4 floors · 3 apartments · 2,928 sq ft · built 1899 · class C0 · owner of record: 356 East 8 Street Llc
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 43 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 43 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 59 days | Annual |
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Sep 1, 2027 in 287 days | Registered through 2027-09-01 |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 3 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 774 days | Next cycle year 2028 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Feb 6, 2025 | Construction CLASS - 1 I POST A PARTIAL STOP WORK ORDER ON 2/5/2025 HOWEVER WHEN I CAME BACK ON THE NEXT DAY(2/6/2025) I OBSERVE THAT THE POSTER WAS REMOVED.COMPLY WITH CODE. #39536755R | Dec 17, 2026 | $2,500 |
| Feb 6, 2025 | Unknown CLASS - 1 3301.5-UNSAFE CONDITIONS. PARK ACCESS AGREEMENT WAS BETWEEN THE PARK AND SWS PERMIT HOLDER (NURUL AMIN) INSTEAD OF SUPPORTED SCAFFOLD PERMIT HOLDER (G K ENGG GROUP LLC) AND SUPPORTED SCAFFOLD IS NOT REFLECTED O #39536760L | Dec 17, 2026 | $5,000 |
| Feb 5, 2025 | Construction CLASS - 2 OBSERVED AN ACTIVE JOB SITE MISSING CONSTRUCTION FENCE AT EXP.#2,3&4 AS PER 3307.7 WHERE REQUIRED FENCE WHEN BUILDING BEING CONSTRUCTED. ALSO, AT EXP.#3 @3&4 OBSERVED NEIGHBORB VINYL FENCE WAS BROKEN DUE TO CON #39536693K | Dec 17, 2026 | $1,000 |
| Feb 5, 2025 | Unknown CLASS - 1 ACTIVE JOBSITE UNDER ALTERATION OBSERVED SIDEWALKS SHED W/ POSTS & BRACES CONTRARY TO PLANS W/ PIPE SCAFFOLD TOP OF DECK MISSING CROSS-BRACES, LOOSE PLANKS @ MULTIPLE LEVELS AT EXPOSURE 1. DAILY INSPECTIONS FOR #39536690P | Dec 17, 2026 | $5,000 |
| Feb 5, 2025 | Unknown CLASS - 1 OBSERVED DEBRIS & STORED MATERIALS ON FIRST FLOOR&CELLAR WHICH MUST BE REMOVED DAILY. ALSO OBSERVED GASOLINE TANK STORED NEXT TO COMBUSTIBLE MATERIALS. STOP ALL STORAGE OF COMBUSTIBLE MATERIALS.STOP ALL WORK AT #39536697H | Dec 17, 2026 | $2,500 |
| Feb 5, 2025 | Site Safety CLASS - 1 ACTIVE ALT. OBSRERVED TEMP. SHORING W/ MULTIPLE POSTS REMOVED FOR STRUCTURAL SUPPORT @ CELLAR &1ST FL, NO REVISED AUDIT PLANS ON-SITE, ACCUMULATED DEBRIS BLOCKED EGRESS, SF CONTRARY TO PLANS, NO DAILY INSPECTIO #39536680L | Dec 17, 2026 | $10,000 |
| Feb 5, 2025 | Construction CLASS - 1 OBSERVED SHORING AT 1ST FLOOR MISSING POST AT MULTIPLE C JOIST, INCORRECT X-BRACING. MISSING SHORING AT CELLAR LEVEL. MAKE -SHIFT SHORING CONTRARY TO THE STRUCTURAL DETAIL ON DM PLAN PAGE DM-004.STOP ALL WORK A #39536695Y | Dec 17, 2026 | $2,500 |
| Feb 5, 2025 | Unknown CLASS - 1 3303.2.3-OBSERVED AN ACTIVE ELECTRICAL PANEL ON CELLAR LEVEL WHICH EXPOSE ALL WORKERS TO ELECTRICAL HAZARD.STOP ALL WORK AT CELLAR, EXCEPT TO PROVIDE SHUT OFF LETTER FROM UTILITY COMPANY AND CONTROL ACCESS FOR #39536698J | Dec 17, 2026 | $5,000 |
| Feb 5, 2025 | Unknown CLASS - 1 3301.6.1&3305.8.7-OBSERVED MATERIALS WERE STORED ON FIRST FLOOR ON A RESTRICTED AREA. THIS WRONGFUL PLACEMENT OVERLOADS THE SLAB AS PER STRUCTURAL PLAN (S-001.00) AND MAY CAUSE COLLAPSE OF THE BUILDING.STOP AL #39536696X | Dec 17, 2026 | $5,000 |
| Dec 18, 2024 | Construction CLASS - 2 AT TIME OF INSPECTION, NOTED AN UNCOVERED DEBRIS CONTAINER, W/ SHARP CONC, WOOD AND OTHER DEBRIS PILED ABOVE, ADJ THE SWS AT EXP 1. MISSING 4' SOLID CONSTRUCTION FENCE AND 18-GAUGE WIRING ABOVE, CREATING A HAZA #39133254M | Dec 29, 2025 DEFAULT | $5,000 |
| Dec 13, 2023 | Construction CLASS - 1 FAILURE TO MAINTAIN BUILDING IN CODE COMPLIANT MANNER. BUILDING IS IN FULL STATE OF DISREPAIR WITH NO ROOF PRESENT AND ALL FRAMING AND BRACING OPEN TO THE ELEMENTS. ENTIRE REAR WALL AT EXP #3 IS OPEN TO THE ELE #39101421Y | Feb 22, 2024 DEFAULT | $3,125 |
None open.
None open.
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Nov 18, 2026, 1:51 AM ET. BBL 1003770010.