6 floors · 71,827 sq ft · built 1971 · class I6 · owner of record: 3518 Bainbridge,
New violations the morning after they're issued, plus deadline reminders. Free for one building.
| Requirement | Due | Status |
|---|---|---|
| Annual parapet observation Check Local Law 126 · By December 31 each year What this isIf the building has a parapet facing a street, sidewalk or other public way, a competent person (such as a mason, engineer or architect) must observe it every year and the owner keeps the report for DOB on request. Detached one- and two-family homes are exempt. Agency page | Dec 31, 2026 in 64 days | Keep the report on file (not filed with DOB) |
| Annual boiler inspection (6 boilers) Applies Boiler inspection · By December 31 each year What this isBoilers are inspected each calendar year and the report is filed in DOB NOW: Safety within 14 days of the inspection (low-pressure boilers in residential buildings of 5 or fewer families are exempt). Latest report on record: 2026-08-21 (Accepted). Agency page | Dec 31, 2026 in 64 days | 1 of 6 without an accepted 2026 report yet |
| Energy and water benchmarking Likely applies Local Law 84 · May 1 each year What this isBuildings over 25,000 sq ft (this lot shows 71,827 sq ft) report energy and water use for the prior calendar year through ENERGY STAR Portfolio Manager. The city's Covered Buildings List is the final word on which buildings must file. Agency page | May 1, 2027 in 185 days | Annual filing |
| Building emissions report Likely applies Local Law 97 · May 1 each year (extensions available) What this isCovered buildings file an annual greenhouse gas emissions report certified by a registered design professional. Buildings over their emissions limit owe penalties, so it pays to check early. Agency page | May 1, 2027 in 185 days | Annual filing |
| Gas piping inspection (2029 cycle) Likely applies Local Law 152 · During 2029 What this isBuildings with gas piping (except one- and two-family homes) need a periodic gas piping inspection by a licensed master plumber every four years. Community district 7 is on the 2029 cycle; certification is filed with DOB after the inspection. Buildings with no gas piping file a certification instead. Agency page | Dec 31, 2029 in 1160 days | Next cycle year 2029 |
| Energy audit and retro-commissioning (2034) Likely applies Local Law 87 · Calendar year 2034 What this isBuildings over 50,000 sq ft file an Energy Efficiency Report every ten years, in the year whose last digit matches the last digit of the tax block (block 3344). Agency page | Dec 31, 2034 in 2986 days | Next due 2034 |
| Issued | Violation | Hearing | Balance |
|---|---|---|---|
| Mar 3, 2021 | Elevators CLASS - 2 CLASS 1 VIOLATION ISSUED RTS, UPON INSPECTION OF DEVICE IT WAS FOUND OUT OF SERVICE REMEDY; REPAIR THEN NOTIFY THE NYCDOB OF SERVICE RESTORE, CLASS 2 , MISSING MANUAL LOWERING BOX KEY REMEDY; PROVIDE, MISSING H #39037083R | Dec 10, 2021 IN VIOLATION | $0 |
| May 16, 2017 | Boilers CLASS - 2 B254,36. AS PER CLASS 254-36 BURNER NOT REGISTERED AS PER DOB RECORDSCORRECT ALL VIOLATING CONDITIONS AND SUBMIT A CERTIFICATE OF CORRECT ION. #32088404Y | Jul 28, 2017 IN VIOLATION | $0 |
| Mar 13, 2009 | Boilers CLASS - 3 50 FULTON VT BOILER 10HP NB90848 GAS 2002 50 REFERENCED BOILER #2 FLUEPIPE IS COMBINED W/ ADJACENT BOILER #1 FLUE PIPE W/ NO INCREASE IN NOMINAL PIPE SIZE TO THE CHIMNEY INCREASE COMBINED FLUE PIPE SIZE OR RUN #32065549N | Sep 15, 2009 IN VIOLATION | $0 |
