5 floors · 1,503,150 sq ft · built 1930 · class I1 · owner of record: Nyc Health And Hospitals Corporation
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Gas piping inspection (2026 cycle) Likely applies Local Law 152 · During 2026 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 9 is on the 2026 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2026 in 65 days | Due this year |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 65 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 1,503,150 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 186 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 186 days | Annual filing |
| Energy audit and retro-commissioning (2029) Likely applies Local Law 87 · Calendar year 2029 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 4829). Agency page | Dec 31, 2029 in 1161 days | Next due 2029 |
| Annual boiler inspection (8 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-10-23 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 3, 2025 | Construction CLASS - 2 PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIONS.BC 3307.6.5.1 AT TIME OF INSPECTION OF PERMITTED SIDEWALK SHED I OBSERVED SEVERAL MISSING BOLT COVERS IN THE PEDESTRIAN PASSAGEWAY AT EXPOSURE 1.THIS CAUS #39544433Y | Nov 6, 2025 POP/IN-VIO | $0 |
| Jun 3, 2025 | Construction CLASS - 2 TEMPORARY CONSTRUCTION EQUIPMENT OR INSTALLATION ON SITE EXPIRED PERMIT. AS OF TODAY 06/09/2025 PERMIT #B01128683-I1-PMM EXPIRED ON 01/22/2025. NO CURRENT PERMIT ON FILE. REMEDY: RENEW PERMIT. #35717083K | Jul 14, 2025 POP/IN-VIO | $0 |
| Jun 3, 2025 | Unknown CLASS - 2 TEMPORARY CONSTRUCTION EQUIPMENT/INSTALLATION ON SITE EXPIRED PERMIT(SHED). AS OF TODAY 06/09/2025 PERMIT #B01006748-I1-SH EXPIRED ON 02/20/2025. NO CURRENT PERMIT ON FILE. REMEDY: RENEW PERMIT. #35717082Z | Jul 14, 2025 POP/IN-VIO | $0 |
| Oct 9, 2024 | Construction CLASS - 1 FAILURE TO TAKE REQUIRED MEASURES TO SECURE PUBLIC SAFETY-UNSAFE FACADE. NOTE: OBSERVED STEP CRACKS IN PARAPET WALL EXP(1) NORTH ELE, EXPOSURE(2) EAST, EXPOSURE(3) SOUTH AND EXPOSURE(4) WEST ELE VERTICAL CRACKS #35686676R | Oct 24, 2024 POP/IN-VIO | $0 |
| Sep 10, 2024 | Construction CLASS - 1 FAILURE TO TAKE REQUIRED MEASURES TO SECURE PUBLIC SAFETY-UNSAFE FACADE. NOTE: OBSERVED STEP CRACKS IN PARAPET WALL EXP(1) NORTH ELE; EXPOSURE(2) EAST, EXPOSURE(3) SOUTH AND EXPOSURE(4) WEST ELE. VERTICAL CRACK #35686690N | Dec 2, 2024 POP/IN-VIO | $0 |
| Jan 16, 2024 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 7A, 8A, AND 9A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL #909955. REMEDY: FILE ACCEPTABLE RE #37026007Z | Jan 23, 2024 POP/IN-VIO | $0 |
| Jan 16, 2024 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 9A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL #914426. REMEDY: FILE ACCEPTABLE REPORT. #37026024K | Jan 23, 2024 POP/IN-VIO | $0 |
| Jan 16, 2024 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 9A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL #909959. REMEDY: FILE ACCEPTABLE REPORT. #37026026Y | Jan 23, 2024 POP/IN-VIO | $0 |
| Jan 16, 2024 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 6, 7A, 8A, AND 9A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL #909958. REMEDY: FILE ACCEPTABLE #37026010J | Jan 23, 2024 POP/IN-VIO | $0 |
