| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 61 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (4 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2025-12-19 (Accepted). Agency page | Dec 31, 2026 in 61 days | 4 of 4 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 175,297 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 182 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 182 days | Annual filing |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 792 days | Next cycle year 2028 |
| Energy audit and retro-commissioning (2034) Likely applies Local Law 87 · Calendar year 2034 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 404). Agency page | Dec 31, 2034 in 2983 days | Next due 2034 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Feb 2, 2026 | Construction CLASS - 2 RE-ISSUED #35691832X. EXIT DOOR NOT SELF-CLOSING. AT THE TIME OF INSPECTION, THE FOLLOWING EXIT DISCHARBE DOORS WERE NOT SELF-CLOSING PROPERLY:-4, 5, 6, 7, AND 9. REMEDY: REPAIR/REPLACE DOOR. #35724898R | Feb 13, 2026 POP/IN-VIO | $0 |
| Feb 2, 2026 | Construction CLASS - 2 RE-ISSUED #35691833H. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION, THE FOLLOWING FPSC SMOKE DOORS WERE NOT SELF-CLOSING:-STAIRWELL #DOORS, CORRIDOR DOORS NEXT TO STAIRWELL 4 #35724897P | Feb 13, 2026 POP/IN-VIO | $0 |
| Feb 2, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: AT THE TIME OF INSPECTION, THE FOLLOWING CLASSROOM DOORS WERE NOT SELF-CLOSING:-414, 413, 402, 406, 400, 404, 401, 402, 317A, 316, 312, 309, 307, 308, 302, #35728752M | Feb 17, 2026 POP/IN-VIO | $0 |
| Feb 2, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: ILLUMINATION FOR EXITS, EXIT DISCHARGES AND PUBLIC CORRIDORS PER BC 1006.1; 27-381. AT THE TIME OF INSPECTION, EMERGENCY LIGHT #2 STAIR 2 AND 3 WAS NOT WOR #35728755H | Feb 17, 2026 POP/IN-VIO | $0 |
| Feb 2, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: AT THE TIME OF INSPECTION, THE WINDOW AND DOORS IN STAIRWELL TO SECOND FLOOR ROOF AREDETACHING FROM WALL. LINTEL, JAMB AND SILL ARE SEPARATED FROM WALL. RE #35728751K | Feb 17, 2026 POP/IN-VIO | $0 |
| Feb 2, 2026 | Construction CLASS - 2 RE-ISSUED #35691834J. FAILURE TO MAINTAIN BUILDING WALL(S) OR APPURTENANCES. AT THE TIME OF INSPECTION, EXTERIOR FACADE HAS BECOME COMPROMISED, ALLOWING WATER TO SEEP IN THE BUILDING AT VARIOUS LOCATIONS CAUSIN #35728750Z | Feb 17, 2026 POP/IN-VIO | $0 |
| Feb 2, 2026 | Construction CLASS - 2 28-301.1. UNLAWFUL PLACEMENT OF FURNISHINGS, DECORATIONS OR OTHER OBJECTS AT EXITS THAT OBSTRUCT ACCESS TO, EGRESS FROM OR VISIBILITY THEREOF PER FDNY 2008 CODE; FC 1027.4. AT THE TIME OF INSPECTION, THE FOLLOW #35728753Y | Feb 17, 2026 POP/IN-VIO | $0 |
| Feb 2, 2026 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER: USE OF PROHIBITED DOOR AND/OR HARDWARE PER BC 1008.1.8; 27-371(J). AT THE TIME OF INSPECTION, CLASSROOM DOORS THROUGHOUT THE SCHOOL HAS SPHERICAL KNOB/HAND #35728754X | Feb 17, 2026 POP/IN-VIO | $0 |
| Feb 2, 2026 | Construction CLASS - 2 RE-ISSUED #35691831Y. FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION, WATER INFILTRATION IN THE 4TH FLOOR STAIRWELL #7 CAUSED BULDING AND SPALLING ON WALLS AND COILING. GYM WAL #35724899Z | Feb 13, 2026 POP/IN-VIO | $0 |
| Jan 27, 2026 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER. AT THE TIME OF INSPECTION, MULTIPLE CRACKS AND DELAMINATION OF CONRETE WERE OBSERVED ON THE TOP OF HAND BALL COURT WALL APPROX. 16' HIGH. THE CONCRETE WALL #35724887L | Feb 13, 2026 POP/IN-VIO | $0 |
