7 floors · 64,294 sq ft · built 1928 · class O6 · owner of record: Eleanor 65th Street Realty Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 50 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2024-07-31 (Accepted). Agency page | Dec 31, 2026 in 50 days | 1 of 1 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 64,294 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 171 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 171 days | Annual filing |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. DOB facade records for this building show $826,000 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2028 in 467 days | No Cycle 10 report on record yet |
| Energy audit and retro-commissioning (2028) Likely applies Local Law 87 · Calendar year 2028 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 1118). Agency page | Dec 31, 2028 in 781 days | Next due 2028 |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1146 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Apr 11, 2024 | Local Law CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE REQUIRED CYCLE 9B REPORT OF CRITICAL EXAMINATION DOCUMENTING CONDITION OF EXTERIOR WALL AND APPURTENANCES REQUIRED BY 28-302.4 FOR CONTROL #903398. REMEDY: SUBMIT ACCEPTABLE REQU #37027696H | Nov 6, 2025 ADMIT/IN-VIO | $0 |
| Apr 9, 2021 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDINGS FACADE AND APPURTENANCES.NOTE:AT THE TIME OF INSPECTION VIEW AT EXPOSURE 1 SOUTH ELEVATION:BULGING MASONRY 2NDFLOOR CRACK AT SOUTH EAST PARAPET WALL,CRACK WATER TABLE AND DAMAGED E #35548671M | Oct 21, 2021 IN VIOLATION | $0 |
| Apr 9, 2021 | Construction CLASS - 2 FAILURE TO COMPLY WITH COMMISSIONER'S ORDER TO FILE A CERTIFICATE OF CORRECTION WITH THE DEPARTMENT OF BUILDINGS.NOTE:AT THE TIME OF INSPECTION RESPONDENT DID NOT COMPLY WITH PREVIOUS VIOLATION#35538975L ISSUED #35548672Y | Oct 21, 2021 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2023 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 9B TECHNICAL REPORT BY 2/21/2023 #01843 | DOB VIOLATION - ACTIVE |
| Aug 30, 2013 | NO REPORT AND / OR LATE FILING (FACADE) FAILED TO FILE FISP CYCLE 7B TECHNICAL REPORT BY 08/21/2012 #00498 | DOB VIOLATION - ACTIVE |
| Nov 30, 2007 | LOCAL LAW 11/98 - FACADE #NRF43053 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Feb 22, 2023 | Facades FISPNRF CYCLE 9B NO REPORT FILED | Active |
| Jul 31, 2018 | Facades FISPNRF FAILED TO FILE FISP CYCLE 8B TECHNICAL REPORT BY 02/21/2018 | Active |
| Nov 30, 2007 | Facades LL1198 CYCLE 6 NO REPORT FILED | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)