| Mar 13, 2009 | Boilers CLASS - 3 50 FULTON VT BOILER 10HP NB90364 GAS 2002 50 REFERENCED BOILER #1 FLUEPIPE IS COMBINED W/ ADJACENT #2 FLUE PIPE W/ NO INCREASE IN NOMINAL PIPE SIZE TO THE CHIMNEY INCREASE COMBINED PIPE SIKE OR RUN FLUE PIPES #32065548L | Sep 15, 2009 IN VIOLATION | $0 |
| Nov 2, 2005 | Boilers Non-Hazardous 50. FULTON Y.T. BOILER, 10HP, NB90848, GAS 2002 (#1) (50) THE FLUE PIPE OF THE REFERENCED HIGH PRESSURE STEAM BOILER IS CONNECTED DIRECTLY TO THE FLUE PIPE OF SIMILAR SIZE INSTALLED ON BOILER #2. CUMMULATIVE FL #32048821Z | Feb 3, 2006 IN VIOLATION | $0 |
| Nov 2, 2005 | Boilers Non-Hazardous 50. FULTON Y.T BOILER, 10HP, NB90364, GAS, 2002 (#2) (50) THE FLUE PIPE OF THE REFERENCED HIGH PRESSURE STEAM BOILER IS CONNECTED DIRECTLY TO THE FLUE PIPE OF SIMILAR SIZE INSTALLED ON BOILER #1. CUMMULATIVE FL #32048823M | Feb 3, 2006 IN VIOLATION | $0 |
| Nov 2, 2005 | Boilers Non-Hazardous 50. A.O SMITH COIL W.T. BOILER LP/HWS 50 PRESSURE RELIEF VALVE IS MOUNTED AT THE LOWEST ELEVATION ON THE BOILER. RE-POSITION THE PRESSURE RELIEF VALVE AT A HIGH ELEVATION ON THE BOILER FOR CODE COMPLIANCE. #32048826H | Jan 20, 2006 IN VIOLATION | $0 |
| Nov 2, 2005 | Boilers Non-Hazardous A.O SMITH COIL W.T. LP HOT WTR BLR GAS. 50 PRESSURE RELIEF VALVE IS MOUNTED AT THE LOWEST ELEVATION ON THE BOILER STRUCTURE. RE-POSITION THE PRESSURE RELIEF VALVE AT A HIGH ELEVATION ON THE BOILER FOR CODE COMP #32048824Y | Jan 20, 2006 IN VIOLATION | $0 |
| Issued | Violation | Status |
|---|---|---|
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00394 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION #00422 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION #00421 | DOB VIOLATION - ACTIVE |
| Mar 16, 2020 | HIGH PRESSURE BOILER VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION #00395 | DOB VIOLATION - ACTIVE |
| Jun 22, 2018 | HIGH PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE 2016 ANNUAL HIGH PRESSURE BOILER INSPECTION #00112 | DOB VIOLATION - ACTIVE |
| Jun 23, 2017 | HIGH PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE 2015 ANNUAL HIGH PRESSURE BOILER INSPECTION #00142 | DOB VIOLATION - ACTIVE |
| Mar 1, 2013 | LOW PRESSURE BOILER VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2011 INSPECTION REPORT #04610 | DOB VIOLATION - ACTIVE |
| Mar 26, 2002 | LOCAL LAW 62/91 - BOILERS #11844 | DOB VIOLATION - ACTIVE |
| Feb 27, 2001 | LOCAL LAW 62/91 - BOILERS #10896 | DOB VIOLATION - ACTIVE |
| Feb 7, 2000 | LOCAL LAW 62/91 - BOILERS #11429 | DOB VIOLATION - ACTIVE |
| Issued | Violation | Status |
|---|---|---|
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 INTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 16, 2020 | Boiler HBLVIO VIOLATION ISSUED - FAILURE TO FILE 2017 EXTERNAL HIGH PRESSURE BOILER INSPECTION | Active |
| Jun 22, 2018 | Boiler HBLVIO VIOLATION ISSUED FOR FAILURE TO FILE 2016 ANNUAL HIGH PRESSURE BOILER INSPECTION | Active |
| Jun 23, 2017 | Boiler HBLVIO VIOLATION ISSUED FOR FAILURE TO FILE 2015 ANNUAL HIGH PRESSURE BOILER INSPECTION | Active |
| Mar 1, 2013 | Boiler LBLVIO VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2011 INSPECTION REPORT | Active |
| Mar 26, 2002 | Boiler LL6291 | Active |
| Feb 27, 2001 | Boiler LL6291 | Active |
| Feb 7, 2000 | Boiler LL6291 | Active |
None open.
Always confirm on the city's own systems before acting: DOB BIS property profile · DOB NOW · HPD Online · Pay ECB/OATH penalties (CityPay)
City records as of Oct 28, 2026, 4:25 PM ET. BBL 2033440012.