| Mar 11, 2025 | Construction CLASS - 2 REISSUE#35678677Z FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER.NOTED EVIDENCE AT WATER DAMAGE,SPALLING PLASTER ON WALLS & CEILINGS.LOCATIONS STAIR B/C BULKHEAD 4TH FL GYM & EXIT 6 & 7 STAIR.2ND FL GYM #35691831Y | May 20, 2025 POP/IN-VIO | $0 |
| Mar 11, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED INTERIOR FPSC SMOKE DOORS NOT OPENING/CLOSING PROPERLY LOCATIONS:3RD FL STAIR B/C,2ND FL STAIR E,1ST FL:EXIT 9 SMOKE DOORS,STAIR E & D,EXIT 4 & 5 SMOK #35691833H | May 20, 2025 POP/IN-VIO | $0 |
| Mar 11, 2025 | Construction CLASS - 2 REISSUE#35663193K EXIT DOOR NOT SELF-CLOSING.NOTED EXTERIOR DOORS AT EXIT#9,6,7,4 & 5 NOT OPENING OR CLOSING PROPERLY.REM:REPAIR/REPLACE DOORS. #35691832X | May 20, 2025 POP/IN-VIO | $0 |
| Mar 11, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.NOTED SOUTH ROOFIN DISREPAIR,MISSING SECTIONS OF ROOFING INSULATION & GRAVEL EXPOSED SECTIONS OF DETERIORATING INSULATION & LOOSE/DETACHED METAL FLASHING.RE #35691835L | May 20, 2025 POP/IN-VIO | $0 |
| Mar 11, 2025 | Construction CLASS - 2 FAILURE TO MAINTAIN BUILDING WALL(S)OR APPURTENANCES.NOTED BUILDINGS EXTERIOR WALLS HAVE BECOME POROUS.ALLOWING WATER INTO INTERIOR SPACES DETERIORATED MORTAR JOINTS & CRACKING NOTED AT SCATTERED LOCATIONS.REM: #35691834J | May 20, 2025 POP/IN-VIO | $0 |
| Feb 12, 2024 | Construction CLASS - 2 REISSUE#35663194M FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER.SPALLING PLASTER & BY GYM 2ND FLOOR,EXIT 6 & 7,EXIT 8,EXIT 9.REM:REPAIR AND/OR REPLACE. #35678677Z | Apr 22, 2024 POP/IN-VIO | $0 |
| Jan 24, 2023 | Construction CLASS - 2 REISSUE #35383913N:FAILURE TO MAINTAIN BUILDING IN CODE-COMPLIANT MANNER:SPALLING & CRACKED PLASTER @14TH FL NEAR RM #617, 3RD FL 313, 2ND FL GYM & EXIT #8.REMEDY:COMPLY WITH CODE. #35663194M | May 9, 2023 POP/IN-VIO | $0 |
| Jan 24, 2023 | Construction CLASS - 2 REISSUE #35260607P EXIT DOOR NOT SELF-CLOSING.2ND FL THROUGHOUT AUDITORIUM BTWN 1ST & 2ND FL EXIT #9, #6, #7.REMEDY:COMPLY WITH CODE. #35663193K | May 9, 2023 POP/IN-VIO | $0 |
| Mar 4, 2022 | Construction CLASS - 2 REISSUE35548339K NOTED:@4FL GYM STAIRWELL BY EXIT6&7,2FL GYM@EXI8&1FL BY EXIT9,ALL HAVE SPALLING PAINT&CRACKS IN VARIOUS AREAS THRUOUT.REPAIR &OR REPLACE #35636305M | Jun 21, 2022 POP/IN-VIO | $0 |
| Mar 4, 2022 | Construction CLASS - 2 REISSUE35548341J NOTED:@4FL GYM ENTRANCE BY EXIT4&5,3FL SMOKE BY STAIRB,2FL SMOKE BY 215,SMOKE BY STAIRB,1FL SMOKE BY EXIT9&EXTERIOR DOOR AUDITORIUM MAIN ENTRANCE,1FL SMOKE@STAIRE,BSMT SMOKE@EXIT6&7,BSMT ENTRAN #35636303Z | Jun 21, 2022 POP/IN-VIO | $0 |
| Mar 2, 2021 | Construction CLASS - 2 REISSUE#35467684R-NOTED:AT THE 4TH FLOOR EXIT#11 BY 404,2ND FLOOR BY THE ELEVATOR,STAIR C BY 213,1ST FLOOR STAIR E BY 114,SMOKE DOOR TO 1ST FLOOR LOWER LEVEL BY THE AUDITORIUM,1ST FLOOR SMOKE BY EXIT#9,AUDITORI #35548341J | Aug 3, 2021 POP/IN-VIO | $0 |
| Mar 2, 2021 | Construction CLASS - 2 REISSUE#35467686K-NOTED:AT THE 4TH FLOOR GYMNASIUM BY UNIT 6 AND 7,3RDFLOOR ROOM 313,2ND FLOOR GYMNASIUM AT EXIT 8 AND 1ST FLOOR BY EXTERIOREXIT DOOR #9;ALL HAVE SPALLING PAINT AND CRACKS IN VARIOUS AREAS THROU #35548339K | Aug 3, 2021 POP/IN-VIO | $0 |
