6 floors · 1188 apartments · 987,444 sq ft · built 1948 · class D3 · owner of record: Nyc Housing Authority
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 51 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 51 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 67 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 987,444 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 172 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 172 days | Annual filing |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | No current registration found |
| Energy audit and retro-commissioning (2028) Likely applies Local Law 87 · Calendar year 2028 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 7978). Agency page | Dec 31, 2028 in 782 days | Next due 2028 |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 18 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1147 days | Next cycle year 2029 |
| Annual boiler inspection (4 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-03-31 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910426.REM:SUBMIT ACCEPTABLE REQUIRED T #37027427J | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910415.REM:SUBMIT ACCEPTABLE REQUIRED T #37027414K | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910418.REM:SUBMIT ACCEPTABLE REQUIRED T #37027422K | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910407.REM:SUBMIT ACCEPTABLE REQUIRED T #37027411P | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910409.REM:SUBMIT ACCEPTABLE REQUIRED T #37027424Y | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910425.REM:SUBMIT ACCEPTABLE REQUIRED T #37027418H | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910423.REM:SUBMIT ACCEPTABLE REQUIRED T #37027428L | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910413.REM:SUBMIT ACCEPTABLE REQUIRED T #37027417X | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910408.REM:SUBMIT ACCEPTABLE REQUIRED T #37027420R | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910421.REM:SUBMIT ACCEPTABLE REQUIRED T #37027412R | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910419.REM:SUBMIT ACCEPTABLE REQUIRED T #37027429N | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910412.REM:SUBMIT ACCEPTABLE REQUIRED T #37027419J | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910411.REM:SUBMIT ACCEPTABLE REQUIRED T #37027415M | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910417.REM:SUBMIT ACCEPTABLE REQUIRED T #37027423M | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910410.REM:SUBMIT ACCEPTABLE REQUIRED T #37027425X | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910422.REM:SUBMIT ACCEPTABLE REQUIRED T #37027426H | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910406.REM:SUBMIT ACCEPTABLE REQUIRED T #37027416Y | Jun 10, 2024 POP/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#910414.REM:SUBMIT ACCEPTABLE REQUIRED T #37027413Z | Jun 10, 2024 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00172 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00186 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00174 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00170 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00173 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00177 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00189 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00175 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00181 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00180 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00185 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00192 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00182 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00171 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00183 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00188 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00176 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00178 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00179 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00187 | DOB VIOLATION - ACTIVE |
| May 23, 2013 | LL11/98-LOCAL LAW 11/98 - FACADE FAILURE TO MAINTAIN A/CS. ON 5/5/13, AN UNSAFE NOTICES FISP3 DOCUMENT WAS SUBMITTED TO FLSP/DOB UNIT BY ANTHONY STASIO, P.E. STATING BUILDING TENANTS HAD INSTALLED WINDOW-MOUNTED A/CS IN A NON-COMPLIANT MANNER. THE A/CS ARE TO BE INSTALLED PER MANUFACTURERS INSTRUCTION AN BUILDING OWNER REQUIREMENTS #5140407LL | DOB VIOLATION - ACTIVE |
| May 23, 2013 | LL11/98-LOCAL LAW 11/98 - FACADE FAILURE TO MAINTAIN A/CS. ON 5/5/13, AN UNSAFE NOTICES FISP3 DOCUMENT WAS SUBMITTED TO FLSP/DOB UNIT BY ANTHONY STASIO, P.E. STATING BUILDING TENANTS HAD INSTALLED WINDOW-MOUNTED A/CS IN A NON-COMPLIANT MANNER. THE A/CS ARE TO BE INSTALLED PER MANUFACTURERS INSTRUCTION AN BUILDING OWNER REQUIREMENTS #510406LL | DOB VIOLATION - ACTIVE |
| May 23, 2013 | LL11/98-LOCAL LAW 11/98 - FACADE FAILURE TO MAINTAIN A/CS. ON 5/5/13, AN UNSAFE NOTICES FISP3 DOCUMENT WAS SUBMITTED TO FLSP/DOB UNIT BY ANTHONY STASIO, P.E. STATING BUILDING TENANTS HAD INSTALLED WINDOW-MOUNTED A/CS IN A NON-COMPLIANT MANNER. THE A/CS ARE TO BE INSTALLED PER MANUFACTURERS INSTRUCTION AN BUILDING OWNER REQUIREMENTS #510412LL | DOB VIOLATION - ACTIVE |
| May 23, 2013 | LL11/98-LOCAL LAW 11/98 - FACADE FAILURE TO MAINTAIN A/CS. ON 5/5/13, AN UNSAFE NOTICES FISP3 DOCUMENT WAS SUBMITTED TO FLSP/DOB UNIT BY ANTHONY STASIO, P.E. STATING BUILDING TENANTS HAD INSTALLED WINDOW-MOUNTED A/CS IN A NON-COMPLIANT MANNER. THE A/CS ARE TO BE INSTALLED PER MANUFACTURERS INSTRUCTION AN BUILDING OWNER REQUIREMENTS #510420LL | DOB VIOLATION - ACTIVE |
| Apr 25, 2001 | CONSTRUCTION #17PVO1 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Jun 27, 2012 | B | Apt 3C · § 27-2005 HMC:TRACE AND REPAIR THE SOURCE AND ABATE THE NUISANCE CONSISTING OF MOLD ... COVERING APPROXIMATELY 20 SQUARE FEET AT NORTH WALL IN THE 4th ROOM FROM EAST AT NORTH LOCATED AT APT 3C, 3rd STORY, APARTMENT AT WEST | Aug 1, 2012 |
| Jun 27, 2012 | C | Apt 3C · § 27-2005 HMC:TRACE AND REPAIR THE SOURCE AND ABATE THE NUISANCE CONSISTING OF MOLD ... ABAT\E THE MOLD COVERING APPROXIMATELY 30 SQUARE FEET AT WALLS AND CEILING IN THE BATHROOM LOCATED AT APT 3C, 3rd STORY, APARTMENT AT WEST | Jul 3, 2012 |
| Jun 25, 2012 | B | Apt 3C · § 27-2046.1 HMC: REPAIR OR REPLACE THE CARBON MONOXIDE DETECTING DEVICE(S). DEFECTIVE LOCATED AT APT 3C, 3rd STORY, APARTMENT AT WEST | Jul 30, 2012 |
| Jun 25, 2012 | B | Apt 3C · § 27-2045 ADM CODE REPAIR OR REPLACE THE SMOKE DETECTOR MISSING LOCATED AT APT 3C, 3rd STORY, APARTMENT AT WEST | Jul 30, 2012 |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 10, 2026, 9:22 AM ET. BBL 3079780001.