Manhattan · Block 1603 · Lot 39 · 10029

50 East 98 Street

15 floors · 240,000 sq ft · built 1984 · class H8 · owner of record: Msmc Residential Realty

12open violations
$0ECB/OATH penalties owed
0HPD class C (immediately hazardous)
164dto Energy and water benchmarking

Get an email when anything changes here

New violations the morning after they're issued, plus deadline reminders. Free for one building.

Compliance deadlines

RequirementDueStatus
Annual parapet observation Check
Local Law 126 · By December 31 each year
What this is

If the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page

Dec 31, 2026
in 43 days
Keep the report on file (not filed with DOB)
Energy and water benchmarking Likely applies
Local Law 84 · May 1 each year
What this is

Buildings over 25,000 sq ft (this lot shows 240,000 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page

May 1, 2027
in 164 days
Annual filing
Building emissions report Likely applies
Local Law 97 · May 1 each year (extensions available)
What this is

Covered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page

May 1, 2027
in 164 days
Annual filing
Gas piping inspection (2027 cycle) Likely applies
Local Law 152 · During 2027
What this is

Buildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 11 is on the 2027 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page

Dec 31, 2027
in 408 days
Next cycle year 2027
Facade inspection report (Cycle 10C) Applies
Local Law 11 / FISP · Feb 21, 2027 to Feb 21, 2029
What this is

Buildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 1, 2 or 3 are in sub-cycle 10C. DOB facade records for this building show $56,000 in late-filing or failure-to-file penalties. Agency page

Feb 21, 2029
in 826 days
Filing window not open yet
Energy audit and retro-commissioning (2033) Likely applies
Local Law 87 · Calendar year 2033
What this is

Buildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1603). Agency page

Dec 31, 2033
in 2600 days
Next due 2033
Annual boiler inspection (2 boilers) Applies
Boiler inspection · By December 31 each year
What this is

Boilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-05-07 (Accepted). Agency page

On file2026 reports accepted

Open violations

ECB / OATH (8)
IssuedViolationHearingBalance
Oct 18, 2024Construction CLASS - 2
AT TIME OF INSPECTION, OBSERVED ACTIVE JOBSITE. UPON INSPECTING SUSPENDED SCAFFOLD PLATFORMS NOTICE IT DOES NOT CONFORM WITH MANUFACTURE SPECIFICATION FROM SKYCLIMBER. NO FRONT TOP RAIL INSTALLED ON ANY PLATFOR
#39533553P
Apr 10, 2026
ADMIT/IN-VIO
$0
Oct 18, 2024Construction CLASS - 2
AT TIME OF INSPECTION OBSERVED ACTIVE JOBSITE. UPON INSPECTING SUSPENDED SCAFFOLD SETUP NOTICE SEVERAL DISCREPANCIES. STYROFOAM ON BASE NOT ON DRAWINGS, 12 FT. OUTRIGGER BEAM MISSING COUNTERWEIGHTS, MEASUREMENT
#39533552N
Oct 6, 2025
IN VIOLATION
$0
Mar 27, 2024Construction CLASS - 2
BC 3307.6.4.2.2 STORAGE. AT THE TIME OF INSPECTION, I OBSERVED MISCELLANEOUS MATERIALS BEING STORED ON SIDEWALK SHED THAT ARE NOT INDICATED TO APPROVED PLANS UNDER PERMIT # M00847918-I1-SH EXP. 3/29/2024. REMOV
#39526879J
Apr 10, 2025
IN VIOLATION
$0
Jul 26, 2023Construction CLASS - 2
AT TIME OF INSPECTION AT AN ACTIVE CONSTRUCTION JOB SITE, I OBSERVED TREES AT EXPOSURE #1 AND EXPOSURE #2 WERE NOT PROTECTED. / PROTECT TREES.
#39519803H
Oct 5, 2023
ADMIT/IN-VIO
$0
Jun 30, 2023Construction CLASS - 2
FAILURE TO INSTITUTE SAFETY MEASURES FOR WORKERS CREATING HAZARDOUS FOR TWO WORKERS WERE FALL FROM APPROXIMATELY 15 FEET HIGH, NO FALL PROTECTION WERE PROVIDED RESULTS IN INJURIES, AND IN CONTRARY WITH CODE "33
#39518603Z
Sep 7, 2023
ADMIT/IN-VIO
$0
Jun 30, 2023Unknown CLASS - 2
FAILURE TO IMMEDIATELY NOTIFY THE DEPARTMENT OF INCIDENT. RESPONDENT WAS DELAY TO NOTIFY BUILDINGS OF 2 WORKERS FALL FROM THE TOP OF SIDEWALK SHED AND GET INJURED.
#39518602R
Sep 7, 2023
ADMIT/IN-VIO
$0
Jun 29, 2021Construction CLASS - 2
FAILURE TO MAINTAIN BUILDING EXTEIROR WALLS.FACADE AND APPURTENANCES NOTE AT THE TIME OF MY INSPECTION VIEW AT EXPOSURE 1 NORTH ELEVATION DETERIORATION OF COATING AT WINDOW LINTELS WEST ROOF AREA OBSERVED MISSI
#35577959Y
Nov 4, 2021
IN VIOLATION
$0
May 20, 2021Construction CLASS - 2
FAILURE TO MAINTAIN EXTERIOR BUILDING FACADE OR APPURTENANCES.NOTE:AT TIME OF INSPECTION,OBSERVED AT ROOF LEVEL;MISSING COPING STONE SECTIONS IN NUMEROUS LOCATIONS.(I)OPEN-CRACKED BRICK JOINTS ON BULKHEAD.REMED
#35559762L
Dec 2, 2021
IN VIOLATION
$0
DOB (2)
IssuedViolationStatus
Aug 1, 2024FAILURE TO CORRECT SWARMP CONDITIONS (FACADE)
FAILURE TO CORRECT SWARMP CONDITIONS
#00170
DOB VIOLATION - ACTIVE
Feb 21, 2024HAZARDOUS CONDITION (FACADE)
CYCLE 9C UNSAFE REPORT FILED
#911790
DOB VIOLATION - ACTIVE
DOB NOW Safety (2)
IssuedViolationStatus
Aug 1, 2024Facades FISPFCS
FAILURE TO CORRECT SWARMP CONDITIONS
Active
Feb 21, 2024Facades FISPHAZ
CYCLE 9C UNSAFE REPORT FILED
Active
HPD (0)

None open.

Check the agency records

Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)

City records as of Nov 18, 2026, 11:22 AM ET. BBL 1016030039.

Look up another building