| Feb 6, 2020 | Construction CLASS - 2 REISSUE#35383913N DATE OF ISSUE:02-08-2019.FAILURE TO MAINTAIN BUILDING IN CODE COMPLIMANT MANNER SPALLING AND CRACKED PLASTER AT 4TH FLOOR NEAR EIXT 617 DOOR WAY 3RD FLOOR ROOM 313 CEILING 2ND FL GYM AT EXIT 8 #35467686K | May 26, 2020 POP/IN-VIO | $0 |
| Feb 6, 2020 | Construction CLASS - 2 REISSUE #35381220L DATE OF ISSUE 02-08-2019.EXIT DOOR NOT SELF CLOSING AT FIRST FLOOR EXIT-9(OUTSIDE)ONE DOOR FROM LOBBY RIGH TSIDE ONE DOOR & 2ND FLOOR STAIR CASE-C EXIT 3 ONE DOOR NOT SELF CLOSING PROPERLY AT #35467684R | Aug 4, 2020 POP/IN-VIO | $0 |
| Jul 17, 2019 | Boilers CLASS - 2 FOUND UNREGISTERED LOCHINVAR AWN501PM BOILER IN BOILER ROOM., MAINTAIN BOILER; REGISTER BOILER #39005804L | Jul 19, 2019 POP/IN-VIO | $0 |
| Feb 8, 2019 | Construction CLASS - 2 REISSUE #35311974Y DATE OF ISSUE 01-29-2018 EXIT DOOR NOT SELF-CLOSING,AT FIRST FLOOR MAIN ENTRANCE ONE EXIT DOOR NOT SELF CLOSING PROPERLY AT 2ND FLR EXIT NEXT TO ELEVATOR.AUDITORIUM BETWEEN 1ST AND 2ND FOOR N #35381220L | May 7, 2019 POP/IN-VIO | $0 |
| Feb 8, 2019 | Construction CLASS - 2 REISSUE: 35317536L DATE OF ISSUE 01.29.2018. FAILURE TO MAINTAIN BLDG IN CODE COMPLIANT MANNER SPALLING AND CRACKED PLASTER AT 4TH FLOOR NEAR EXIT 617 DOORWAY 3RD FLOOR ROOM 313 CEILING 2ND FL GYM AT EXT 8 AND #35383913N | May 7, 2019 POP/IN-VIO | $0 |
| Jan 29, 2018 | Construction CLASS - 2 REISSUED 35260607P/EXIT DOOR NOT SELF CLOSING:NOTE AT 2NF FLR EXIT NEXT TO ELEVATOR AUDITORIUM BETWEEN 1ST AND 2ND FLR DOOR NOT CLOSING ALSOEXIT DOORS AT EXIT 9 FOR RIGHT HAND SIDE AND EXIT 6 & 7 FOR LEFT HAND #35311974Y | Apr 17, 2018 POP/IN-VIO | $0 |
| May 3, 2017 | Construction CLASS - 2 EXIT DOOR NOT SELF CLOSING. NOTED AT 2ND FLR EXIT NEXT TO ELEVTOR,AUDITORIUM BETWEEN 1ST AND 2ND FLR, HALL FLAGS EXIT 9 HAVE SOME DOORS THATARE NOT SELF CLOSING. ALSO OBSERVED AT THE BASEMENT EXIT 6/7 BY EMERG #35260607P | Jul 11, 2017 POP/IN-VIO | $0 |
| Issued | Violation | Status |
|---|---|---|
| Jan 13, 1997 | LOCAL LAW 10/81 - ELEVATOR #03645 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 29, 2026 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2025 Cat1 Test Affirmation of Correction | Active |
| Oct 29, 2026 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Dec 15, 2025 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2024 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Oct 10, 2025 | Elevators FTC-VT-PER-CO Violation Issued-Failure To File 2024 Periodic Inspection Affirmation of Correction | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 25, 2024 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2023 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 11, 2024 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2023 Cat1 Test Affirmation of Correction | Active |
| Sep 11, 2024 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2023 Periodic Inspection Report | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2021 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2021 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2018 Cat1 Test Affirmation of Correction | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2020 Cat1 Test Affirmation of Correction | Active |
| Aug 25, 2023 | Elevators FTF-VT-PER-CO Violation Issued-Failure To File 2022 Periodic Inspection Report | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Cat1 Test Affirmation of Correction | Open |
| Oct 29, 2026 | DOB Safety | Elevators: Violation Issued-Failure To File 2025 Periodic Inspection Affirmation of Correction | Open |