10 floors · 44,115 sq ft · built 1906 · class O6 · owner of record: Mandelbaum & Gluck
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 47 days | Keep the report on file (not filed with DOB) |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 44,115 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 168 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 168 days | Annual filing |
| Facade inspection report (Cycle 10B) Applies Local Law 11 / FISP · Feb 21, 2026 to Feb 21, 2028 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 0, 7 or 8 are in sub-cycle 10B. DOB facade records for this building show $45,000 in late-filing or failure-to-file penalties. Agency page | Feb 21, 2028 in 464 days | No Cycle 10 report on record yet |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 5 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1143 days | Next cycle year 2029 |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-06-17 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Jun 17, 2024 | Construction CLASS - 2 A. C. 27-929.1, FAILURE TO COMPLETE THE INSTALLATION OF A FULL SYSTEM OF AUTOMATIC SPRINKLERS AND FILE A FINAL SPRINKLER REPORT PREPARED BY A REGISTERED DESIGN PROFESSIONAL IN AN OFFICE BUILDING 100 FEET OR MOR #37028793Y | Oct 10, 2024 IN VIOLATION | $0 |
| Apr 28, 2010 | Construction CLASS - 2 FAILURE TO FILE AN ACCEPTABLE 6TH ROUND TECHNICAL REPORT IN COMPLIANCEW/CODE PROVISIONS: PERIODIC INSPECTION OF EXTERIOR WALLS AND APPURTENANCES AS REQUIRED BY ARTICLE 28.302 & THE DOB RULES AND REGULATIONS. #36013040L | Jul 15, 2010 IN VIOLATION | $0 |
| Mar 24, 2010 | Construction CLASS - 1 FAILURE TO PROVIDE SAFETY MEASURES; SIDEWALK SHED ETC. 5TH CYCLE WAS FILED "UNSAFE" BY ENGINEER, AND NO FILING OF 6TH CYCLE ENGINEER REPORT W/DOB. REMEDY: PROVIDE SAFETY MEASURES; SIDEWALK SHED, ETC. AND FILE #34744432R | Jul 15, 2010 IN VIOLATION | $0 |
| Nov 28, 2008 | Construction CLASS - 2 FAILURE TO SUBMIT AN ACCEPTABLE 6TH ROUND TECHNICAL REPORT IN COMPLIANCE WITH CODE PROVISIONS: PERIODIC INSPECTION OF EXTERIOR WALLS & APPURTENANCES AS REQUIRED BY ARTICLE 28.302 & THE D.O.B. RULES & REGULATION #36006328P | Jul 15, 2010 IN VIOLATION | $0 |
| Mar 2, 2007 | Construction Non-Hazardous SEC 27-597:QUESTIONABLE CONSTRUCTION. NOTED:AT 2ND FL A WOOD PLATFORM APPROX 9' X 20' X 40' MADE OF PLYWOOD & 2" X 6" JOISTS W/ 3"CAST IRON PIPE COLUMNS HAS BEEN ERECTED W/ STRAPS SUSPENDING THE JOISTS,THE #34533908N | Jun 14, 2007 IN VIOLATION | $0 |
| Aug 16, 1999 | Local Law Non-Hazardous FAILURE TO OBTIAN A CERTIFICATE OF ELECTRICAL INSPECTION FROM TH EBUREAU OF ELECTRICAL CONTROL FOR THE INSTALLATION OF EMERGENCY POWER TO EXIT LIGHTS FAILURE TO ONTIAN A CERTIFICATE OF ELECTRICAL INSPECTION #34176883N | Sep 30, 1999 WRITTEN OFF | $0 |
| Issued | Violation | Status |
|---|---|---|
| Nov 1, 2023 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) FAILURE TO CORRECT SWARMP CONDITIONS #00017 | DOB VIOLATION - ACTIVE |
| Feb 13, 2023 | HAZARDOUS CONDITION (FACADE) CYCLE 9B UNSAFE REPORT FILED #910719 | DOB VIOLATION - ACTIVE |
| Sep 3, 2019 | SPRINKLER FAILED TO FILE FINAL SPRINKLER REPORT BY JULY 1, 2019 #NRF00142 | DOB VIOLATION - ACTIVE |
| Oct 8, 2010 | ELEVATOR ANNUAL INSPECTION / TEST #00946 | DOB VIOLATION - ACTIVE |
| Nov 30, 2007 | LOCAL LAW 11/98 - FACADE #NRF42707 | DOB VIOLATION - ACTIVE |
| Nov 19, 2004 | LOCAL LAW 10/81 - ELEVATOR #00543 | DOB VIOLATION - ACTIVE |
| Aug 13, 2004 | ELEVATOR #9444/106169 | DOB VIOLATION - ACTIVE |
| Aug 13, 2004 | ELEVATOR #H9444106169 | DOB VIOLATION - ACTIVE |
| Apr 21, 2004 | LOCAL LAW 10/81 - ELEVATOR #00609 | DOB VIOLATION - ACTIVE |
| Mar 18, 1993 | LOCAL LAW 62/91 - BOILERS #00405 | DOB VIOLATION - ACTIVE |
| Jul 1, 1992 | LOCAL LAW 10/80 - FACADE #NRF0303 | DOB VIOLATION - ACTIVE |
| Apr 7, 1992 | LOCAL LAW 10/81 - ELEVATOR 2 #00796 | DOB VIOLATION - ACTIVE |
| Apr 25, 1991 | LOCAL LAW 10/81 - ELEVATOR 2 #00579 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Sep 18, 2025 | Gas Piping - LL152 FTF-PL-PER Cycle 1, Sub-cycle B (premises is in Community District 5) | Active |
| Nov 1, 2023 | Facades FISPFCS CYCLE 9B FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| Feb 13, 2023 | Facades FISPHAZ CYCLE 9B UNSAFE REPORT FILED | Active |
| Sep 3, 2019 | Sprinklers FTF-SP-FINAL | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |
| Oct 8, 2010 | Elevators VCAT1 | Active |
| Nov 30, 2007 | Facades LL1198 CYCLE 6 NO REPORT FILED | Active |
| Nov 19, 2004 | Elevators LL1081 | Active |
| Nov 19, 2004 | Elevators LL1081 | Active |
| Apr 21, 2004 | Elevators LL1081 | Active |
| Apr 21, 2004 | Elevators LL1081 | Active |
| Mar 18, 1993 | Boiler LL6291 | Active |
| Apr 7, 1992 | Elevators LL1081 | Active |
| Apr 7, 1992 | Elevators LL1081 | Active |
| Apr 25, 1991 | Elevators LL1081 | Active |
| Apr 25, 1991 | Elevators LL1081 | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)