class V1 · owner of record: Congregation Beth Aron V'Israel Karlin S Tolin Inc.
New violations the morning after they're issued, plus deadline reminders. Free for one building.
We couldn't find building attributes for this lot, so no deadlines are listed.
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| May 15, 2026 | Construction CLASS - 2 BC 1704.5.3. FAILURE TO PROVIDE A CONTINUOUS INSPECTION DURING GROUTING OPERATION. AS NOTED: AT TIME OF INSPECTION AT AN ACTIVE JOBSITE OF APROPOSED 6 STORY BUILDING ALREADY AT THE BULKHEAD. OBSERVED AT THE 6TH #35726426H | Jul 22, 2026 STIPULATION/IN-VIO | $0 |
| Feb 1, 2026 | Unknown CLASS - 2 ATOI. OF A 6 STORY NEW BUILDING AT ROOF, BUILDING APPROXIMATELY 9654 SQUARE FEET. SITE CLOSED AND THERE WERE NO CONSTRUCTION ACTIVITY. UPON SHOUTING AT PERIMETER AND BANGING ON FENCE AND DOOR TO ALERT WATCHPERS #39549789H | Feb 4, 2027 | $2,500 |
| Feb 1, 2026 | Construction CLASS - 1 AT TIME OF INSPECTION. OBSERVED ACTIVE HVAC WORK BEING PERFORMED BY THREE WORKERS AT A NEW SIX-STORY BUILDING. DEPARTMENT RECORDS REVIEW CONFIRMED NO AFTER-HOURS VARIANCE PERMIT ON FILE AUTHORIZING SUCH WORK ON #39549786M | Feb 4, 2027 | $2,500 |
| Jan 19, 2026 | Construction CLASS - 2 AT TIME OF INSPECTION, OBSERVED OFFICE TRAILER BARRICADED IN STAGING AREA AT EXPOSURE #4 THAT DID NOT REFLECT ON THE SITE SAFETY PLAN. #39549292M | Feb 23, 2027 | $1,250 |
| Sep 23, 2025 | Unknown CLASS - 2 MISCELLANEOUS VIOLATIONS.ATOI I OBSERVED A JOBSITE WITH BUILDING FOOTPRINT OF 9000 SQ.FT.A PERSON DRESSED AS A SECURITY GUARD WHO WHEN ASKEDCOULD NOT PRESENT HIS SECURITY CREDENTIALS.THIS IS IN VIOLATION OF BC3 #39545239P | Aug 25, 2026 DEFAULT | $5,000 |
| Sep 23, 2025 | Construction CLASS - 2 FAILURE TO COMPLY WITH MANUFACTURER SPECIFICATIONS.ATOI I OBSERVED YODOCK BARRICADES AT EXP#1 NOT CONNECTED AND NOT FILLED WITH WATER.THIS POSES HAZARDS FOR PASSING VEHICULAR TRAFFIC.REM:COMPLY WITH SPECIFICATI #39545240M | Aug 25, 2026 DEFAULT | $3,125 |
| Aug 10, 2024 | Unknown CLASS - 2 BC 3307.2.1 FAILURE TO COMPLY WITH DOT REGULATIONS AS PER 34 RCNY 2-05 AND ADMIN CODE PROVISION 19-107,19-108. OCCUPYING AND CLOSING OF SIDEWALK AND 1 LANE AT STREET LEVEL AT EXPOSURES 1 / 4. CREATING A UNSAF #39531287M | Jun 16, 2026 IN VIOLATION | $625 |
| Aug 7, 2024 | Unknown CLASS - 2 BC 3301.8.1 USE AND TAMPERING PROHIBITED. -- AT THE TIME OF MY INSPECTION WHILE RESPONDING TO AN INCIDENT WHERE A WORKER WAS INJURED IN AN EXCAVATED PIT AND WAS REMOVED BY FDNY. UPON REVIEW OF THE EVIDENCE PRO #39531199M | Feb 16, 2027 | $2,500 |
| Aug 7, 2024 | Construction CLASS - 2 AT THE TIME OF MY INSPECTION OF AN ACTIVE JOB SITE WHERE A WORKER WAS INJURED IN AN EXCAVATION WHILE REMOVING A LARGE FOUNDATION WALL AT EXPOSURE 3, I OBSERVED THAT THERE WERE NO SAFETY MEASURES IN PLACE WHILE #39531197Z | Feb 16, 2027 | $5,000 |
| Dec 2, 2022 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING DEMOLITION PHASE, I OBSERVED LARGE AMOUNT OF DEMOLITION DEBRIS PILING UP APPROXIMATELY 13 FEET, DEMOLITION SEQUENCE WAS NOT FOLLOWED AS PER APPROVED DOCUMENTS, #39509891H | Jul 1, 2024 IN VIOLATION | $1,250 |
| Dec 2, 2022 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING DEMOLITION PHASE, I OBSERVED LARGE AMOUNT OF DEMOLITION DEBRIS PILING UP APPROXIMATELY 13 FEET, UPON REVIEW OF THE APPROVED DEMOLITION DOCUMENTS SEQUENCE WAS N #39509886N | Jul 1, 2024 IN VIOLATION | $1,250 |
| Dec 2, 2022 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING DEMOLITION PHASE, I OBSERVED LARGE AMOUNT OF DEMOLITION DEBRIS PILING UP APPROXIMATELY 13 FEET, DEMOLITION SEQUENCE WAS NOT FOLLOWED AS PER APPROVED DOCUMENTS, #39509893L | Jul 1, 2024 IN VIOLATION | $1,250 |
| Dec 2, 2022 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING DEMOLITION PHASE, I OBSERVED LARGE AMOUNT OF DEMOLITION DEBRIS PILING UP APPROXIMATELY 13 FEET, UPON REVIEW OF THE APPROVED DEMOLITION DOCUMENTS SEQUENCE WAS N #39509894N | Jul 1, 2024 IN VIOLATION | $2,500 |
| Dec 2, 2022 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION OF A 2 STORY BUILDING DEMOLITION PHASE, I OBSERVED LARGE AMOUNT OF DEMOLITION DEBRIS PILING UP APPROXIMATELY 13 FEET, UPON REVIEW OF THE APPROVED DEMOLITION DOCUMENTS SEQUENCE WAS N #39509892J | Jul 1, 2024 IN VIOLATION | $1,250 |
| Issued | Violation | Status |
|---|---|---|
| Jun 30, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION #41413 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | LOW PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION #14685 | DOB VIOLATION - ACTIVE |
| Aug 16, 1993 | LOCAL LAW 62/91 - BOILERS #30953 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jun 30, 2023 | Boiler LBLVIO VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION | Active |
| Apr 25, 2023 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2022 INSPECTION REPORT | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 27, 2026, 1:43 AM ET. BBL 3054370001.