| Jan 16, 2024 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 9A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL #909960. REMEDY: FILE ACCEPTABLE REPORT. #37026027X | Jan 23, 2024 POP/IN-VIO | $0 |
| Dec 2, 2022 | Local Law CLASS - 2 FAILURE TO SUBMIT ACCEPTABLE REQUIRED CYCLE9A REPORT OF CRITICAL EXAM DOCUMENTING CONDITION OF EXTERIOR WALL&APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL909959.SUBMIT ACCEPTABLE REQUIRED TECHNICAL REPORT #37023904P | Feb 8, 2023 POP/IN-VIO | $0 |
| Jun 28, 2022 | Construction CLASS - 1 FAILURE TO MAINTAIN EXTERIOR BUILDING WALLS AND APPURTENANCES.NOTED ATTIME OF INSPECTION I OBSERVED ON EXP1,2,3,AND 4,CRACKS,STEP CRACKS,VERTICAL CRACKS CORRDING,SAGGING METAL LINTELS ON SEVERAL FLOORS AND PARA #35651574X | Nov 23, 2022 POP/IN-VIO | $0 |
| Sep 9, 2021 | Construction CLASS - 2 WORK WITHOUT PERMIT. DEVICE 3P3525 WAS REMOVED WITHOUT PERMIT BEING OBTAINED AND APPLICATION BEING FILED. REMEDY; FILE APPLICATION AND OBTAIN PERMIT FOR WORK AND SCHEDULE TEST APPOINTMENT WITH NYCDOB. #39047244H | Sep 14, 2021 POP/IN-VIO | $0 |
| Sep 9, 2021 | Construction CLASS - 2 WORK WITHOUT PERMIT. DEVICE 3P1373 WAS REMOVED WITHOUT PERMIT BEING OBTAINED AND APPLICATION BEING FILED. REMEDY; FILE APPLICATION AND OBTAIN PERMIT FOR WORK AND SCHEDULE TEST APPOINTMENT WITH NYCDOB. #39047245J | Sep 14, 2021 POP/IN-VIO | $0 |
| Sep 9, 2021 | Construction CLASS - 2 WORK WITHOUT PERMIT. DEVICE 3P1372 WAS REMOVED WITHOUT PERMIT BEING OBTAINED AND APPLICATION BEING FILED. REMEDY; FILE APPLICATION AND OBTAIN PERMIT FOR WORK AND SCHEDULE TEST APPOINTMENT WITH NYCDOB. #39047246L | Sep 14, 2021 POP/IN-VIO | $0 |
| May 1, 2020 | Construction CLASS - 1 BC3307.6.4.4=VERTICAL MEMBERS AND BEAMS NOET AT THE TIME OF MY INSPECTION I OBSERVED SIDEWALK SHED IN PLACE UPON INSPECTIONI OBSERVED TEH UPRIGHT POSTS TO TEH SIDEWALK SHED WERE PLACE LESS THAN 18 INCHES FROM T #35491769X | Oct 7, 2020 POP/IN-VIO | $0 |
| May 1, 2020 | Construction CLASS - 2 PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIOSN NOTE AT THE TIME OF MY INSPECTION I OBSERVED SIDEWALK SHED IN PLACE UPON MY INSPECTION I OBSERVED (1) TEH BRACING MEMBERS CONNECTING TEH FRAME OF THE SIDE #35491768Y | Oct 7, 2020 POP/IN-VIO | $0 |
| Aug 29, 2019 | Construction CLASS - 2 PEDESTRIAN PROTECTION DOES NOT MEET CODE SPECIFICATIONS. AT THE TIME OF INSPECTION IT WAS OBSERVED THAT THE SIDEWALK SHED ERECTED UNDER JOB#320254817 WAS NOT CODE COMPLIANT. ALL OF THE LIGHTS WERE INOPERABLE CA #35432716M | Dec 30, 2019 DEFAULT | $10,000 |
| Aug 1, 2018 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INTIAL FACADES REPORT REQUIRED BY28-302.5 FOR CONTROL# 809954. RMDY: FILE ACCEPTABLE REPORT #37012063X | Feb 11, 2019 POP/IN-VIO | $0 |
| Aug 1, 2018 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL# 809957. RMDY: FILE ACCEPTABLE REPORT. #37012069R | Feb 11, 2019 POP/IN-VIO | $0 |
| Aug 1, 2018 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REPORT REQUIRED BY 28-302.5 FOR CONTROL# 809955. RMDY: FILE ACCETABLE REPORT #37012056H | Feb 11, 2019 POP/IN-VIO | $0 |
| Aug 1, 2018 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED CYCLE 8A REPORT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL FACADES REQUIRED BY 28-302.5 FOR CONTROL# 809958. RMDY: FILE ACCEPTABLE REPORT #37012038Y | Feb 11, 2019 POP/IN-VIO | $0 |
