORE FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3 #2401288 | DOB VIOLATION - ACTIVE |
| Oct 30, 2024 | CONSTRUCTION FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. NOTE: AT TIME OF INSPECTION OBSERVED MISSING/CRACKED GLASS PANELS IN MULTIPLE LOCATIONS ON MULTIPLE FACADE AT ALL EXPOSURES OBSERVED DAMAGED WINDOW FRAMES AT ALL FACADES REMEDY: REPAIR AND/OR REPLACE #SR30903DO | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01431 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01430 | DOB VIOLATION - ACTIVE |
| Jun 3, 2024 | CONSTRUCTION FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.OBSERVED BROKEN/ MISSING/GLASS PANE AT EXP1,2,& 4 WITH DEFECTED WINDOW FRAMES.ROOF AREA :DAMAGED PARAPET WALL.OPEN JOINTS.DAMAGED FACADE AT M/C ROOM WITH STEP CRACKS AT SKY LIGHT.REMEDY:REPAIR AND/OR REPLACE #SR0902NS | DOB VIOLATION - ACTIVE |
| Dec 1, 2023 | FAILURE TO POST ENERGY GRADE/SCORE FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3 #2301290 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #02350 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #04679 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #04482 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #03426 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #02143 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION #01058 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION #04421 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION #03278 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION #02367 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION #02239 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION #04773 | DOB VIOLATION - ACTIVE |
| May 2, 2023 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #00991 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01755 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00619 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00618 | DOB VIOLATION - ACTIVE |
| Apr 22, 2023 | FAILURE TO SUBMIT EER FAILURE TO SUBMIT AN EER PER AD. CODE SEC. 28-308.4 IN 2022 #10327 | DOB VIOLATION - ACTIVE |
| Dec 1, 2022 | FAILURE TO POST ENERGY GRADE/SCORE FAILURE TO DISPLAY ENERGY EFFICIENCY SCORE AND ENERGY EFFICIENCY GRADE AS PER ADCODE SEC. 28-309.12.3 #2201323 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION #00709 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00675 | DOB VIOLATION - ACTIVE |
| Sep 6, 2019 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2017 CAT 1 INSP/TST TST #04559 | DOB VIOLATION - ACTIVE |
| Apr 5, 2019 | ELEVATOR ANNUAL INSPECTION / TEST VIOLATION ISSUED TO ELEVATOR - FAILURE TO FILE CATEGORY 1 2017 INSPECTION/TEST #01882 | DOB VIOLATION - ACTIVE |
| Jan 26, 2018 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST #05507 | DOB VIOLATION - ACTIVE |
| Jan 26, 2018 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST #05509 | DOB VIOLATION - ACTIVE |
| Jan 26, 2018 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2016 CAT 1 INSP/TST #05508 | DOB VIOLATION - ACTIVE |
| Aug 2, 2017 | FAILURE TO BENCHMARK FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 #00377 | DOB VIOLATION - ACTIVE |
| Jul 19, 2017 | FACADE SAFETY PROGRAM #HAZ86961 | DOB VIOLATION - ACTIVE |
| Jan 3, 2017 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2015 CAT 1 INSP/TST #05644 | DOB VIOLATION - ACTIVE |
| May 30, 2014 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST #05538 | DOB VIOLATION - ACTIVE |
| May 30, 2014 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST #05537 | DOB VIOLATION - ACTIVE |
| May 30, 2014 | (OTHER BLDGS TYPES) - ELEVATOR AFFIRMATION OF CORRECTION VIO ISSUED TO ELEVATOR - FAIL TO CORRECT DEFECTS ON 2012 CAT 1 INSP/TST #05539 | DOB VIOLATION - ACTIVE |
| May 22, 2014 | CONSTRUCTION DUE TO LIGHTING STRIKING PARAPET BRICKS & MASONSY HAS DETACHED & FALLE N TO THEW GROUND. DAMAGED AREA APPROX. 8' X 4' AT ROOOF LEVEL #ER0905RWS | DOB VIOLATION - ACTIVE |
| Dec 31, 2013 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 7C TECHNICAL REPORT BY 02/21/2013 #01123 | DOB VIOLATION - ACTIVE |
| Nov 6, 2013 | LL11/98-LOCAL LAW 11/98 - FACADE CYCLE 7 UNSAFE REPORT FILED #HAZ74619 | DOB VIOLATION - ACTIVE |
| Jan 21, 2010 | CONSTRUCTION FAILURE TO MAINTAIN EXTERIOR BUILDING WALLS SLIGHTLY DEFECTIVE BRICK A ND MORTAR IN VARIOUSAREAS OF EXTERIOR FACADE THRU OUT ALSO MINOR CRACK S OBSERVED REMEDY; MAKE SITE SAFE MAKE REPAIRS/ REPLACEMENTS MAINTAIN PREMISES AS PER DOB CODE AND REGULATION #0902SH | DOB VIOLATION - ACTIVE |
| Jan 6, 1998 | ELEVATOR #LL108102316 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #03132 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #25454 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #31605 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #25455 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #25453 | DOB VIOLATION - ACTIVE |
| Apr 25, 1991 | LOCAL LAW 10/81 - ELEVATOR 10 #02671 | DOB VIOLATION - ACTIVE |
| Apr 25, 1991 | ELEVATOR #LL108102673 | DOB VIOLATION - ACTIVE |
| Dec 18, 1989 | PUBLIC ASSEMBLY #1101B | DOB VIOLATION - ACTIVE |
| Oct 12, 1989 | PUBLIC ASSEMBLY #1101B | DOB VIOLATION - ACTIVE |
| Oct 12, 1989 | PUBLIC ASSEMBLY #1102B | DOB VIOLATION - ACTIVE |
| Oct 12, 1989 | ELEVATOR #LL108104986 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Sep 25, 2026 | Benchmarking - LL84 DQ-EN-BENCH FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for HP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for HP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2025 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Affirmation of Correction | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION | Active |
| Sep 23, 2024 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-INT-HP Violation Issued-Failure To File 2019 Internal Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2018 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-INT-HP Violation Issued-Failure To File 2020 Internal Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for HP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2018 External Inspection Affirmation of Correction for HP Device | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Aug 11, 2023 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2019 Cat1 Test Report | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 30, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2018 INTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION | Active |
| Jun 20, 2023 | Boiler HBLVIO VIOLATION ISSUED-FAILURE TO FILE 2019 INTERNAL HGH PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Apr 25, 2023 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Dec 1, 2022 | Energy Grade - LL33 FTP-EN-EGRDEA | Active |
Showing 60 of 98. Full list on the agency site.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 25, 2026 | DOB Safety | Benchmarking - LL84: FAILURE TO FILE BENCHMARKING REPORT OF ENERGY USE AS PER AD. CODE SEC. 28-309.4 | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)