2 floors · 14,500 sq ft · built 1925 · class E1 · owner of record: Bsp Realty Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 45 days | Keep the report on file (not filed with DOB) |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 776 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Apr 15, 2026 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. OBSERVED AT EXP 1 EXTERIOR FACADE DAMAGED/MISSING MASONRY BRICKS, MORTAR JOINTS, AND MAJOR VERTICAL AND HORIZONTAL CRACKS AT VARIOUS LOCATIONS AND WHERE TH #39184686X | Dec 11, 2026 | $2,500 |
| Mar 2, 2022 | Construction CLASS - 1 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIOLATION#35581294N ISSUED ON 8/12/21 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01.WORK WITHOUT PERMIT.REM:C #35569372P | Jun 3, 2022 DEFAULT | $12,500 |
| Mar 2, 2022 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIOLATION#35581273L ISSUED ON 8/21/21 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01.OCCUPANCY CONTRARY TO THA #35569371N | Jun 3, 2022 DEFAULT | $5,000 |
| Mar 2, 2022 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIOLATION#39047214R ISSUED ON 9/9/21 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01.FAILURE TO OBEY A VACATE O #35569370L | Jun 3, 2022 DEFAULT | $5,000 |
| Dec 17, 2021 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIOLATION#39047214R ISSUED ON 9/9/2021 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01.REMEDY:COMPLY WITH COMMI #35566911L | Jul 29, 2022 IN VIOLATION | $3,125 |
| Dec 8, 2021 | Construction CLASS - 1 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIOLATION#35581274N ISSUED ON 8/21/2021 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01.NO PERMIT OR APPLICATIO #35565028H | Feb 16, 2023 IN VIOLATION | $2,500 |
| Dec 8, 2021 | Construction CLASS - 2 FAILURE TO COMPLY WITH THE COMMISSIONER'S ORDER CONTAINED IN SUMMONS/VIOLATION#35581273L ISSUED ON 8/21/2021 AND TO FILE A CERTIFICATE OF CORRECTION PURSUANT TO 28-201.1 AND 1RCNY 102-01.REMEDY:COMPLY WITH COMM #35565029J | Feb 16, 2023 IN VIOLATION | $1,250 |
| Sep 9, 2021 | Construction CLASS - 1 FULL VACATE ORDER DUE TO SUBSTANTIAL FIRE DAMAGE TO THE REAR OF BUILDING ISSUED ON 08/21/2021. AS OF 09/09/2021 FIRST FLOOR FRONT SECTION OCCUPIED AND BEING OPERATED AS ALUMINUM CAN DEPOSITORY/COLLECTION CENTER #39047214R | Apr 8, 2022 IN VIOLATION | $4,800 |
| Aug 21, 2021 | Construction CLASS - 1 OCCUPANCY CONTRARY TO THAT ALLOWED BY CERTIFICATE OF OCCUPANCY OR BUILDING DEPT RECORDS. C OF O #28611 STATES 2ND FLOOR TO BE OCCUPIED AS SHOWROOM AND OFFICE FOR 10 PERSONS MAY 2RD FLOOR NOW OCCUPIED AS CHURCH #35581273L | Dec 17, 2021 IN VIOLATION | $2,500 |
| Aug 21, 2021 | Construction CLASS - 1 WORK WITHOUT PERMIT.AT ROOF LEVEL ALL JOISTS REPLACED WITH NEW METAL JOISTS AND SHEATHING.NO PERMITS ON FILE.REMEDY:OBTAIN PERMITS. #35581274N | Dec 17, 2021 IN VIOLATION | $2,500 |
| Mar 22, 2005 | Construction Hazardous 20050805YAT THE TIME OF INSPECTION WITH THE BUILDING BEING VACANT. REMEDY: SEAL BUILDING AS PER BLDG. DEPT SPECIFICATION #34468767K | Jun 16, 2006 WRITTEN OFF | $0 |
| May 24, 2004 | Construction Non-Hazardous FAILURE TO MAINTAIN BUILDING.DEFECTS NOTED:FRONT FACADE,SECOND FLOOR AT EAST SIDE,DOOR AND WINDOW PARTIALLY OPEN TO DROP COUNTER BALANCE STAIR.DOOR OPEN AT TOP AND WINDOW SAME.REMEDY:MAINTAIN BUILDING.SEAL BUIL #34434046P | Aug 9, 2004 WRITTEN OFF | $0 |
| Nov 28, 2003 | Construction Hazardous FAILURE TO MAINTAIN BUILDING. HAZARDOUS- WORK NOTED: ATFRONT OF PREMISES, AT SECOND FLOOR AREA TWO (2) WINDOWS OPEN TO BLDG ADJACENT. REMEDY: MAINTAIN BUILDING. IMMEDIATELY MAKE SITE SAFE #34423933H | Jan 16, 2004 WRITTEN OFF | $0 |
| Jun 19, 2000 | Construction Non-Hazardous FAILURE TO MAINTAIN. DEFECT IS: CRACKED DEFECTIVE + LEARIZIG BRICK PERSPET WOLL AT FRONT OF BUILDING. REMEDY-MAKE NECESSARY REPAIRS IN A SOFE MOUNER. #34252936J | Aug 11, 2000 WRITTEN OFF | $0 |
| Dec 7, 1994 | Construction Non-Hazardous EXIT SIGN DEFECTIVE/FAIL TO MEET BUILDING CODE STONDARDS. EXIT SIGNS DEFECTIVE AND MISSING SOUTH/EAST FRONT. REMEDY: REPLACE SIGN AND MAINTAIN. #34117023N | Jan 20, 1995 WRITTEN OFF | $0 |
| Issued | Violation | Status |
|---|---|---|
| Dec 22, 2021 | FAIL TO CERTIFY CLASS 1 FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION #00282 | DOB VIOLATION - ACTIVE |
| Nov 10, 2021 | FAIL TO CERTIFY CLASS 1 FAILURE TO CERTIFY CORRECTION ON IMMEDIATELY HAZARDOUS (CLASS 1) ECB VIOLATION #00202 | DOB VIOLATION - ACTIVE |
| Aug 23, 2021 | CONSTRUCTION EMERG WORK:DUE TO 3-ALARM FIRE 8/21/21 BLDG@REAR SUFERD EXTENSIVE FIRE DMG.EXTN ROOF IS OF LGHT GAUGE JOIST ON MASN WALLS.ROOF DMG+PRTLY COLP PARPT WALLS DISENGAGED FRM WALLS LEAN@RISK COLP&HAZ.WALLS NOT PRP BRCD OWNR IMMD ENGAG NYSPE+ENDORS CONTR PRTLY DEMO ALL FALL/OVRHEAD HAZ+TMP BRCE EXTR WALLS. #FEU20301FF | DOB VIOLATION - ACTIVE |
| Aug 23, 2021 | CONSTRUCTION FTM SAFE CONDN:DUE 3 ALARM FIRE 8/21/21 BLDG SUFRD EXTNSVE FIRE DMG.AT REAR EXTN,ROOF LIGHT GAUGE JOIST OVR MASN WALLS.ROOF EXTNSVE DMG&PRTLY COLP.PARAPT WALLS DISENG FRM WALLS LEAN@RISK PRTLY COLP.WALLS NOT PROP BRCD.OWNR MUST HIRE A NYSPE+ENDORSE CONTR EVALU WHOLE BLDG+OBTAN PRMTS FOR RPRS.PRMT FO #FEU20302FF | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Jan 8, 2026 | Gas Piping - LL152 FTF-PL-PER Cycle 2, Sub-cycle A (premises is in Community District 3) | Active |
| Dec 22, 2021 | AEUHAZ FTC-AEU-HAZ | Active |
| Nov 10, 2021 | AEUHAZ FTC-AEU-HAZ | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 16, 2026, 11:36 AM ET. BBL 2029050020.