| Apr 4, 2018 | Elevators CLASS - 2 59B7,68B7,68M7. BRAKE MAINTENANCE TAG MISSING INFORMATION; 68B7-MAIN TENANCE LOG MISSING INFORMATION; 68M7-MAINTENANCE CONTROL PROGRAM MISSING. #38262314J | Apr 23, 2018 POP/IN-VIO | $0 |
| Nov 7, 2016 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED REPORT INDICATING CORRECTION OF UN SAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW 11/98 REPORT. RMDY: FILE ACCEPTABLE AMENDED REPORT. #37001648H | Jan 23, 2017 POP/IN-VIO | $0 |
| Nov 7, 2016 | Local Law CLASS - 2 FAILURE TO FILE ACCEPTABLE AMENDED REPORT INDICATING CORRECTION OF UN SAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW 11/98 REPORT. RMDY: FILE ACCEPTABLE AMENDED REPORT. #37001647X | Jan 23, 2017 POP/IN-VIO | $0 |
| May 28, 2016 | Construction CLASS - 1 FAILURE TO TAKE REQUIRED ACTIONS TO SECURE PUBLIC SAFETY- UNSAFE FACADES. NOTED: NO SAFETY MEASURES WERE IN PLACE AS REQUIRED. ON 5/16/16 A QEWI,PAUL MILLMAN,SUBMITTED A FISP3 DOCUMENT DECLARING THE FACADE AS ' #35174359Y | Jul 18, 2016 POP/IN-VIO | $0 |
| Jan 7, 2016 | Construction CLASS - 2 3307.6.5 FAIL TO MAINTAIN SIDEWALK SHED AS REQ BY CODE. NOTE:SIDEWALK SHED ERECTED UNDER JOB #320254817 ALONG EXP #1 IS POORLY MAINTAINED IN THAT PARAPET WALL IS LOOSE AND LEANING.REM:COMPLY W/NOV. #35171125H | Apr 4, 2016 POP/IN-VIO | $0 |
| Jan 7, 2016 | Construction CLASS - 2 3307.6.5 FAIL TO MAINTAIN ADEQUATE ILLUMINATION BENEATH SIDEWALK SHED AS REQ BY CODE.NOTE:SIDWALK SHED ERECTED UNDER JOB #320254826 ALONG EXP #1, HAS INOPERABLE BULBS RENDERING AFFECTED AREA VISIBLY DARK/SHADOW #35171126J | Apr 4, 2016 POP/IN-VIO | $0 |
| Sep 21, 2015 | Construction CLASS - 2 28-317.3 FAILURE TO REGISTER COOLING TOWER. RMDY: COMPLY W/CODE. #37000390P | Nov 9, 2015 POP/IN-VIO | $0 |
| Jul 14, 2015 | Construction CLASS - 2 TEMPORARY CONSTRUCTION EQUIPMENT ON SITE WITH EXPIRED PERMIT. NOTED: AT TIME OF INSPECTION SIDEWALK SHED AT SITE WITH EXPIRED PERMIT JOB# 320404308 EXPIRATION DATE 6/1/12. REMEDY: COMPLY WITH CODE, OBTAIN A PER #35132652H | Oct 19, 2015 POP/IN-VIO | $0 |
| Jun 8, 2015 | Construction CLASS - 2 FAILURE TO MAINTAIN EXTERIOR BLDG.BLDG A,B,C TOWERS.SOUTHERN ELEV EXP1STEEL METAL PANEL MISSING DEFECTIVE WOOD FRAMES,MISSING GLASS,WINDOW (UPPER LOWER)MISSING WEST ELEV.EXP2-8 FL.(TRIM) DEFECTIVE & HANGING.NOR #35133205K | Jul 27, 2015 POP/IN-VIO | $0 |
| May 29, 2015 | Local Law CLASS - 2 FAILURE TO FILE AN ACCEPTABLE AMENDED CYCLE 7 REPORT TO THIS DEPT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW FISP REPORT. REMEDY: FILE AN AMENDED REPORT FOLLOWING REMEDIAL REPAIR #36027731H | Aug 17, 2015 POP/IN-VIO | $0 |
| May 29, 2015 | Local Law CLASS - 2 FAILURE TO FILE AN ACCEPTABLE AMENDED CYCLE 7 REPORT TO THIS DEPT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW FISP REPORT. REMEDY: FILE AN AMENDED REPORT FOLLOWING REMEDIAL REPAIR #36027732J | Aug 17, 2015 POP/IN-VIO | $0 |
| Jan 21, 2015 | Unknown CLASS - 2 FAILURE TO COMPLY W/ THE COMM'S ORDER TO FILE A CERT OF CORRECTION W/ THE DEPT OF BLDG FOR NOTICE OF VIOLATION #3511864R ISSUED ON 12/02/14 PURSUANT TO 28-204.4 & 1RCNY 102-01.REM:FILE A CERT OF CORRECTION. #35042267M | Mar 9, 2015 POP/IN-VIO | $0 |
| Nov 18, 2014 | Construction CLASS - 1 FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER.NOTED:SHED PRESENT APPROX.500LINEAR FT W/DEFECT INCLUDING 2 SECTIONS OF WOOD PARAPET(16FT)HAS FALLEN TO GROUND.REMEDY:MAKE AREA SAFE REPAIR &/OR REPLACE #35111864R | Jan 5, 2015 POP/IN-VIO | $0 |
| Sep 2, 2014 | Construction CLASS - 2 FAILURE TO MAINTAIN EXTERIOR BLDG A(BLDGS A,B AND C TOWERS) WOODEN WINDOWS AND FRAMES -LOOSE WOOD,SPLIT UP.SOME EXAMPLES:TOWER A-EXP1/SOUTH ELEV,4&5FLR; TOWER B-EXP1/SOUTH ELEV, 4&5FLRS; TOWER C-EXP1/SOUTH ELE #35095219R | Oct 20, 2014 POP/IN-VIO | $0 |
| Apr 24, 2013 | Construction CLASS - 2 FAILURE TO MAINTAIN FACADE AND APPURTENANCES.NOTED:AT ALL EXPOSURES ATALL 3 TOWERS (A,B,C) THERE ARE WOODEN WINDOWS THAT HAVE LOOSE WOOD, SPLIT WOOD WITH HANGING PIECES FROM 2 FL TO 10 FL.RMDY:MAKE SAFE IMMED #35001880J | Jun 10, 2013 POP/IN-VIO | $0 |
| Sep 17, 2012 | Unknown CLASS - 2 SEC. 28-302.5. FAILURE TO PROVIDE SAFETY MEASURES (SUCH AS SIDEWALK SHED. FENCE, ETC) TO PROTECT THE PUBLIC FROM UNSAFE CONDITIONS AS PER 1RCNY 103-04 AND AS PER COMPLAING. #3424101 BY RA/PE DATE 8.2.12. REMEDY #34984864N | Nov 5, 2012 POP/IN-VIO | $0 |
| Apr 26, 2012 | Construction CLASS - 2 FAILURE TO MAINTAIN FACADE & APPURTENANCES. NOTED: AT ALL EXPOSURE OF ALL TOWERS (A,B,&C) OLD WOOD WINDOW FRAMES ARE BROKEN,BREAKING & SOME HAVE LOOSE WOOD PIECES HANGING FROM AT WEST EXPOSURE OF 'B' TOWER ONE #34925947Z | Jun 11, 2012 WRITTEN OFF | $0 |
| Mar 26, 2010 | Construction CLASS - 2 FAILURE TO FILE AN AMENDED 5TH ROUND REPORT ACCEPTABLE TO THIS DEPT INDICATING CORRECTION OF UNSAE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW11/98 REPORT.REM:FILE AN AMENDED REPORT FOLLOWING REMEDIAL REPAIRS OF #36012909Y | Jun 14, 2010 WRITTEN OFF | $0 |
| Dec 11, 2009 | Construction CLASS - 2 FAILURE TO FILE AN AMENDED SIXTH ROUND REPORT ACCEPTABLE TO THIS DEPT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW 11/98 REPORT REMEDY:FILE AN AMENDED REPORT FOLLOWING REPAIRS OF TH #36010942R | Feb 1, 2010 WRITTEN OFF | $0 |
| Dec 4, 2009 | Construction CLASS - 2 FAILURE TO FILE AN AMENDED SIXTH ROUND REPORT ACCEPTABLE TO THIS DEPT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW 11/98 REPORT REMEDY:FILE AN AMENDED REPORT FOLLOWING REPAIRS OF TH #36010867X | Feb 1, 2010 WRITTEN OFF | $0 |
| Dec 4, 2009 | Construction CLASS - 2 FAILURE TO FILE AN AMENDED SIXTH ROUND REPORT ACCEPTABLE TO THIS DEPT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW 11/98 REPORT REMEDY:FILE AN AMENDED REPORT FOLLOWING REPAIRS OF TH #36010869J | Feb 1, 2010 WRITTEN OFF | $0 |
| May 28, 2009 | Construction CLASS - 2 FAILURE TO FILE AN AMENDED SIXTH ROUND REPORT ACCEPTABLE TO THIS DEPT INDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW 11/98 REPORT REMEDY:FILE AN AMENDED REPORT FOLLOWING REMEDIAL REPA #36009612X | Jul 20, 2009 WRITTEN OFF | $0 |
| Jan 9, 2009 | Construction CLASS - 2 FAILURE TO FILE AN AMENDED FOURTH ROUND REPORT ACCEPTABLE TO THIS DEPTINDICATING CORRECTION OF UNSAFE CONDITIONS DESCRIBED IN INITIAL LOCAL LAW 11/98 REPORT REMEDY:FILE AN AMENDED REPORT FOLLOWING REMEDIAL REPA #36008144J | Apr 13, 2009 WRITTEN OFF | $0 |
| Issued | Violation | Status |
|---|---|---|
| Apr 29, 2026 | CONSTRUCTION BOROUGH COMMISSIONER HAS ORDERED ALL WORK STOPPED UNDER PERMIT #B00621114-I1 ON 11/18/25. CONTRACTOR WITHDRAWAL #26-01161 | DOB VIOLATION - ACTIVE |
