11 floors · 44,792 sq ft · built 2006 · class RC · owner of record: Unavailable Owner
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 4 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 49 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 49 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 44,792 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 170 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 170 days | Annual filing |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. DOB facade records for this building show $174,000 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2028 in 466 days | No Cycle 10 report on record yet |
| Annual boiler inspection (5 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-08-10 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Oct 19, 2022 | Local Law CLASS - 2 FAILURE TO SUBMIT ACCEPTABLE REQUIRED CYCLE 8B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL & APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL 813985.AGG1:PRIOR NOV 37021441Z UNDER 28-302 #37023135J | Feb 16, 2023 DEFAULT | $10,000 |
| Jun 1, 2021 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 8B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL & APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#813985. REMEDY: SUBMIT ACCEPTABLE REQUIRE #37021441Z | Feb 24, 2022 IN VIOLATION | $1,250 |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #01122 | DOB VIOLATION - ACTIVE |
| Apr 6, 2018 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT #03643 | DOB VIOLATION - ACTIVE |
| Apr 6, 2018 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT #03644 | DOB VIOLATION - ACTIVE |
| Apr 6, 2018 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT #03645 | DOB VIOLATION - ACTIVE |
| Apr 6, 2018 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT #03646 | DOB VIOLATION - ACTIVE |
| Apr 6, 2018 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT #03647 | DOB VIOLATION - ACTIVE |
| Oct 19, 2017 | PLUMBING THE BOROUGH COMMISSIONER HAS ISSUED 15 DAY LETTER OF INTENT TO REVOKE ALL APPROVALS AND PERMITS UNDER APPLICATION #140706136 DUE TO AUDIT OBJECTIONS. STOP ALL PLUMBING WORK UNDER ABOVE CITED APPLICATION #PL0402DL | DOB VIOLATION - ACTIVE |
| May 15, 2014 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT #05259 | DOB VIOLATION - ACTIVE |
| May 15, 2014 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT #05260 | DOB VIOLATION - ACTIVE |
| May 15, 2014 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT #05261 | DOB VIOLATION - ACTIVE |
| May 15, 2014 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT #05262 | DOB VIOLATION - ACTIVE |
| May 15, 2014 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT #05263 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Nov 25, 2024 | Parking Structures FTF-PS-INITL Failure to file sub cycle 1A compliance report by 12/31/2023 | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Jul 31, 2018 | Facades FISPNRF FAILED TO FILE FISP CYCLE 8B TECHNICAL REPORT BY 02/21/2018 | Active |
| Apr 6, 2018 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT | Active |
| Apr 6, 2018 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT | Active |
| Apr 6, 2018 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT | Active |
| Apr 6, 2018 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT | Active |
| Apr 6, 2018 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2016 INSPECTION REPORT | Active |
| May 15, 2014 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT | Active |
| May 15, 2014 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT | Active |
| May 15, 2014 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT | Active |
| May 15, 2014 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT | Active |
| May 15, 2014 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |