| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Sep 15, 2026 | Unknown CLASS - 1 AT THE TIME OF INSPECTION SIX-STORY NEW BUILDING I OBSERVED AT EXPOSURE #4 NO OVERHEAD PROTECTION FOR ADJACENT PROPERTY'S BALCONY. FACADE INCOMPLETE. FAILURE TO PROVIDE OVERHEAD PROTECTION CREATES HAZARD FOR PU #39559162N | Nov 25, 2026 PENDING | $10,000 |
| Sep 15, 2026 | Construction CLASS - 1 AT THE TIME OF INSPECTION SIX-STORY NEW BUILDING I OBSERVED BAKER SCAFFOLD ON SITE AT VARIOUS LOCATION WITHOUT OUTRIGGERS TO PREVENT IT FROM FALLING. FAILURE TO PROVIDE AND MAINTAIN THE BAKER'S SCAFFOLD IN ACCO #39559161L | Nov 25, 2026 PENDING | $2,500 |
| Sep 15, 2026 | Unknown CLASS - 1 AT THE TIME OF INSPECTION SIX-STORY NEW BUILDING I OBSERVED AT EXPOSURE #1, ADJACENT TO SIDEWALK SHED MATERIALS STORED ON STREET AND DELIVERY TRUCK. THERE WAS NO 4 FEET SOLID BARRIER FROM GROUND LEVEL WITH 18 G #39559160J | Nov 25, 2026 PENDING | $5,000 |
| Sep 11, 2026 | Unknown CLASS - 2 BC 3308.7-GUARDRAIL SYSTEM-OBSERVED INADEQUATE GUARDRAIL SYSTEM ON WINDOWS OPENING THROUGH OUT WHOLE BUILDING-ALL GUARDRAIL SYSTEM MISSING/NOT INSTALLED TOE BOARD AS REQUIRED(DEBRIS VISIBLE BEHIND ON BALCONIES) #39559096Y | Nov 18, 2026 PENDING | $2,500 |
| Sep 11, 2026 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION I OBSERVED VERY BIG AMOUNT/PILES OF GARBAGE/DEBRIS ACCUMULATED IN COURTYARD WITH WORKERS WORKING AROUND IT/WALKING THROUGH IT-MAKING IN HAZARDOUS FALL/FIRE CONDITIONS #39559099J | Nov 18, 2026 PENDING | $2,500 |
| Sep 11, 2026 | Unknown CLASS - 2 OSUPPORTED SCAFFOLD INSTALLED AT EXP#4 APPROX. 2 FEET FROM ADJOINING PROPERTY WINDOWS(436 CARROLL STR) -SUPPORTED SCAFFOLD NET ON SIDE WAS NOT TIED ADEQUATELY/LOOSE , PLATFORM(PLANKS) CLOSE TO WINDOWS,NO TOE BO #39559097X | Nov 18, 2026 PENDING | $2,500 |
| Mar 4, 2026 | Construction CLASS - 1 AT THE TIME OF MY INSPECTION OF A PROPOSED 6-STORY NEW BUILDING AT SOE PHASE. I OBSERVED EXCAVATION OPERATION AND PREPARATION FOR PILE INSTALLATION, UPON REVIEW OF SITE SAFETY PLANS, IT SHOWS PILE MACHINE AND E #39551193J | Feb 9, 2027 | $2,500 |
| Mar 4, 2026 | Unknown CLASS - 1 3307.2.1.-AT THE TIME OF INSPECTION OF A PROPOSED 6-STORY NEW BUILDING AT SOE PHASE. I OBSERVED PEDESTRIAN WALKWAY YODOK JERSEY BARRIERS ON STREET WAS 39 INCHES AT EXPOSURE #1, UPON REVIEW OF DOT PERMIT, PEDEST #39551194L | Feb 9, 2027 | $5,000 |
None open.
None open.
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 15, 2026 | ECB | Unknown: AT THE TIME OF INSPECTION SIX-STORY NEW BUILDING I OBSERVED AT EXPOSURE #4 NO OVERHEAD PROTECTION FOR ADJACENT PROPERTY'S BALCONY. FACADE INCOMPLETE. FAILURE TO PROVIDE OVERHEAD PROTECTION CREATES HAZARD FOR PU | Open |
| Sep 15, 2026 | ECB | Construction: AT THE TIME OF INSPECTION SIX-STORY NEW BUILDING I OBSERVED BAKER SCAFFOLD ON SITE AT VARIOUS LOCATION WITHOUT OUTRIGGERS TO PREVENT IT FROM FALLING. FAILURE TO PROVIDE AND MAINTAIN THE BAKER'S SCAFFOLD IN ACCO | Open |
| Sep 15, 2026 | ECB | Unknown: AT THE TIME OF INSPECTION SIX-STORY NEW BUILDING I OBSERVED AT EXPOSURE #1, ADJACENT TO SIDEWALK SHED MATERIALS STORED ON STREET AND DELIVERY TRUCK. THERE WAS NO 4 FEET SOLID BARRIER FROM GROUND LEVEL WITH 18 G | Open |
| Sep 11, 2026 | ECB | Construction: OBSERVED NEEDLE BEAMS WITH 3.5' SUPPORTED SCAFFOLD INSTALLED AT 4TH FL-EXP#2 CONTRARY TO PLANS -BEAMS NOT ATTACHED TO SLAB WITH ANGLES/BOLTS THROUGH SLAB,NO STEEL PLATES ANCHORED TO SLAB -STOP ALL USE OF NEEDL | Closed |
| Sep 11, 2026 | ECB | Construction: SUPPORTED SCAFFOLD INSTALLED IN COURTYARD CONTRARY TO PLANS-FIRST ROW USING 5' FRAME THEN 2' FRAME ON TOP -NOT ON PLANS,USING CLAMPS FOR CROSS BRACING-NOT ON PLANS,CONFIGURATION OF FRAMES ON BALCONIES NOT AS ON | Closed |
| Sep 11, 2026 | ECB | Unknown: BC 3308.7-GUARDRAIL SYSTEM-OBSERVED INADEQUATE GUARDRAIL SYSTEM ON WINDOWS OPENING THROUGH OUT WHOLE BUILDING-ALL GUARDRAIL SYSTEM MISSING/NOT INSTALLED TOE BOARD AS REQUIRED(DEBRIS VISIBLE BEHIND ON BALCONIES) | Open |
| Sep 11, 2026 | ECB | Construction: AT THE TIME OF MY INSPECTION I OBSERVED VERY BIG AMOUNT/PILES OF GARBAGE/DEBRIS ACCUMULATED IN COURTYARD WITH WORKERS WORKING AROUND IT/WALKING THROUGH IT-MAKING IN HAZARDOUS FALL/FIRE CONDITIONS | Open |
| Sep 11, 2026 | ECB | Unknown: OSUPPORTED SCAFFOLD INSTALLED AT EXP#4 APPROX. 2 FEET FROM ADJOINING PROPERTY WINDOWS(436 CARROLL STR) -SUPPORTED SCAFFOLD NET ON SIDE WAS NOT TIED ADEQUATELY/LOOSE , PLATFORM(PLANKS) CLOSE TO WINDOWS,NO TOE BO | Open |