| Apr 29, 2026 | CONSTRUCTION BOROUGH COMMISSIONER HAS ORDERED ALL WORK STOPPED UNDER PERMIT #310103553 ON 8/19/2020 DUE TO CONTRACTOR WITHDRAWAL #26-01146 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01378 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00549 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01382 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00553 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00550 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01380 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01381 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00552 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 INTERNAL HGH PRESSURE INSPECTION #01379 | DOB VIOLATION - ACTIVE |
| Nov 14, 2025 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL HGH PRESSURE INSPECTION #00551 | DOB VIOLATION - ACTIVE |
| Jun 3, 2025 | CONSTRUCTION FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. OBSERVED LARGE STEP CRACKS ON EXPOSURE 3, SOUTH ELEVATION IN MULTIPLE LOCATIONS REMEDY: REPAIR AND/OR REPLACE #SR30901XN | DOB VIOLATION - ACTIVE |
| Oct 9, 2024 | CONSTRUCTION EMERGENCY WORK ORDER DUE TO MASONRY CORNER DISPLACEMENT. ALONG THE NORTH EAST CORNER FROM 2NDFL TO TOP OF PARAPET WALL.REMEDY: OWNER TO IMMEDIATELY PROVIDE PLOT PLAN W/DIMENSION NOTING AREA FO BE CLOSED/PRO RETAIN NYS DESIGN PROF & SUPERVISE ALL REPAIR WORKS. DAILY REPORT TO FACADE UNIT. FACADES@BUI #LL0901AK | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01469 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01470 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01468 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01467 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 INTERNAL HGH PRESSURE INSPECTION #01466 | DOB VIOLATION - ACTIVE |
| Sep 23, 2024 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL HGH PRESSURE INSPECTION #00585 | DOB VIOLATION - ACTIVE |
| Sep 10, 2024 | CONSTRUCTION EMERGENCY WORK ORDER DUE TO MASONRY CORNER DISPLACEMENT ALONG THE NE CORNER FROM 2FL TO TOP OF PARAPET WALL. REMEDY:IMMEDIATELY PROVIDE PLOT PLAN W/DIMENSION NOTING AREA TO BE CLOSED/PROTECTED,RETAIN NYS REG DESIGN PROF TO DIRECT & SUPERVISE ALL REPAIR WORK.SUB TO FACADE UN DAILY REPORT TO FACADE UN #LL0901AK | DOB VIOLATION - ACTIVE |
| Nov 6, 2023 | HAZARDOUS CONDITION (FACADE) CYCLE 9A UNSAFE REPORT FILED #911306 | DOB VIOLATION - ACTIVE |
| Nov 6, 2023 | HAZARDOUS CONDITION (FACADE) CYCLE 9A UNSAFE REPORT FILED #911305 | DOB VIOLATION - ACTIVE |
| Oct 11, 2023 | HAZARDOUS CONDITION (FACADE) CYCLE 9A UNSAFE REPORT FILED #911291 | DOB VIOLATION - ACTIVE |
| Oct 9, 2023 | HAZARDOUS CONDITION (FACADE) CYCLE 9A UNSAFE REPORT FILED #911290 | DOB VIOLATION - ACTIVE |
| Aug 15, 2023 | HAZARDOUS CONDITION (FACADE) CYCLE 9A UNSAFE REPORT FILED #911224 | DOB VIOLATION - ACTIVE |
