7 floors · 29,760 sq ft · built 2001 · class N2 · owner of record: Alma Rangel Gardenshousing Development F Und Corp.
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 47 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 29,760 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 168 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 168 days | Annual filing |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 10 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 778 days | Next cycle year 2028 |
| Annual boiler inspection (3 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-01-30 (Accepted). Agency page | On file | 2026 reports accepted |
| Facade inspection report (Cycle 10A) Applies Local Law 11 / FISP · Feb 21, 2025 to Feb 21, 2027 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 4, 5, 6 or 9 are in sub-cycle 10A. Agency page | On file | Cycle 10 filing on record: SAFE (2026-09-16) |
None open.
None open.
None open.
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Oct 10, 2023 | B | Apt 7D · § 27-2005 ADM CODE REPAIR THE BROKEN OR DEFECTIVE PLASTERED SURFACES AND PAINT IN A UNIFORM COLOR THE CEILING IN CLOSET IN THE PRIVATE HALLWAY LOCATED AT APT 7D, 7th STORY, 1st APARTMENT FROM WEST AT NORTH | Nov 14, 2023 |
| Oct 10, 2023 | B | Apt 7D · § 27-2005 ADM CODE REPAIR THE ROOF SO THAT IT WILL NOT LEAK OVER CEILING IN THE PRIVATE HALLWAY LOCATED AT APT 7D, 7th STORY, 1st APARTMENT FROM WEST AT NORTH | Nov 14, 2023 |
| Oct 10, 2023 | B | Apt 7D · § 27-2005 ADM CODE REPAIR THE ROOF SO THAT IT WILL NOT LEAK OVER CEILING IN THE BATHROOM LOCATED AT APT 7D, 7th STORY, 1st APARTMENT FROM WEST AT NORTH | Nov 14, 2023 |
| Oct 10, 2023 | B | Apt 7D · § 27-2005 ADM CODE REPAIR THE ROOF SO THAT IT WILL NOT LEAK OVER CEILING IN THE 1st ROOM FROM NORTH AT WEST LOCATED AT APT 7D, 7th STORY, 1st APARTMENT FROM WEST AT NORTH | Nov 14, 2023 |
| Oct 10, 2023 | B | Apt 7D · § 27-2005 ADM CODE REPAIR THE ROOF SO THAT IT WILL NOT LEAK OVER CEILING IN THE 1st ROOM FROM NORTH AT EAST LOCATED AT APT 7D, 7th STORY, 1st APARTMENT FROM WEST AT NORTH | Nov 14, 2023 |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 14, 2026, 3:25 PM ET. BBL 1017350012.