4 floors · 254,343 sq ft · built 1965 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 46 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 254,343 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 167 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 167 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1142 days | Next cycle year 2029 |
| Energy audit and retro-commissioning (2035) Likely applies Local Law 87 · Calendar year 2035 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1215). Agency page | Dec 31, 2035 in 3333 days | Next due 2035 |
| Annual boiler inspection (4 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-05-26 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Mar 10, 2026 | Construction CLASS - 2 REISSUE: 35717116H-FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION OBSERVED WATER SEEPING THROUGH THE CONCRETE. REMEDY: COMPLY WITH CODE. #35728647K | May 11, 2026 POP/IN-VIO | $0 |
| Apr 15, 2025 | Construction CLASS - 2 REISSUE#35663219J DATE OF ISSUE:02.21.2023 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.AT THE TIME OF INSPECTION OBSERVED & NOTED THAT AT CELLAR LEVEL FULL TANK RM OBSERVED WATER SEEPING THROUGH CONCR #35717116H | Jun 26, 2025 POP/IN-VIO | $0 |
| Feb 21, 2023 | Construction CLASS - 2 REISSUE#35650801M FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED AT TIME OF INSPECTION,I OBSERVED AT OIL TANK ROOM WATER SEEPING THROUGH CONCRETE CEILING SPALLING EXPOSING REBAR AND BEAMS.VIO#35650 #35663219J | Jun 15, 2023 POP/IN-VIO | $0 |
| Mar 15, 2022 | Construction CLASS - 2 REISSUE#35486643Y.DATE OF ISSUE:4/15/2020.FAILURE TO MAINTAIN BUILDINGIN CODE COMPLIANT MANNER.NOTED AT OIL TANK ROOM WATER SEEPING THROUGH CONCRETE PAD FROM UNDERGROUND SPALLING CONCRETE CEILING EXPOSING REBAR #35650801M | Jul 14, 2022 POP/IN-VIO | $0 |
| Apr 15, 2020 | Construction CLASS - 2 REISSUE #35402262J FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER NOTED AT OILTANK ROOM WATER SEEPING THROUGH CONCRETE PAD FROM UNDER GROUND SPALLING CONCRETE CEILING EXPOSING REBARS IN THE BEAMS. MAKE #35486643Y | Jun 4, 2020 POP/IN-VIO | $0 |
| Apr 2, 2019 | Construction CLASS - 2 REISSUE 35311289X FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. NOTED AT OIL TANK ROOM IN DISREPAIR WITH WATER LEAK FROM UNDERGROUND ALSO CONCRETE CEILING SPALLING EXPOSING REBAR AND BEAMS. REMEDY: REP #35402262J | Jun 27, 2019 POP/IN-VIO | $0 |
| Feb 20, 2018 | Construction CLASS - 2 REISSUE #35267277N FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. NOTED AT FUEL TANK ROOM CEILING HAS PENETRATIONS, CONCRETE COVER FOR BEAMS MISSING EXPOSING BEAMS, CORROSION IN MULTIPLE LOCATIONS. #35311289X | May 3, 2018 POP/IN-VIO | $0 |
| May 18, 2017 | Construction CLASS - 2 FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER. REISSUE NOV#35195314N NOTED: AT FUEL TANK ROOM 1 CORRODED LIGHT FIXTURE & PENETRATION @ CEILING W/EXPOSED STEEL BEAM. REMEDY: COMPLY W/CODE. #35267277N | Aug 17, 2017 POP/IN-VIO | $0 |
| May 19, 2015 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. IN FUEL TANK ROOM CONCRETE CEILING SPALLING EXPOSING REBAR & BEAMS. AT EXTERIOR EN TRY AT SOUTN EAST CORNER. REISSUE: 35093295J. RMDY: COMPLY W/NOV #35128448Z | Aug 20, 2015 POP/IN-VIO | $0 |
| Mar 28, 2014 | Construction CLASS - 2 RE-ISSUE # 35016533R. FAILURE TO MAINTAIN BLDG IN CODE-COMPLIANT MANNER. -IN FUEL TANK ROOM CONCRETE CEILING SPALLING EXPOSING REBAR & BEAMS. -AT EXTERIOR ENTRY AT SOUTH EAST CORNER. REMEDY: REPAIR/REPLACE CONC #35093295J | Jun 5, 2014 POP/IN-VIO | $0 |
| May 13, 2013 | Construction CLASS - 2 REISSUE- 34941377X. CONCRETE CEILING SPALLING EXPOSING REBAR AND BEAMS. REMEDY: REPAIR/REPLACE CONCRETE. #35016533R | Jul 18, 2013 POP/IN-VIO | $0 |
| Feb 23, 2012 | Construction CLASS - 2 REISSUE # 34921758L. CONCRETE CEILING SPALLING AT CELLAR LEVEL IN FUEL TANK ROOM, EXPOSING REBAR. REMEDY: REPAIR SPALLING CONCRETE. #34941377X | May 3, 2012 POP/IN-VIO | $0 |
| Jul 28, 2011 | Construction CLASS - 2 SPALLING CONCRETE. AT CELLAR LEVEL FUEL TANK ROOM, SPALLING CONCRETE CEILING EXPOSING RUSTING RE-BAR AND STEEL GIRDER. REMEDY: REPAIR CONCRETE SURFACE. #34921758L | Sep 15, 2011 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Sep 23, 2020 | CONSTRUCTION BOROUGH COMMISSIONER ISSUED STOP WORK ORDER TO APPLICATION #103651013 DUE TO CONSTRUCTION SUPERINTENDENT WITHDRAWAL. (NO ACCESS PROVIDED 0% OF WORK COMPLETED) STOP WORK IMMEDIATELY AND MAKE SITE SAFE. #20-01299 | DOB VIOLATION - ACTIVE |
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #01000 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2019 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2020 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 15, 2026, 3:37 AM ET. BBL 1012150001.