5 floors · 18 apartments · 6,870 sq ft · built 1900 · class C4 · owner of record: 521 E. 5th Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 43 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 43 days | Annual |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-09-15 (Accepted). Agency page | Dec 31, 2026 in 43 days | 2 of 2 without an accepted 2026 report yet |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 59 days | Annual |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 774 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Dec 10, 2025 | Construction CLASS - 1 FAILURE TO MAINTAIN MULTIPLE IMPROPERLY INSTALLED A/C UNITS WITH INADEQUATELY SECURED BRACKETS, CREATING OBSTRUCTIONS ALONG FACADE EXPOSURE 1. CONDITIONS INCLUDE 1 UNIT AT THE 2ND STORY, 2 AT THE 3RD STORY, 1 A #39169960Y | Feb 19, 2026 DEFAULT | $12,500 |
| Dec 10, 2025 | Construction CLASS - 1 NO ACCESS GAINED. NO CERTIFICATE OF CORRECTION ON FILE AS PER COMMISSIONER'S REQUEST FOR CLASS 1 WORK WITHOUT A PERMIT VIOLATION #35576198Y ISSUED 2/17/2022 FOR WORKERS INSTALLING A RUBBER ROOF USING TORCH . NO #39169940R | Feb 19, 2026 DEFAULT | $12,500 |
| Dec 10, 2025 | Construction CLASS - 2 UNABLE TO GAIN ACCESS. CERTIFICATE OF CORRECTION NOT SUBMITTED FOR CLASS 1 FAILURE TO MAINTAIN VIOLATION #35576199X ISSUED ON 2/17/2022 FOR EXCESSIVE ROOF DECK MATERIALS REMOVED AND PLACED ALL AROUND TO INCLUDE #39169939J | Feb 19, 2026 DEFAULT | $6,250 |
| May 16, 2024 | Construction CLASS - 1 FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION# 35576198Y ISSUED ON 02/17/2022 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01. FAILURE TO FILE FOR D #39114583J | Jan 9, 2025 IN VIOLATION | $2,500 |
| May 16, 2024 | Construction CLASS - 1 FAILURE TO COMPLY WITH THE COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION# 35576199X ISSUED ON 02/17/2022 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01. FAILURE TO SAFEGUARD #39114589K | Jan 9, 2025 IN VIOLATION | $2,500 |
| Dec 12, 2023 | Construction CLASS - 1 UNLAWFUL ACTS: FAILURE TO COMPLY WITH COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION #35576199X ISSUED ON 02/17/2022 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01 (INADEQUATE #39101175H | Mar 21, 2024 IN VIOLATION | $2,500 |
| Dec 12, 2023 | Construction CLASS - 1 UNLAWFUL ACTS: FAILURE TO COMPLY WITH COMMISSIONERS ORDER CONTAINED IN SUMMONS/VIOLATION #35576198Y ISSUED ON 02/17/2022 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01 (WORK WITHO #39101142L | May 2, 2024 IN VIOLATION | $2,500 |
| Feb 17, 2022 | Construction CLASS - 1 FAILURE TO MAINTAIN ADEQUATE HOUSEKEEPING NOTE:AT TIME OF INSPECTION OBSERVED WORK BEING PERFORMED ON THE ROOF PUTTING DOWN A RUBBOR ROOF.THEY REMOVED ROOF DECK MATERIALS TO GET TO THE ROOF PILES OF 2X4 MATERIA #35576199X | Nov 17, 2022 IN VIOLATION | $2,500 |
| Feb 17, 2022 | Construction CLASS - 1 WORK WITHOUT A PERMIT.NOTE AT TIME OF INSPECTION OBSERVED WORKERS INSTALLING A RUBBER ROOF USING A TORCH.NO PERMIT FOUND ON THE DEPARTMENT OF BUILDINGS WEBSITE.REMEDY:COMPLY WITH NOTICE OF VIOLATION. #35576198Y | Nov 17, 2022 IN VIOLATION | $2,500 |
| Issued | Violation | Status |
|---|---|---|
| May 11, 2022 | FAIL TO CERTIFY CLASS 1 FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION #00018 | DOB VIOLATION - ACTIVE |
| May 11, 2022 | FAIL TO CERTIFY CLASS 1 FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION #00019 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Mar 17, 2026 | AEUHAZ FTC-AEU-HAZ | Active |
| May 11, 2022 | AEUHAZ FTC-AEU-HAZ | Active |
| May 11, 2022 | AEUHAZ FTC-AEU-HAZ | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| May 6, 2025 | B | Apt A0 · § 27-2005 HMC: PROPERLY REPAIR OR REPLACE THE BROKEN OR DEFECTIVE UPPER ESCUTCHEN PLATE AT STEAM RISER AT CEILING IN THE 1st ROOM FROM NORTH LOCATED AT APT A0, 1st STORY, 1st APARTMENT FROM NORTH AT EAST | Jun 10, 2025 |
| May 6, 2025 | B | Apt A0 · § 27-2005 HMC: PROPERLY REPAIR OR REPLACE THE BROKEN OR DEFECTIVE UPPER ESCUTCHEN PLATE AT STEAM RISER AT CEILING IN THE 3rd ROOM FROM NORTH LOCATED AT APT A0, 1st STORY, 1st APARTMENT FROM NORTH AT EAST | Jun 10, 2025 |
| May 6, 2025 | B | Apt A0 · § 27-2005 HMC: PROPERLY REPAIR OR REPLACE THE BROKEN OR DEFECTIVE UPPER ESCUTCHEN PLATE AT STEAM RISER AT CEILING IN THE 4th ROOM FROM NORTH LOCATED AT APT A0, 1st STORY, 1st APARTMENT FROM NORTH AT EAST | Jun 10, 2025 |