1 floors · 25,675 sq ft · built 1982 · class K2 · owner of record: Nyc Department Of Small Business Services
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 70 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 25,675 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 191 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 191 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 2 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1166 days | Next cycle year 2029 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jul 6, 2026 | Construction CLASS - 1 CHAIN LINK FENCE HAS BEEN VANDALIZED AND A HOLE HAS BEEN MADE TO ACCESS CONSTRUCTION SITE, REPAIR AND/REPLACE; REFER TO POP AGENCY AND MAKE NEEDED REPAIRS #39194792Z | Jul 9, 2026 POP/IN-VIO | $0 |
| Oct 16, 2025 | Unknown CLASS - 2 I OBSERVED UNSAFE ELECTRICAL CONDITIONS WIRES, BOXES AND FIXTURES DAMAGE DUE TO FIRE., COMPLY WITH EC; FIX ALL CONDITIONS ACCORDING TO NEC AND NYC AMENDMENTS #39164249J | Dec 30, 2025 DEFAULT | $4,000 |
| Issued | Violation | Status |
|---|---|---|
| Sep 2, 2026 | CONSTRUCTION OBSERVED SEVERE STRUCTURE CONDITIONS AT CENTER OBSERVED AT 1ST & 2ND FLOORS A LARGE SEPARATION IN FLOORS RUNNING THROUGH ENTIRE BUILDING. ENTIRE BUILDING IS ANGLED AT EXPO 2 LEFT SIDE REAR DOCK IS PARTIALLY SUBMERGED IN WATER ENTIRE STRUCTURE POTENTIAL TO COLLAPSE. #26-02153 | DOB VIOLATION - ACTIVE |
| Sep 2, 2026 | CONSTRUCTION EMERGENCY WORK ORDER.BLDG STRCTRE IS LEANING SIGNIFICANTLY TOWARDS THE EXP2SIDE.THERE IS A LARGE SEPARATION@THE CENTER OF THE BLDG FRM THE STRCTRL MOVEMNT.PRTL CLLPSE@THE 1STFL&EXT DOCK.OWNR TO IMMED RTAIN NYSPE,DEMO ENDRSD CNTRCTR,&ABATEMENT CNTRCTR TO IMMED DEMO THE BLDG SUBMT PROPOSED MEANS&METHD #FEU40202AK | DOB VIOLATION - ACTIVE |
| Sep 2, 2026 | CONSTRUCTION EMERGENCY WORK ORDER.AT TIME OF INSPCTN,OBSRVD THE BLDG TO BE IN A STATE OF EXTREME DISRPAIR.BLDG STRCTRE IS LEANIG SIGNIFICANTLY TOWARDS THE EXP2SIDE THERE IS A LARGE SEPARATION@EXT WALLS BULGED.IMMED RPAIR THE EXISTNG TGHTBRD CNSTRCTN FENCE TO SECURE THE SITE FRM UNAUTHORIZD ACCESS.FILE FOR FENCE #FEU40201AK | DOB VIOLATION - ACTIVE |
| Oct 21, 2025 | CONSTRUCTION I OBSERVED FIRE DAMAGE THROUGHOUT THE BUILDING WIRES, BOXES AND FIXTURES DAMAGE DUE TO FIRE. #25-02365 | DOB VIOLATION - ACTIVE |
| Oct 15, 2025 | CONSTRUCTION STRUCTURE RENDERED NON-COMPLIANT. AT TIME OF INSPECTION OBSERVED STRUCTURE IN COMPLETE DISREPAIR WHERE WINDOWS ARE MISSING MULTIPLE PENETRATIONS THROUGH BUILDING EXPOSING INTERIOR TO ELEMENTS FURTHERING THE DETERIORATION. #25-02336 | DOB VIOLATION - ACTIVE |
| Oct 15, 2025 | CONSTRUCTION STRUCTURE RENDERED NON-COMPLIANT. AT TIME OF INSPECTION OBSERVED STRUCTURE IN COMPLETE DISREPAIR WHERE WINDOWS ARE MISSING MULTIPLE PENETRATIONS THROUGH BUILDING EXPOSING INTERIOR TO ELEMENTS FURTHERING THE DETERIORATION. #25-02334 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Sep 18, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle B (premises is in Community District 2) | Active |
| Sep 18, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle B (premises is in Community District 2) | Active |
| Sep 18, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle B (premises is in Community District 2) | Active |
None open.
| Date | Source | What | Now |
|---|---|---|---|
| Sep 2, 2026 | DOB | CONSTRUCTION: OBSERVED SEVERE STRUCTURE CONDITIONS AT CENTER OBSERVED AT 1ST & 2ND FLOORS A LARGE SEPARATION IN FLOORS RUNNING THROUGH ENTIRE BUILDING. ENTIRE BUILDING IS ANGLED AT EXPO 2 LEFT SIDE REAR DOCK IS PARTIALLY SUBMERGED IN WATER ENTIRE STRUCTURE POTENTIAL TO COLLAPSE. | Open |
| Sep 2, 2026 | DOB | CONSTRUCTION: EMERGENCY WORK ORDER.BLDG STRCTRE IS LEANING SIGNIFICANTLY TOWARDS THE EXP2SIDE.THERE IS A LARGE SEPARATION@THE CENTER OF THE BLDG FRM THE STRCTRL MOVEMNT.PRTL CLLPSE@THE 1STFL&EXT DOCK.OWNR TO IMMED RTAIN NYSPE,DEMO ENDRSD CNTRCTR,&ABATEMENT CNTRCTR TO IMMED DEMO THE BLDG SUBMT PROPOSED MEANS&METHD | Open |
| Sep 2, 2026 | DOB | CONSTRUCTION: EMERGENCY WORK ORDER.AT TIME OF INSPCTN,OBSRVD THE BLDG TO BE IN A STATE OF EXTREME DISRPAIR.BLDG STRCTRE IS LEANIG SIGNIFICANTLY TOWARDS THE EXP2SIDE THERE IS A LARGE SEPARATION@EXT WALLS BULGED.IMMED RPAIR THE EXISTNG TGHTBRD CNSTRCTN FENCE TO SECURE THE SITE FRM UNAUTHORIZD ACCESS.FILE FOR FENCE | Open |
| Jul 6, 2026 | ECB | Construction: CHAIN LINK FENCE HAS BEEN VANDALIZED AND A HOLE HAS BEEN MADE TO ACCESS CONSTRUCTION SITE, REPAIR AND/REPLACE; REFER TO POP AGENCY AND MAKE NEEDED REPAIRS | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 22, 2026, 5:52 PM ET. BBL 4004890023.