11 floors · 12 apartments · 43,369 sq ft · built 1900 · class RM · owner of record: Unavailable Owner
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual property registration Applies HPD registration · September 1 each year What this isResidential buildings with three or more units, and one- and two-family homes the owner doesn't occupy, register with HPD every year ($13 fee). An unregistered building can't start a nonpayment case in Housing Court and faces civil penalties. Agency page | Overdue | Registration expired 2026-09-01 |
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 69 days | Keep the report on file (not filed with DOB) |
| Bedbug annual filing Applies Local Law 69 · December 1 to 31 each year What this isOwners of multiple dwellings file their bedbug infestation history for the prior year with HPD and post or distribute it to tenants. Agency page | Dec 31, 2026 in 69 days | Annual |
| Annual notice: window guards and lead paint Applies HPD / Health Code · January 1 to 16 each year What this isDeliver the annual notice to every unit asking whether a child lives there (window guards for children 10 and under; lead paint for children under 6 in pre-1960 buildings), then follow up on units that don't return it by mid-February. Agency page | Jan 16, 2027 in 85 days | Annual |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 43,369 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 190 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 190 days | Annual filing |
| Gas piping inspection (2028 cycle) Likely applies Local Law 152 · During 2028 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 1 is on the 2028 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2028 in 800 days | Next cycle year 2028 |
| Facade inspection report (Cycle 10C) Applies Local Law 11 / FISP · Feb 21, 2027 to Feb 21, 2029 What this isBuildings taller than six stories file a facade inspection report by a QEWI once every five-year cycle. Tax blocks ending in 1, 2 or 3 are in sub-cycle 10C. Agency page | Feb 21, 2029 in 852 days | Filing window not open yet |
| Annual boiler inspection (1 boiler) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-04-29 (Accepted). Agency page | On file | 2026 reports accepted |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Oct 15, 2026 | Unknown CLASS - 2 AT THE TIME OF INSPECTION, A 12-STORY BUILDING WITH AN ACTIVE FACADE PERMIT WAS OBSERVED. THE DEBRIS NETTING ON THE PIPE SCAFFOLD WAS NOT PROPERLY SECURED, CONTRARY TO BC 3314.8.2, CREATING A HAZARDOUS CONDITIO #39560580Y | Dec 24, 2026 PENDING | $2,500 |
| Apr 22, 2019 | Construction CLASS - 2 FAILURE TO PROVIDE APPROVE/ACCEPTED CONSTRUCTION PLANS/DOCUMENT AT SITE. AT TIME OF INSPECTION, PLANS PROVIDED HAD OPPX # 1/04 STAMP AND STAE NOV 21.2018, BUT DID NOT HAVE THE JOB # ON THEM. REMEDY: PROVIDE APP #35409278X | Jun 13, 2019 IN VIOLATION | $315 |
| Apr 22, 2019 | Plumbing CLASS - 1 ELECTRICAL WORK WITHOUT A PERMIT. OBSERVED ON ENTIRE 2ND FLOOR APARTMENT, ALL ELECTRICAL WORK HAS BEEN REMOVED AND REPLACE WITH NEW ELECTRICAL PANEL, NEW BREAKERS, NEW BX CABLE, NEW BX BOXES FOR OUTLETS, RECEPT #35409279H | Jun 13, 2019 IN VIOLATION | $800 |
| Issued | Violation | Status |
|---|---|---|
| Aug 1, 2024 | FAILURE TO CORRECT SWARMP CONDITIONS (FACADE) FAILURE TO CORRECT SWARMP CONDITIONS #00168 | DOB VIOLATION - ACTIVE |
| Feb 21, 2024 | HAZARDOUS CONDITION (FACADE) CYCLE 9C UNSAFE REPORT FILED #911777 | DOB VIOLATION - ACTIVE |
| Mar 9, 2020 | ELEVATOR #9027/674844 | DOB VIOLATION - ACTIVE |
| Nov 16, 2005 | CONSTRUCTION #0201CF | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Oct 10, 2025 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2024 Cat1 Test Affirmation of Correction | Active |
| Aug 1, 2024 | Facades FISPFCS FAILURE TO CORRECT SWARMP CONDITIONS | Active |
| Feb 21, 2024 | Facades FISPHAZ CYCLE 9C UNSAFE REPORT FILED | Active |
| Nov 14, 2023 | Boiler FTC-BE-EXT-LP Violation Issued-Failure To File 2018 External Inspection Affirmation of Correction for LP Device | Active |
| Oct 23, 2023 | Elevators FTC-VT-CAT1-CO Violation Issued-Failure To File 2022 Cat1 Test Affirmation of Correction | Active |
| Apr 2, 2007 | Elevators LL1081 | Active |
| Apr 2, 2007 | Elevators LL1081 | Active |
| Apr 2, 2007 | Elevators LL1081 | Active |
| Feb 13, 2004 | Boiler LL6291 | Active |
| Mar 19, 2003 | Boiler LL6291 | Active |
| Mar 26, 2002 | Boiler LL6291 | Active |
| Issued | Class | Violation | Correct by |
|---|---|---|---|
| Sep 2, 2025 | C | Apt 3 · HMC ADM CODE: § 27-2017.4 ABATE THE INFESTATION CONSISTING OF ROACHES IN THE ENTIRE APARTMENT LOCATED AT APT 3, 3rd STORY, 1st APARTMENT FROM SOUTH AT WEST | Sep 28, 2025 |
| Date | Source | What | Now |
|---|---|---|---|
| Oct 15, 2026 | ECB | Unknown: AT THE TIME OF INSPECTION, A 12-STORY BUILDING WITH AN ACTIVE FACADE PERMIT WAS OBSERVED. THE DEBRIS NETTING ON THE PIPE SCAFFOLD WAS NOT PROPERLY SECURED, CONTRARY TO BC 3314.8.2, CREATING A HAZARDOUS CONDITIO | Open |
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 23, 2026, 12:40 PM ET. BBL 1001717502.