| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 64 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 64 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 80 days | Annual |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1160 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jun 15, 2021 | Construction CLASS - 1 UNLAWFULLY CONSTINUED WORK WHILE ON NOTICE OF STOP WORK ORDER.AS NOTED:AT TIME OF INSPECTION CONSTRUCTION SITE AN ACTIVE OBSERVED AT EXP #4 ON PIPE SCAFFOLDING WORKERS FAMING EXTERIOR WALLS AND ALSO INTERIOR FR #35549464Y | Nov 18, 2022 IN VIOLATION | $5,000 |
| Jun 8, 2021 | Unknown CLASS - 1 PERMIT HOLDER FAILED TO ENSURE WORKERS REQUESITE SAFETY ORIENTATION-STOP ALL WORK WITHIN INTERIOR AND EXTERIOR ALL EXPOS PROVIDED WORK ORIENTATION SAFETY.NOTE:AT TIME OF INSPECTION OF A 6 STORY NEW BUILDING UND #35559573M | Oct 20, 2021 IN VIOLATION | $2,500 |
| Jun 8, 2021 | Construction CLASS - 1 FAILURE TO INSTITUTE AND MAINTAIN SAFETY EQUIPMENT MEASURES FOR TEMPORARY CONSTRUCTION-INSTALL HANDRAILS ON EXP #3 STAIRCASE LEADING FROM MAIN FLOOR TO BACKYARD AREA AND INSTALL HANDRAILS ON INTERIOR STAIRCASE #35559574Y | Oct 20, 2021 IN VIOLATION | $2,500 |
| Jun 8, 2021 | Construction CLASS - 1 BC3314.8 DEBRIS NETTING SCF SHALL BE ENCLOSED W/ DEBRIS NETTING OF SYNTHETIC NETTING,SHALL BE INSTALLED TOP TO BOTTOM OF ALL OPEN SECS OF SUPPORTED SCFS&SHALL BE MAINTAINED AS PER CODE NOTE:ATO MY INSP OF PROPO #35574850R | Oct 20, 2021 IN VIOLATION | $625 |
| Jun 8, 2021 | Construction CLASS - 1 28-401.4 REQUIREMENT OF LICENSE-STOP ALL WORK WITHIN AND OUTSIDE BUILDING PERIMETER-IT SHALL BE UNLAWFUL FOR ANY PERSON TO ENGAGE IN CITY ANY BUSINESS OR TRADE WITHOUT HAVING FIRST OBTAINED A LICENSE FROM COMM #35559572K | Oct 20, 2021 IN VIOLATION | $5,000 |
| May 21, 2021 | Construction CLASS - 1 BC33076422-MATERIAL STORAGE ON SIDEWALK SHED.AS NOTED:AT TIME OF INSPECTION AT AN ACTIVE CONSTRUCTION SITE,OBSERVED SIDEWALK SHED ERECTED ONEXPOSURE#1 AND #4.OBSERVED DEBRIS,MATERIAL AND NUMEROUS BAGS OF TRASH #35559871K | Oct 27, 2021 IN VIOLATION | $625 |
| May 21, 2021 | Construction CLASS - 2 AC2810512-CONDITION OF NEW BUILDING PERMIT.AS NOTED:AT TIME OF INSPECTION AT AN ACTIVE JOBSITE OBSERVED ON THE BIS SYSTEM NEW BUILDING PERMIT#320979090-01-NB STATING 'MASONRY' AS THE PRIMARY STRUCTURAL SYSTEM A #35559870Z | Oct 27, 2021 IN VIOLATION | $1,250 |
| May 21, 2021 | Construction CLASS - 2 BC33017-FAILURE TO PROVIDE APPROVED P.E CONSTRUCTION DOCUMENTS.AS NOTED:AT TIME OF INSPECTION AT AN ACTIVE JOBSITE,OBSERVED(1)TWO SEPERATE STEEL STAIRCASES PLACED FROM CELLAR LEVEL TO FIRST FLOOR LEVEL.UPON REQ #35559872M | Oct 27, 2021 IN VIOLATION | $625 |
None open.
None open.
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 28, 2026, 10:27 AM ET. BBL 3020117504.