| Aug 2, 2023 | HAZARDOUS CONDITION (FACADE) CYCLE 9A UNSAFE REPORT FILED #911211 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #03982 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #04606 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #04526 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #03983 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 INTERNAL HGH PRESSURE INSPECTION #03981 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #03436 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #03371 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #02851 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #02850 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL HGH PRESSURE INSPECTION #02849 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #02278 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #02198 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #01624 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #01623 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 INTERNAL HGH PRESSURE INSPECTION #01622 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION #01066 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION #00470 | DOB VIOLATION - ACTIVE |
| Jun 30, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL HGH PRESSURE INSPECTION #00469 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION #03426 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION #02926 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION #02928 | DOB VIOLATION - ACTIVE |
| Jun 20, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2019 EXTERNAL HGH PRESSURE INSPECTION #02927 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01929 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00808 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00807 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00806 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00805 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 INTERNAL HIGH PRESSURE INSPECTION #00804 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01932 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01933 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01931 | DOB VIOLATION - ACTIVE |
| Apr 25, 2023 | HIGH PRESSURE BOILER VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL HIGH PRESSURE INSPECTION #01930 | DOB VIOLATION - ACTIVE |
| Feb 22, 2022 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9A TECHNICAL REPORT BY 02/21/2022 #01172 | DOB VIOLATION - ACTIVE |
Showing 60 of 128. Full list on the agency site.
| Issued | Violation | Status |
|---|---|---|
| Oct 2, 2026 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Report | Active |
| Oct 2, 2026 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Report | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Oct 31, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle C (premises is in Community District 9) | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Aug 29, 2025 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Report | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-HP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for HP Device | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Report | Active |
| Sep 11, 2024 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Report | Active |
Showing 60 of 164. Full list on the agency site.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Report | Open |
| Oct 2, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Report | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 27, 2026, 11:02 AM ET. BBL 3048290001.