5 floors · 71,305 sq ft · built 1916 · class W1 · owner of record: Nyc Department Of Education
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 63 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 71,305 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 184 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 184 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1159 days | Next cycle year 2029 |
| Energy audit and retro-commissioning (2035) Likely applies Local Law 87 · Calendar year 2035 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 585). Agency page | Dec 31, 2035 in 3350 days | Next due 2035 |
| Annual boiler inspection (2 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-05-29 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jun 25, 2026 | Construction CLASS - 2 REISSUE ECB#35720607J FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED MAIN H.W.HEATER VALVE LEAKING IN THE BOILER ROOM.REM:REPAIR AND/OR REPLACE. #35734504Y | Jul 27, 2026 POP/IN-VIO | $0 |
| Jun 25, 2026 | Construction CLASS - 2 REISSUE ECB#35720608L FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.ILLUMINATION FOR EXITS,EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1;27-381.NOTED EMERGENCY LIGHTS NOT WORKING THROUGHOUT BUILDIN #35734503M | Jul 27, 2026 POP/IN-VIO | $0 |
| Jun 25, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED BROKEN/CRACKED WINDOW GLASS PANELS IN WALL BETWEEN CLASSROOM#400 AND MAIN CORRIDOR AND ABOVE DOOR ENTRY TO CLASSROOM#401.REM:REPAIR AND/OR REPLACE. #35734505X | Jul 27, 2026 POP/IN-VIO | $0 |
| Jul 14, 2025 | Construction CLASS - 2 RE-ISSUE #35682922P. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. ILLUMINATION FOR EXITS, EXIT DISCHARGES AND PUBLIC CORRIDORS PERBC 1006.1; 27-381. NOTED: AT T. O. I. THERE WERE SEVERAL EMERGENCY LIG #35720608L | Aug 27, 2025 POP/IN-VIO | $0 |
| Jul 14, 2025 | Construction CLASS - 2 RE-ISSUE #35682924Z. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. NOTED: THE H.W. HEATER IN THE BOILER ROOM NEEDS ATTENTION. IT'S LEAKING WATER, PONDING ON FLOOR. REMEDY: REPAIR/REPLACE. #35720607J | Aug 27, 2025 POP/IN-VIO | $0 |
| Aug 29, 2024 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING WATER HEATER IN BOILER ROOM VALVE LEAKING WATER AND HEATER BLOW UP HOLE IN TANKS.REM:REPAIR AND REPLACE. #35682924Z | Nov 7, 2024 POP/IN-VIO | $0 |
| Aug 29, 2024 | Construction CLASS - 2 FAILURE TO MAINTAIN BUIDING NO LIGHT WORK IN YARD AND ENG LIGHT NOT WORK IN FULL BUILDING.REM:REPAIR OR REPLACE. #35682922P | Nov 7, 2024 POP/IN-VIO | $0 |
None open.
None open.
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 29, 2026, 11:18 PM ET. BBL 1005850041.