| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 62 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-11-05 (Accepted). Agency page | Dec 31, 2026 in 62 days | 2 of 2 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 404,920 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 183 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 183 days | Annual filing |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. DOB facade records for this building show $540,000 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2028 in 479 days | No Cycle 10 report on record yet |
| Energy audit and retro-commissioning (2028) Likely applies Local Law 87 · Calendar year 2028 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 208). Agency page | Dec 31, 2028 in 793 days | Next due 2028 |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1158 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Feb 25, 2025 | Construction CLASS - 2 1RCNY 103-09(E). FAILURE TO FILE A RETAINING WALL CONDITION ASSESSMENTREPORT BY THE DEADLINE AS REQUIRED BY 1RCNY 103-09(E)(2) AND (5). TO DATE, THE DEPARTMENT HAS NOT RECIEVED A RETAINING WALL CONDITION ASSESS #37033884X | May 28, 2025 DEFAULT | $6,250 |
| Feb 25, 2025 | Construction CLASS - 2 1RCNY 103-09(E). FAILURE TO FILE A RETAINING WALL CONDITION ASSESSMENTREPORT BY THE DEADLINE AS REQUIRED BY 1RCNY 103-09(E)(2) AND (5). TO DATE, THE DEPARTMENT HAS NOT RECIEVED A RETAINING WALL CONDITION ASSESS #37033858M | May 28, 2025 DEFAULT | $6,250 |
| Feb 25, 2025 | Construction CLASS - 2 1RCNY 103-09(E). FAILURE TO FILE A RETAINING WALL CONDITION ASSESSMENTREPORT BY THE DEADLINE AS REQUIRED BY 1RCNY 103-09(E)(2) AND (5). TO DATE, THE DEPARTMENT HAS NOT RECIEVED A RETAINING WALL CONDITION ASSESS #37033885H | May 28, 2025 DEFAULT | $6,250 |
| Feb 25, 2025 | Construction CLASS - 2 1RCNY 103-09(E). FAILURE TO FILE A RETAINING WALL CONDITION ASSESSMENTREPORT BY THE DEADLINE AS REQUIRED BY 1RCNY 103-09(E)(2) AND (5). TO DATE, THE DEPARTMENT HAS NOT RECIEVED A RETAINING WALL CONDITION ASSESS #37033870P | May 28, 2025 DEFAULT | $6,250 |
| Jun 17, 2024 | Construction CLASS - 2 A.C. 27-929.1, FAILURE TO COMPLETED THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MO #37028922L | Dec 5, 2024 ADMIT/IN-VIO | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#909065.REM:SUBMIT ACCEPTABLE REQUIRED T #37028116R | Dec 4, 2024 IN VIOLATION | $0 |
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL#909066.REM:SUBMIT ACCEPTABLE REQUIRED T #37028111H | Dec 4, 2024 IN VIOLATION | $0 |
| Feb 28, 2023 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HE #37025422L | Jan 8, 2024 IN VIOLATION | $0 |
| Nov 1, 2021 | Construction CLASS - 2 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AM OFFICE BUILDING 100 FEET OR MORE IN HEIGHT IN E #37022546J | Apr 27, 2022 ADMIT/IN-VIO | $0 |
| Mar 30, 2021 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MORE IN HE #37020805X | Aug 25, 2021 ADMIT/IN-VIO | $0 |
| Jul 13, 2020 | Construction CLASS - 2 27-929.1 FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY REGISTERED DESIGN PROFESSIONAL BY JULY 1,2019,IN AN OFFICE BUILDING 100 FEET #37019944H | Dec 23, 2020 IN VIOLATION | $0 |
| Nov 15, 2019 | Construction CLASS - 2 A.C 27-929.1,FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL BY 7/1/2019,IN AN OFFICE BLDG 100 FT OR #37016869N | Nov 9, 2020 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00635 | DOB VIOLATION - ACTIVE |
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #00637 | DOB VIOLATION - ACTIVE |
| Dec 15, 2022 | RETAINING WALL FAILED TO FILE CYCLE 1 TECHNICAL REPORT BY 12/31/2018 PER RCNY 103-09 #00350 | DOB VIOLATION - ACTIVE |
| Dec 15, 2022 | RETAINING WALL FAILED TO FILE CYCLE 1 TECHNICAL REPORT BY 12/31/2018 PER RCNY 103-09 #00364 | DOB VIOLATION - ACTIVE |
| Dec 15, 2022 | RETAINING WALL FAILED TO FILE CYCLE 1 TECHNICAL REPORT BY 12/31/2018 PER RCNY 103-09 #00365 | DOB VIOLATION - ACTIVE |
| Feb 9, 2021 | CONSTRUCTION BOROUGH COMMISSIONER HAS ORDERED ALL WORK STOPPED UNDER APPLICATION #321194275 ON 2/8/2021 DUE TO CONSTRUCTION SUPERINTENDENT WITHDRAWAL #21-00110 | DOB VIOLATION - ACTIVE |
| Feb 9, 2021 | CONSTRUCTION BOROUGH COMMISSIONER HAS ORDERED ALL WORK STOPPED UNDER.APPLICATION #321194275 ON 2/8/2021 DUE TO CONSTRUCTION SUPERINTENDENT WITHDRAWAL #21-00111 | DOB VIOLATION - ACTIVE |
| Oct 1, 2019 | RETAINING WALL FAILED TO FILE CYCLE 1 TECHNICAL REPORT BY 12/31/2018 PER RCNY 103-09 #00864 | DOB VIOLATION - ACTIVE |
| Sep 3, 2019 | SPRINKLER FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019 #NRF01050 | DOB VIOLATION - ACTIVE |
| Jan 1, 2018 | CONSTRUCTION WORK WITHOUT A PERMIT #CER01SM | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Oct 2, 2023 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Affirmation of Correction | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Dec 15, 2022 | Retaining Walls FTF-RW-INITL | Active |
| Dec 15, 2022 | Retaining Walls FTF-RW-INITL | Active |
| Dec 15, 2022 | Retaining Walls FTF-RW-INITL | Active |
| Oct 1, 2019 | Retaining Walls FTF-RW-INITL | Active |
| Sep 3, 2019 | Sprinklers FTF-SP-FINAL | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Nov 18, 2025 | I | §27-2107 ADM CODE OWNER FAILED TO FILE A VALID REGISTRATION STATEMENT WITH THE DEPARTMENT AS REQUIRED BY ADM CODE §27-2097 AND IS THEREFORE SUBJECT TO CIVIL PENALTIES, PROHIBITED FROM CERTIFYING VIOLATIONS, AND DENIED THE RIGHT TO RECOVER POSSESSION OF PREMISES FOR NONPAYMENT OF RENT UNTIL A VALID R | — |
| May 7, 2026 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Aug 10, 2026 |
| Jun 13, 2025 | A | (A) § HMC:FILE ANNUAL BEDBUG REPORT IN ACCORDANCE WITH HPD RULE AS DESCRIBED ON THE BACK OF THIS NOTICE OF VIOLATION OR AS DESCRIBED ON HPDS WEBSITE, WWW.NYC.GOV\HPD, SEARCH BED BUGS. | Sep 16, 2025 |
| Date | Source | What | Now |
|---|---|---|---|
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 30, 2026, 2:41 PM ET. BBL 3002080002.